HomeMy WebLinkAbout26829AGENDA
REGULAR MEETING OF
AZUSA UTILITY BOARD/AZUSA CITY COUNCIL
AZUSA LIGHT & WATER
729 N. AZUSA AVENUE
AZUSA, CA 91702
I
AZUSA UTILITY BOARD
URIEL E. MACIAS
CHAIRPERSON
ROBERT GONZALES
VICE CHAIRPERSON
KEITH HANKS
BOARIO MEMBER
i
SEPTEMBER 28, 2009
6:30 P.M.
JOSEPH R. ROCHA
BOARD MEMBER
ANGEL CARRILLO
BOARD MEMBER
6:30 P.M. Convene to Regular Meeting of the Azusa Utility Board and Azusa City Council
l • Call to Order
•
Pledge to the Flag
• Roll Call
A. PUBLIC PARTICIPATION
(Person/Group shall be allowed to speak without interruption up to five (S) minutes maximum time,
subject to compliance with applicable meeting rules. Questions to the speaker or responses to the
speaker's questions or comments shall be handled after the speaker has completed his/her comments.
Public Participation will be limited to sixty (60) minutes time.)
�
�.
B. CONSENT CALENDAR
The Consent Calendar adopting the printed recommended action will be enacted with one vote. If Staff or
Councilmembers wish to address any item on the Consent Calendar individually, it will be considered under
SPECLIL CALL ITEMS.
Minutes. Recommendation: Approve minutes of regular meeting on July 27, 2009 as written.
July 27 Minutes.pdf
2. Approval of Extension of Civiltec Design Contract for Project WF -221. Recommendation:
Approve the extension of contract of Civiltec Engineers, Incorporated for Project WF -221, South
Reservoir demolition and replacement, from June 30, 2009 to December 31, 2009.
w
CNhec Contract
Extension. pdf
Recommendation: Approve additional compensation for Hall & Foreman, Incorporated for Project W-
265, engineering design services for pipeline replacement, in amount of $24,950.
U i
--
CO to Hag &
H&F Exhibit. pdf
Forenen. pdf
4. Approval of Additional Compensation for Black & Veatch for Proiect WVF-207.
Recommendation: Approve additional compensation to Black & Veatch for additional compensation for
construction management engineering services for Project WVF-207, Canyon Membrane Water
Treatment Plant (WTP) upgrade and expansion, in amount of $43,700.
i
CO for Blick & B&V CO Exhibit. pdf
Veatch. pdf
Opt
1
i !
I
II
t
3.
4.
SCHEDULED ITEMS
Approval of Request for Proposals (RFP) for Power Supply Study. Recommendation: Approve
statement of work for a power supply study and authorize staff to issue RFP for the study.
Power Suppy
RFP. pdf
Approval of Change Order for SSC Construction, Incorporated for Project WVF-207.
Recommendation: Approve Change Order No. 15 for additional compensation and time to SSC
Construction, Incorporated for additional work required for Project WVF-207, Canyon Filtration Plant
Membrane Treatment upgrade and expansion project, in amount of $82,412.25.
STAFF REPORTSICOMMUNICATIONS
Consumer Service Customer Identification Theft Prevention Annual Update
ID Theft Prev
Rpt. pdf
San Juan Fuel Cost Adjustment
Legislative
Govr E.O.pdf
SSC CO. pdf
SSC C015
Exhibit.pdf
STAFF REPORTSICOMMUNICATIONS
Consumer Service Customer Identification Theft Prevention Annual Update
ID Theft Prev
Rpt. pdf
San Juan Fuel Cost Adjustment
Basin Water Supply and Key Well Elevation Update (Verbal)
Legislative Update
Legislative
Govr E.O.pdf
San Juan FCA.pdf
San Juan FCA
Exhibd. pdf
Basin Water Supply and Key Well Elevation Update (Verbal)
Legislative Update
003
Legislative
Govr E.O.pdf
Update.pdf
003
5. Solid Waste Recycling Programs Update
E. DIRECTORS' COMMENTS
F. ADJOURNMENT
1. Adjournment.
"In compliance with the Americans with Disabilities Act, if you need special assistance to participate in a city
meeting, please contact the City Clerk at 626-812-5229. Notification three (3) working days prior to the
meeting or time when special services are needed will assist staff in assuring that reasonable arrangements
can be made to provide access to the meeting."
"In compliance with Government Code Section 54957.5, agenda materials are available for inspection by
members of the public at the following locations: Azusa City Clerk's Office - 213 E. Foothill Boulevard,
Azusa City Library - 729 N. Dalton Avenue, and Azusa Light & Water -729 N. Azusa Avenue, Azusa CA. "
4 004
t
Recycling Prograr s
Program Stats
Update. pdf
Exhibit. pdf
E. DIRECTORS' COMMENTS
F. ADJOURNMENT
1. Adjournment.
"In compliance with the Americans with Disabilities Act, if you need special assistance to participate in a city
meeting, please contact the City Clerk at 626-812-5229. Notification three (3) working days prior to the
meeting or time when special services are needed will assist staff in assuring that reasonable arrangements
can be made to provide access to the meeting."
"In compliance with Government Code Section 54957.5, agenda materials are available for inspection by
members of the public at the following locations: Azusa City Clerk's Office - 213 E. Foothill Boulevard,
Azusa City Library - 729 N. Dalton Avenue, and Azusa Light & Water -729 N. Azusa Avenue, Azusa CA. "
4 004
CITY OF AZUSA
MINUTES OF THE REGULAR MEETING
OF THE AZUSA UTILITY BOARD/CITY COUNCIL.
MONDAY, JULY 27, 2009 — 6:30 P.M.
The Utility Board/City Council of the City of Azusa met at the above date and time, at the Azusa Light and
Water Conference Room, located at 729 N. Azusa Avenue, Azusa, California.
Vice Chairman Gonzales called the meeting to order. Call to Order
Cary Kalscheuer, Assistant to Utilities Director, led in the Flag Salute. Flag Salute.
ROLL CALL Roll Call
PRESENT: BOARD MEMBERS: GONZALES, CARRILLO, HANKS, ROCHA
ABSENT: BOARD MEMBERS: MACIAS
ALSO PRESENT: Also Present
City Attorney Ferre, City Manager Delach, Assistant City Manager Makshanoff, Interim Director of
Utilities Tang, Assistant to Utilities Director Kalscheuer, Assistant Director Customer Care and Solutions
' Vanca, Director of Public Works/Assistant City Manager Haes, Assistant Director of Water Operations
Anderson, Public Information Officer Quiroz, Operations Captain Momot, Sr. Electric Engineer Langit,
Storekmper Alvarez, City Clerk Mendoza, Administrative Technician Hernandez.
PUBLIC PARTICIPATION Pub Part
Mr. Mike Lee commended all who participated in the Korean Armistice Day Celebration and thanked all
M. Lee
who attended; he spoke about Planning Commission positions, and asked council to reconsider the possible
comments
review and/or re -appointment of the current commissioners.
Mr. Jorge Rosales asked Boardmembers if the loan that the Redevelopment Agency acquired from the City
J. Rosales
on March of 2008, has been paid.
comments
f
r Ms. Stephanie Mills expressed her opposition to the possible review and/or re -appointment of the current
S. Mills
Planning Commissioners.
comments
The CONSENT CALENDAR consisting of Items B-1 through B-3, was approved by motion of Board Consent Cal
Member Carrillo, seconded by Board Member Hanks and unanimously carried.* apvd.
The minutes of the regular meeting of June 22, 2009, were approved as written. Min appvd
005
2. Approval was given for a License Agreement with Power Settlements Consulting and Software, LLC. Lic Agmnt
and the Mayor was authorized to execute said agreement. Power Settlmnt
A RESOLUTION OF THE AZUSA UTILITY BOARD/CITY COUNCIL OF THE CITY OF Res. 09-C68
AZUSA, COMMITTING TO MATCH ANY GRANT FUNDS THAT MAY BE AWARDED BY matching
THE U.S. DEPARTMENT OF ENERGY FOR A SMART GRID PROJECT IN THE CITY OF funds
AZUSA UP TO ONE MILLION DOLLARS.
Sched Items
Board Member Rocha addressed the item regarding Annual Water Rights Transactions, questioning the Water .
dates of the closing of the agreement to be on June 30, 2009. Rights
Transactions
Interim Utilities Director Tang, explained that water lease is an accounting exercise administered by Water
Master and is done before the end of each fiscal year; between June 15 and June 30, is when the water lease
is transferred, this agreement is structured between that time. The request for approval is for ratification of
the agreement, and to adopt resolution to authorize staff to engage in discussion with outside entities.
After light discussion was held, it was moved by Board Member Carrillo, seconded by Board Member
Hanks and unanimously carried* to Ratify the execution of the water rights lease agreement with the City of
Arcadia.
Board Member Carrillo offered a Resolution entitled:
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF AZUSA, CALIFORNIA, ADOPTING A
POLICY AUTHORIZING THE CITY MANAGER OR HIS DESIGNEE TO ENTER INTO
REPLACEMENT WATER AGREEMENTS AND PRODUCTION RIGHT AGREEMENTS.
Moved by Board Member Carrillo, seconded by Board Member Hanks and unanimously carried to waive
further reading and adopt. Resolution passed and adopted by the following vote of the Board.
AYES: BOARD MEMBERS:,
NOES: BOARD MEMBERS:
ABSENT: BOARD MEMBERS:
STAFF REPORTS/COMMUNICATIONS
GONZALES, CARRILLO, HANKS, ROCHA
NONE
MACIAS
Res. 09-C69
Replacement
Water
Agreements
& Prod Rights
Staff Rpts
Interim Director of Utilities Tang presented a follow up report from Ms. Susanne Avila, regarding the
CRC
California Resources Connection (CRC) agreement, for river walk and compost workshops. This report is
Report
part of the agreement with CRC, and is required to provide to the City, pursuant to the City's funding
support for the events.
Interim Director of Utilities Tang presented information regarding Power Resources Projects: The Lodi
Update
Energy Center is an ongoing agreement; however, the Preliminary Staff Assessment it is facing delays in
on Power
getting approval by the California Energy Commission because of the backlog due to the employee's state
Resources
mandatory furlough. The Garnet Wind Project is now operating, after six months of testing. Staff is working
Projects
through Southern California Public Power Authority for ajoint application of ICE Bear technology; a device
that builds up ice during the off-peak hours, and releases the cooling during the summer afternoons; the city
library is currently using the ICE Bear unit.
Interim Director of Utilities Tang presented information on the Filtration Plant, which has been completed;
Update
staff has been engaged in intensive conditioning of the plant; due to the size of this project, the completion is
Water
complex, and before they begin operating it, they need to insure everything has been properly checked for
Filtration .
protections purposes. It is estimated to start operating on August 10.
Plant
07/27/09 PAGE TWO
Interim Director of Utilities Tang presented an information report answering questions that were posed by Update Report
Directors at the last Utility Board Meeting of June 22, regarding Customer Service Division's Lifeline Cust Svcs
Program, various billing practices, drop box message, customer count breakdown, and customer usage of
online payment features.
Interim Director of Utilities Tang presented information regarding Photo Voltaic Solar System Update for Photo Voltaic
Cardinal Laboratories; 3 years ago pursuant to State Legislation Azusa established distribution of solar Solar System
program for retail customers through Cardinal Laboratories. The expected rebate for Azusa is $336,600. It is
estimated to be completed by the end of this month with a ribbon cutting in mid September.
Interim Director of Utilities Tang presented information on Climate Change Legislation; H.R.2454 that was H.R. 2454
passed by the Federal House of Representatives; the Southern California municipal utilities including Azusa, Climate
has exposure to coal generations which is one of the main sources of green house gas, and even though this Change
legislation doesn't protect Azusa 100%, it is better than California AB 32. This new bill will give a Bill
reasonable transition period for a targeted reduction of green house gas, that goes to 2025, 2030, a 15 to 20
year life span. Another aspect favorable to Azusa is the "Cap -and -Trade" regulatory on allowances of
emissions. To buy allowances under the bill, Azusa should be able to get them at no cost as part of the
transition.
Interim Director of Utilities Tang presented an update on the San Gabriel Valley Municipal Water District's Promotion
Public Education Program to conserve water, which is being promoted by postings on bus shelters. water Conserv
Interim Director of Utilities Tang presented an update on Azusa's water supply, which seems to be Water
reasonable. Azusa's savings have been from 15% to 20%, compared to couple of years ago, if customers Patrol
continue to cooperate in saving water, Azusa should be able to make it through summer and fall. There is update
concern on enforcement due to the high heat. Water patrol units have been reinstated during weekends until
the end of September.
Vice Chairman Gonzales, thanked City staff and Los Angeles County staff, for the Morris Dam tour, which
was very educational.
City Manager Delach responded to question posed at public participation regarding the loan that
Redevelopment Agency acquired from the City, stating that due to delay on property sales, the payment of
the nob: has also been delayed, and it is estimated that action on the note will begin September or October.
Moved by Board Member Gonzales, seconded by Board Member Carrillo and unanimously carried* to Adjourn
adjourn the Utility Board Meeting in memory of Mr. Richard "Dick" Stanford, former Councilmember, who in memory
passed away earlier today. of D. Stanford
TIME OF ADJOURNMENT: 7:07** P.M.
SECRETARY
NEXT RESOLUTION NO. 09-C70.
*Denotes Chairman Macias absent.
** A special meeting of the City Council and the Redevelopment Agency was held immediately following a
15 minute recess.
j 07/27/09 PAGE THREE
007
CONSENT CALENDAR
TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD AND AZUSA CITY COUNCIL
FROM: GEORGE F. MORROW, DIRECTOR OF UTILITIES
DATE: SEPTEMBER 28, 2009
SUBJECT: EXTENSION OF TIME TO CIVILTEC ENGINEERS' CONTRACT FOR
DESIGN OF PROJECT WF -221 SOUTH RESERVOIR DEMOLITION AND
REPLACEMENT
RECOMMENDATION
It is recommended that the Utility Board/City Council approve the extension of Civiltec
Engineers' contract for engineering design services for the South Reservoir Demolition and
Replacement Project WF -221 from June 30, 2009 to December 31, 2009.
BACKGROUND
At its regular meeting held October 27, 2008, the Utility Board/City Council approved the award
of a contract for consultant engineering design services for the South Reservoir Demolition and
Replacement Project to Civiltec Engineers. Civiltec's contract terminated on June 30, 2009.
Because Civiltec has not yet completed the design of Projeci WF -221, it is necessary to extend
the termination date of June 30, 2009 to December 31, 2009.
Staff has reviewed the provision of a time extension for Civiltec and finds it to be acceptable.
This is presently not a time sensitive project for ALW.
FISCAL IMPACT
There is no fiscal impact from the extension of time of this contract.
Prepared by:
Chet Anderson, Assistant Director - Water Operations
11:
CONSENT CALENDAR
TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD AND AZUSA CITY COUNCIL
FROM: GEORGE F. MORROW, DIRECTOR OF UTILITIES
DATE: SEPTEMBER 28, 2009 4
SUBJECT: ADDITIONAL COMPENSATION TO HALL & FOREMAN, INC. FOR EXTRA
COST RELATED TO ADDITIONAL WORK FOR PIPELINE REPLACEMENT
PROJECT W-265 DESIGN ENGINEERING SERVICES
RECOMMENDATION
It is recommended that the Utility Board/City Council approve the addition of $24,950 to the
Hall & Foreman (H&F) contract to provide Design Engineering Services for Pipeline
Replacement Project W-265.
BACKGROUND
At its regular meeting of March 23, 2009, the Utility Board approved award of a contract for
consultant design services for Project W-265, Pipeline Replacement ($99,800).
Hall & Foreman's work on the project began in early July, 2009. During their pipeline design
work, it became clear that installing a portion of the pipeline as planned in existing rights of way
from Brookport Street in West Covina northerly between two houses to the Big Dalton Wash
storm drain channel north of the homes, was not practical.
As a result, it was necessary to choose a new alignment. The new alignment would connect
Brookport Street to Lark Ellen Avenue by running along the Big Dalton Wash storm drain
channel from Lark Ellen Avenue to Vincent. This would enable the new pipelines to connect to
the existing water system.
As a result of the realignment, Hall & Foreman incurred additional expenses ($24,950) as is
itemized in an attachment to this Staff Report. Staff has reviewed the proposed change order and
finds it to be reasonable.
FISCAL IMPACT
The fiscal impact of this additional cost is $24,950 (which is a 25% increase in the original:
design services contract amount). This request is the first addition to the scope and cost of Hall &.
Foreman's contract. This additional cost will be paid from Account 32-80-000-721-
7130/7210733-7130 in FY 2009-2010 capital improvement program budget.
Prepared by:
Chet Anderson, Assistant Director- Water Operations
010
Mr. Chet Anderson
Assistant Director, Water Operations
Azusa Light & Water
Second Floor Desk
729 N. Azusa Avenue
i
Azusa, CA 91702
i
Subject: Additional Services for Project No. W-265; Lark Ellen, Brookport St., Benwood
I
St., Benbow St., Vogue Av., Coney Ave., and Roxburgh Av.
Dear Mr. Anderson:
HFI is requesting additional compensation in the amount of $24,950 for changes to the contract
executed on May 18, 2009. The change in the Scope of Services includes the realignment of the new
18" transmission line within the project area and extending the design across the San Dimas channel
and the Big Dalton channel on Lark Ellen. The Scope of Services for the additional work is attached as
FAibit A. .
If you have any questions, please do not hesitate to call me directly at (714) 665-4516.
Sincerely,
I
Hall & Foreman, Inc.
Jon E. Bourgeois, P.E.
President/Principal
T4.1m
1778217" Street. SWR 2DD
Tusft CA 9 218 619 47
Tel 714.665.4500 . F 714.665.4SD1
I
swn cladw T.m Ia
25157 Spr rOdd CoUrk SWR 350 Three Beft . m Ord4 SuMe 100
Sena C wkk CA 917365465 TMK^ CA 925963745
Tel 661.2B4.7400 . Fax 661.284.7401 Tel 951.294.9300 . 951.7949301
a
14297 Goon Avenue. SWR 101
VldoMlle, CA 92392.2335
Td 760.524.9100 .760.524.9101
Oil
1:014:11030 �
SCOPE OF SERVICES
Water Main Improvement Project W-265
A. Additional Work Limits:
Lark Ellen Avenue: Bellbrook St to Big Dalton Wash
Prepare plan and profile design for the installation of 1000 -feet of 18"
pipeline in Lark Ellen Avenue. Project design will include the
elevated pipeline crossing at the Big Dalton Wash and San Dimas Wash.
Fee: $4,000
Cypress Street: Lark Ellen to 650' East
Prepare plan view construction sheet for the installation of new 8" water
line in frontage road north of Cypress Street east of Lark Ellen.
Connection will be made at intersection of Lark Ellen and Cypress. This
new pipeline is required to alleviate cross zone connection in Cypress
Street and Vogue Avenue. This pipe segment was not in the RFP project
description.
Fee: $1,750
Vincent Avenue & Big Dalton Wash
Prepare plan view and construction details to abandon existing water line
from Vincent Avenue east to the 18" waterline within the Big Dalton
Wash right-of-way.
Fee: $1,500
Bellbrook Street: Coney Ave to Lark Ellen
Delete plan only preparation for the installation of 8" water main and
prepare plan and profile design for installation of 2200 -feet of 18" water
main. (2 sheets)
Fee $6,000
B. Surveying & Mapping
Complete ground survey topo for Lark Ellen north of Bellbrook St. Topo
will include location of street curbs, finish surface elevations, at grade
utility facilities and detail topo of access entrances to flood control
channel property.
Complete additional field survey of Vincent Avenue at Big Dalton Wash.
Topo will include location of street curbs and finish surface elevations,
and location of at grade utility facilities.
Fee: $4,000
012
I C. Permits
Submit and process Flood and Roadway encroachment permit
through County of Los Angeles Public Works for additional pipeline
crossing San Dimas Wash. Permit processing will include construction
details, and profile alignment crossing over existing flood control channels
at San Dimas Wash and Big Dalton Wash. Payment of all permit fees will
be paid for by Agency. Work does not include preparation of easements
or licensing agreements.
Fee: $3,500
D. Utility Research & Coordination
Contact utility Agencies to request Atlas maps of new project limits. Plot
utility alignments on plans and show conflicts with new pipelines.
Provide notification to utility agencies on plan design and potential
relocation requests.
Fee: $1,000
f E.. Traffic Control Plans
Prepare traffic control and phasing plans for the pipeline construction in
Lark Ellen and Cypress. Plans will be prepared in accordance with
Caltrans Traffic Control Manual, and MUTCD requirements and
processed as part of the LA County Road Permit. Plans will include
required signage, traffic control devices, and work area limits.
Fee: $3,200
Total Fees Requested for Additional Work under Change Order No.l: $24,950
013
I
�I
AZUSA
UGHT R 'NATER
CONSENT CALENDAR
TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD AND AZUSA CITY COUNCIL
FROM: GEORGE F. MORROW, DIRECTOR OF UTILITIE
DATE: SEPTEMBER 28, 2009
SUBJECT: ADDITIONAL COMPENSATION TO BLACK & VEATCH FOR EXTRA COST
RELATED TO ADDITIONAL WORK FOR THE CANYON MEMBRANE
WATER TREATMENT PLANT UPGRADE AND EXPANSION PROJECT
CONSTRUCTION MANAGEMENT ENGINEERING SERVICES
RECOMMENDATION
It is recommended that the Utility Board/City Council approve the addition of $43,700 to the
Black & Veatch (B&V) contract to provide Construction Management Engineering Services for
Canyon Membrane Water Treatment Plant (WTP) Upgrade and Expansion Project, project
W VF -207.
At its regular meeting of November 20, 2006, the City Council approved the award of the
contract for consultant construction management services for the membrane treatment upgrade
and expansion of the Canyon Filtration Plant to Black & Veatch for an estimated cost of
$1,147,000. The construction of the plant improvements began January 29, 2007, however, the
completion of the project extended beyond the adjusted project completion date of December 17,
2008. During the course of the project, a number of additions and changes to B&V's Scope of
Services were necessary for the prosecution of the construction project and amendments to the
contract were reviewed/approved by Utility Board on July 28, 2008 ($326,800) and on April 27,
2009 ($102,000) in conjunction with an extension of the expected Completion Date to April 30,
2009. As a result, Black & Veatch's total contract is $1,575,800.
TI -Re project achieved Substantial Completion on July 15, 2009 and SSC has been doing startup
adjustments and minor finishing work since then. Because the project completion has extended
beyond April 30, 2009, B&V incurred additional expenses for project management work. As a
result, B&V submitted a contract change request in the amount of $43,700 for those additional
costs.
014
Attached is a letter from Black & Veatch documenting its change order request. Staff reviewed
this request, including a fee reduction to reimburse ALW for costs it incurred when the restrooms
had to be modified to meet California ADA requirements, and finds it to be reasonable.
FISCAL IMPACT
The fiscal impact of this additional cost is $43,700 which represents an additional 2.8170 to the
final cost of Black & Veatch's original construction services contract. Total additions to the
Black & Veatch contract to date are $472,500 (41.2% of original cost); final adjusted contract
cost is $1,619,500. This additional cost will be paid from Account 32-80-000-721-7130/72107C-
7130.
Prepared by:
Chet Anderson, Assistant Director- Water Operations
015
a®
BLACK & VEATCH
t 15615 Alton Parkway, Suite 300
Irvine, California 92618
( rel: (949) 753-0500
Fax: (949) 753-1252
Azusa Light and Water
Canyon Filtration Plant Membrane Treatment Upgrade
and Expansion Project
Mr. Chet Anderson, P.E.
Assistant Director of Utilities — Water Operations
Azusa Light and Water
I' '729 N. Azusa Ave.
Azusa, CA 91702
Dear Mr. Anderson:
Black & Veatch Corporation
B&V Project 140777
B&V File A.2
September 14, 2009
Subject: Engineering Amendment Request
As a follow-up to our discussion on Thursday, September 10, 2009, we are sending this letter
requesting an amendment to our engineering services budget for the Canyon Filtration Plant
]Membrane Treatment Upgrade and Expansion project.
:Project Status
The Canyon Filtration Plant Membrane Treatment Upgrade and Expansion project reached
substantial completion on July 15, 2009 and the plant has been in operation for several weeks. A
punch list was generated in July 2009 and SSC has addressed most of the items on the punch list.
A project status meeting was held on September 10, 2009 between ALW, SSC, and B&V to
discuss the outstanding items on the punch list and final closeout documentation. All items on
the punch list were discussed and addressed with an action plan. With the exception of three
items; potassium permanganate system, paving and alarm setpoint programming issue, all other
items were resolved. SSC is working on completing these items in an expedited manner. B&V
will work with SSC in the coming weeks to ensure that these items are complete.
16&V Engineering Budget Status and Out of Scope Services
The engineering services provided by the Black & Veatch team were performed in response to
the SSC's work. B&V received an amendment from ALW in April 2009 to perform the
engineering services through end of May 2009, which was the revised substantial completion
(late projected by SSC at the time the amendment request was approved. This amendment
included a part-time inspection (2 days a week) and project management time through the end of
May 2009. We expended our budget at the end of May 2009. Our actual 31 inspection days
through end of May exceeded the budgeted 22 inspection days because of the additional startup
activities and mechanical performance test. Please note that the additional inspection during
Black 8 Veatch Corporation - 15615 Alton Parkway, Suite 300 - Irvine, California 92618 USA - Telephone 949.753.0500 • Fax 949.753.1252
016
Azusa Light and Water B&V Project 140777
Canyon Filtration Plant Membrane Treatment Upgrade and Expansion File A.2
Engineering Amendment Request September 14, 2009
May was provided on a full time basis during the 7 day mechanical performance test which was
conducted over a span of two weeks to coincide with ALW's plant staff work schedule.
Since June to date, our services included the following activities:
Perform On -Site Inspection (Total 28 days)
Nine additional days in May as explained above
Eight inspection days in June
Six inspection days in July
Three inspection days in August
Two inspection days in September
These inspection activities were performed to inspect the outstanding items prior to Substantial
Completion in July and to inspect the final punch list items post Substantial Completion to date.
We don't anticipate requiring any additional inspection days on this project.
Project Management Activities (June 2009 to Sep 14, 2009)
These activities included the Project Manager and supporting staff's time for coordinating with
ALW and SSC with regards to construction and startup activities, and internal project
management and accounting activities. The following table provides a breakdown of the project
management activities performed during these months.
Name
Duties Performed
Hours Spent
June/Se 2009
Ashu Shirolkar, PM
. Attend project meeting with ALW (August 24,
45
2009)
. Coordination with contractor and Azusa Light
and Water
. Internal project management and accounting
Jake Holden, Project Engineer
. Coordination with Contractor and ALW,
60
. Office activities including review of
contractor's pay applications
Project Accounting Staff
. Tracking Budget
10
(Carmen Haynes, Mike Dowell,
. Preparing Draft and Final Invoices
Sara Beth Heaviland, Hazel
Boyd)
Project Administration Staff
. Project Administration Support
14
(Rashelle Smith, Cynthia
. Clerical Support
McIntire
Project Management Activities (Sep 14, 2009 to October 15, 2009)
As we work through the final project close-out documentation and completion of the punch list
items, we anticipate following activities will be required through the middle of October, 2009,
(expected project close-out date).
Project management activities including coordination with SSC and ALW with regards to
the project closeout. Review of final pay application will be performed.
It is anticipated that additional resident inspection will not be required on this project.
Page 2
017
Azusa Light and Water B&V Project 140777
Canyon Filtration Plant Membrane Treatment Upgrade and Expansion File A.2
Engineering Amendment Request September 14 2009
As part of this amendment request, ALW asked B&V to review the additional construction costs
incurred by ALW for the modifications needed to the O&M Building restroom in order to meet
the ADA requirements. B&V proposes a reduction in our amendment request to alleviate these
costs incurred by ALW. We have estimated the following hours and fee estimate for our
services from June 2009 through middle of October 2009 (projected final completion date).
Summary of Addifinnal Wnrk
Work
Performed
Part-time Resident Inspection
224
$31,300
(June -Sep 14,
2009)
Project Management Activities
129
$21,500
Resident Inspection
0
$0
New Work
(Sep 14—Oct.
Project Management (2 hours/week)
10
$1,600
E
Subtotal
363
$54,400
Fee Reduction
L
$10,700
Total Additional Budget Requested 1
$43,700
Page 3
1•
Azusa Light and Water B&V Project 140777
Canyon Filtration Plant Membrane Treatment Upgrade and Expansion File A.2
Engineering Amendment Request September 14, 2009
Summary
The final closeout for the project is expected to occur in mid-October. SSC is working on
addressing the remaining few punch list items and final project close-out documentation will be
issued in the upcoming week. B&V hereby requests an amendment to our engineering budget in
the amount of $43,700 for the additional work items summarized in this letter.
Please contact us if you have questions or require additional information.
Cc: Steve Foellmi, B&V
Jake Holden, B&V
B&V File
Very truly yours,
BLACK & VEATCH
Page 4
Ashu Shirolkar, P.E.
Project Manager
019
C 4F
AZUSA
AGENDAITEM
TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD AND AZUSA CITY COUNCIL
FROM: GEORGE MORROW, DIRECTOR OF UTILITIES
DATE: SEPTEMBER 28, 2009
SUBJECT: REQUEST FOR PROPOSALS FOR POWER SUPPLY STUDY
RECOMMENDATION
That the Utility Board/City Council approve the statement of work included in this report for a
power supply study and authorize staff to issue a request for proposals for the study.
BACKGROUND
Azusa Light & Water has not engaged in the development of a formal and comprehensive power
supply plan for a numberof years.
In the recent past, there have been numerous changes and developments in the electric utility
industry which have the potential to impact Azusa's power supply strategies and objectives. The
primary developments include the adoption of Assembly Bill 32 which established green house
gas (GHG) goals/restrictions for California and the implementation of an Executive Order signed
by the Governor of California on September 15, 2009 increasing renewable portfolio standards
(RPS) from 20% to 33% in 2020. Similar GHG and RPS legislation is pending at the Federal
level.
In addition, the retirement of Azusa's long-time Director of Utilities (Joe Hsu) and the
resignation of the organization's chief power supply planner (Bob Tang), as well as the
appointment of a new Director of Utilities on August 31, suggest that this may be an excellent
time to step back and review/assess the present power supply commitments of the electric utility
and to begin to formulate goals and strategies for the acquisition of new power resources in the
fulure.
020
Approval to Issue Request for Proposals for Power Supply Study
September 28, 2009
Page 2
Key items for statement of work for the Power Supply Study include the following:
• Review/document the utility's load forecast and recommend changes, if appropriate,
based on current conditions in the industry and the economy,
• Review/document the utility's current power supply commitments to include the form
and nature of such commitments, expected capacity and energy contributions and present
and future cost profiles projections,
• Review/document the utility's current electric transmission arrangements to include the
form and nature of such commitments and present/future cost projections,
• Evaluate the utility's proposed participation and participation level in the planned Lodi
Energy Center with respect to costs & benefits,
• Review/document the utility's current program/approach to purchase wholesale electric
capacity and energy to satisfy projected load obligations and as a hedge to future power
costs,
• Review/document the utility's current program/approach to acquire Congestion Revenue
Rights (CRR's) as a hedge against locational marginal prices (LMP's) within the
California Independent System Operation (CAISO) network,
• Review/document the utility's obligations to maintain Resource Adequacy (RA) and
Local Capacity Resources (LCR) pursuant to CAISO rules/guidelines,
• Review the utility's current power resources that qualify in meeting Renewable Energy
goals and provide input/recommendations regarding the future acquisition of RPS
qualified resources by Azusa,
• Review/document the utility's current Green House Gas "footprint" as well as
documenting the probable level or range of carbon reductions that will be required by the
utility to conform with the requirements of AB 32,
• Assess the utility's potential for demand-side management (DSM) and appropriately
integrate reasonably levels of same into the planning study
• Provide spreadsheet models prepared for the purposes of this study including load
forecast, power supply costs, RA and LCR capacity, RPS and GHG, and
• Develop a strategic vision/direction for power supply resources that can provide the
utility with a roadmap for considering/evaluating future power supply options.
This project could take 4 to 6 months to complete. The most time sensitive portion of the study
relates to the Lodi Energy Center (LEC). We would request an early review and report prior to
December 31, 2009 on this project which should be consistent with the commitment deadline for
LEC.
FISCAL IMPACT
The cost of this study will be reported to the Utility Board following receipt of proposals from
qualified consulting firms.
Prepared by:
George Morrow, Director of Utilities
021
� P
AZLJSA
UGMf R WATIt
AGENDA ITEM
TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
! BOARD AND AZUSA CITY COUNCIL
I
FROM: GEORGE F. MORROW, DIRECTOR OF UTILITIES
DATE: FEBRUARY 28, 2009
j SUBJECT: APPROVAL OF CHANGE ORDER PROVIDING ADDITIONAL
f COMPENSATION AND TIME TO SSC CONSTRUCTION, INC. FOR
AGGREGATED ADDITIONAL WORK REQUIRED ON PROJECT WVF-207
CANYON FILTRATION PLANT MEMBRANE TREATMENT UPGRADE AND
EXPANSION
RECOMMENDATION
It is recommended that the Utility Board/City Council approve Change Order No. 15 for the
addition of $82,412.25 and 108 days to the SSC Construction, Inc. contract for Project WVF-
207, Canyon Filtration Plant Membrane Treatment Upgrade and Expansion.
BACKGROUND
On November 20, 2006, the Azusa City Council accepted the bid of SSC Construction, Inc. to
construct Project WVF-207, Canyon Filtration Plant Membrane Treatment Upgrade and
Expansion.
Change Order No. 15 represents an aggregation of SSC Change Order Requests (COR) 13, 27,
35, 36, 37, 38, 39, 40, 41, and 42. Also included in this Change Order is a cost reduction offered
by SSC to settle the matter of time over the completion date and possible liquidated damages. An
overview of Change Order Requests 13, 27, 35, 36, 37, 38, 39, 40, 41, and 42 is provided below.
A detailed justification/ explanation of each COR is provided by reference to an attached Black
& Veatch letter and Change Order Form.
CHANGE ORDER REQUESTS
COR 13: O&M Building Permit Contract Time Extension and Additional Architectural Costs
Extra time spent awaiting a Building Permit plus minor architectural additions or revisions
resulted in extra costs. SSC has requested an additional $5,186.61 and a 91 calendar day
extension.
022
Change Order No. 15 to SSC Contract (Project WVF-207)
September 28, 2009
Page 2
COR 27: Special Inspection Charges
SSC incurred costs for Special Inspection for rebar, masonry, and structural steel that were not
SSC's responsibility to provide at their own cost. SSC has requested reimbursement of
$77,116.80.
COR 35: Membrane Building Blower Air
The blower air piping for the membrane system was installed by SSC using steel pipe per the
specification. The City's supplier of the membrane system, Siemens, requested that the piping be
changed to stainless steel pipe. SSC is requesting reimbursement of $38,960.42, the difference in
cost between stainless steel piping and standard steel pipe.
COR 36: Membrane Building Compressed Air
The. compressed air piping for the membrane system was installed by SSC using carbon steel
pipe per the specification. The City's supplier of the membrane system, Siemens, requested that
the piping be changed to copper pipe. Siemens also requested the installation of air filters in
several locations. SSC is requesting reimbursement of $45,658.78, the difference in cost between
stainless steel piping and copper pipe, and a time extension of 10 calendar days.
COR 37: O&M Building City Inspection Corrections
City building inspector identified items to be corrected during final inspection. Among the items
were ADA compliant toilets and signage, and GFI outlet in certain areas. SSC is requesting an
additional $11,394.37 for the modifications and a 7 calendar day time extension.
COR 38: Membrane Building Spandrel Beam
Pre-engineered spandrel beams were installed at an elevation that put them in conflict with
openings in the masonry walls for the HVAC ducts and louvers. The duct work had to be
modified to wrap around the spandrel beams. SSC has requested $9,294.22 for the modifications
to the ductwork and installation of the modified ductwork.
COR 39: Road widening per LACFD Plan Review Comments
LA County Fire Department reviewed the plant road plans and required the plant access road to
be widened from 20 feet to 26 feet in several locations, and also required two fire department
connections to be relocated. SSC has requested $27,222.97 for making the modifications
required by LA County Fire Department.
COR 40: New Circuits for Sample Pumps
Because the sample pump supplier could not guarantee a weather proof casing for the specified
pumps, an alternative pump was recommended. The alternative pumps also required dedicated
electric supply and breakers. SSC has requested $2,088.82 for these modifications.
CREDITS
1. Credit for deletion of tracer study (COR 41).
Staff operators determined the plant needs to be fine tuned over the next few months before
the tracer study is run. Because the tracer study would not be run as a part of their contract,
SSC is issuing a credit of $25,000 to ALW.
023
Change Order No. 15 to SSC Contract (Project WVF-207)
September 28, 2009
Page 3
2. Credit for deletion of sound survey allowance (COR 42).
An allowance was provided for SSC to install sound walls if a sound survey demonstrated that
sound walls were unnecessary. Because the sound walls were determined to be unnecessary,
SSC is issuing a credit a credit of $73,375.00 to ALW.
3. SSC Change Order Cost Reduction
Negotiations between ALW and SSC took place in which SSC offered a compromise of a
credit to the contract of $36,135.74 to resolve the issue of liquidated damages for delays.
The net total additional compensation requested by SSC is $82,412.25. The total additional time
requested is 108 Calendar Days. Staff has viewed each of SSC's change order requests and finds
them to be reasonable.
I
f
Including this Change Order, the final contract price for this project is $36,598,114.39 with
$692,614.39 in Change Orders. Change Orders for this contract represent 1.93% of the original
t contract price of $35,905,500.
i
FISCAL IMPACT
I This request has a fiscal impact of $82,412.25 to be funded from the capital improvement
j program budget account 32-80-721-000-7130/72107C-7130.
Prepared by:
Cliet Anderson, Assistant Director- Water Operations
1 024
BLACK & VEATCH
building a virorl d Gf diflerence-
ENERGY WATER INFORMATION GOVERNMENT
City of Azusa
Canyon Filtration Plant Membrane Treatment Upgrade and
Expansion
Mr. Chet Anderson, P.E.
Assistant Director of Utilities- Water Operations
Azusa Light & Water
729 N. Azusa Avenue, 2nd Floor
Azusa, CA 91702
Dear Mr. Anderson:
B&V Project 140777
B&V File 1.6
September 16, 2009
Subject: Change Order No. 15
Black & Veatch (B&V) is furnishing this letter as summary for the final change order for the
project, Change Order No. 15, which includes open SSC Change Order Requests (COAs), SSC's
COR cost reduction, and pending credits to ALW. A description of these items is provided and
SSC's document with regards to this final change order is attached.
1) Open SSC Change Order Requests:
COR 13: O&M Building Permit Contract Time Extension and Additional Architectural Costs
Obtaining a building permit was required for the O&M Building. SSC could not proceed with
the O&M Building construction until a permit was provided by the City of Azusa Building Plan
Check Department and approval was provided by the Los Angeles County Fire Department
(LACFD) Building Plan Check Unit. SSC has requested a 91 calendar day extension to the
contract for delays associated with receiving the 0&M Building Permit. In addition, minor
architectural additions/revisions resulted in $5,186.61 of additional costs. B&V has reviewed
Change Order Request (COR) 13 and recommends acceptance.
COR 27: Special Inspection Charges
SSC has requested reimbursement for costs incurred for Special Inspection services for rebar,
masonry, and structural steel performed by Converse Consulting during construction. Per
Specification 00700, Paragraph 13.03, the OWNER is responsible for costs associated with these
inspection services. The total reimbursement requested is $77,1 16,80. B&V has reviewed COR
27 and recommends acceptance.
COR 35: Membrane Building Blower Air
The blower air piping for the membrane system was installed as steel pipe per Specification
01630, pipe schedule. Per Siemens' recommendation, in order to prevent damage to the
membranes, this pipe had to be changed to stainless steel piping. SSC is requesting
reimbursement of $38,960.42 for the difference in material costs between steel pipe and stainless
steel pipe. B&V has reviewed COR 35 and recommends acceptance.
Blade & Veatch corporation • 15615 Alton Parkway, Suite 3DO •Twine, California 92618 USA - Telephone 949.753.D500 - Fax 949.753.1252
025
Azusa Light and Water B&V Project 140777
Canyon Filtration Plant Membrane Treatment Upgrade and Expansion File 1.6
Change Order No. 15
COR 36: Membrane Building Compressed Air
The compressed air piping for the membrane system was installed as carbon steel piping per
specifications. Upon commencement of system checkout, Siemens required all compressed air
piping for the membrane system to be copper due to concerns with flaking of steel pipe entering
the air process and subsequently damaging the membranes. In addition, installation of air filters
in several locations was required to satisfy Siemens requirements. The total cost for these
modifications was $45,658.78. SSC has requested a 10 day extension to the contract. duration for
completion of this work. B&V has reviewed Change Order No. 36 and recommends
acceptance.
_ COR 37: O&M Building City Inspection Corrections
The city building inspector identified items to be corrected during the final inspection. These
items included modifications to the men's and women's room toilets, converting the
maintenance garage receptacles to GFI outlets, adding ADA signage, and adding covers for the
maintenance shop lights. The total cost for these modifications was $11,394.37. SSC has
requested a 7 day extension to the contract duration for completion of this work. B&V has
reviewed COR 37 and recommends acceptance.
COR 38: Membrane Building Spandrel Beam
The pre-engineered spandrel beams in the Membrane Building were installed at an elevation
such that they interfered with the openings in the masonry walls for the HVAC ducts and
louvers. Prior to installation, the duct work was modified such that it split and wrapped around
the spandrel beams. The total cost for these modifications and the modified installation was
$9,294.22. B&V has reviewed COR 38 and recommends acceptance.
COR 39: Road Widening per LACFD Plan Review Comments
The Los Angeles County Fire Department reviewed the plans and required the plant access road
to be widened from 20 feet to 26 feet in several locations. In addition, they required relocation
of two fire department connections and associated piping. The total cost for these modifications
was $27,222.97. B&V has reviewed COR 39 and recommends acceptance.
COR 40: New Circuits for Sample Pumps
During the sample pump submittal process, it was determined that the pump supplier could not
guarantee a weather proof motor casing for the pumps specified. B&V recommended an
alternative sample pump from a different manufacturer that was guaranteed to be weather proof.
The new sample pumps had larger horsepower requirements than the original pumps. The
additional horsepower required dedicated cable and a breaker for each pump that previously
shared power with the water quality stations. The total cost for these modifications was
$2,088.82. B&V has reviewed COR 40 and recommends acceptance.
)BU
Azusa Light and Water B&V Project 140777
Canyon Filtration Plant Membrane Treatment Upgrade and Expansion File 1.6
Change Order No. 15
Summary of Open SSC Change Order Requests
Open.C.QR
COR 13
1
lding Permit Contract Time Extension and
Architectural Costs
$5,186.61
COR 27
ection Chares
$77,116.80
COR 35
tAdditional
Buildin Blower Air
$38,960.42
COR 36
to the Membrane Building Compressed Air
ired b Siemens
$45,658.78
COR 37
din City Inspection Corrections
$11,394.37
COR 38
Membrane Building Spandrel Beam
$9,294.22
COR 39
Los Angeles County Fire Department Plan Review
Corrections
$27,222.97
COR 40
New Circuits for Sample Pumps
$2,088.82
TOTAL
$216,922.99
2) Tracer Study Credit:
SSC is proposing to provide a credit of $25,000 to ALW for the tracer study purchase order
they've contracted with a third party company. Per DPH guidelines, the tracer study must be
performed within a year of permit issuance at the required flow rate of 12 MGD. ALW has
noted they would like to fine-tune plant operations at the required flow rate prior to conducting
the tracer study.
3) Sound Survey Allowance Credit:
An allowance of $75,000 was issued in the bid documents for the contractor to conduct a sound
survey for the plant and implement any mitigation measures. The results of the sound survey
indicated sound reduction mitigation measures were not required. Of the $75,000 designated,
SSC spent $1625.00 to perform the sound survey, resulting in a credit to ALW of $73,375.00.
4) SSC Chance Order Cost Reduction:
As part of the negotiation process, SSC has agreed to deduct contractor markups and labor costs
from their CORS under Item I above. The total reduction offered is $36,135.74. After the
meeting on September 10 and follow-up conversations, SSC and ALW have both agreed to
forego pursuing costs associated with approved time extensions and delay to the construction
schedule. As a result the contractual final completion date agreed upon is September 28, 2009.
With the acceptance of this offer by ALW, SSC will also sign a document waiving any and all
rights to making an extended overhead claim.
027
i
Azusa Light and Water B&V Project 140777
Canyon Filtration Plant Membrane Treatment Upgrade and Expansion File 1.6
Chance Order No. 15
Summary'
As shown below, the final change order request amount offered by SSC to close out the project is
$82,412.25. B&V recommends approval of this addition to the contract price.
Open CORS $216,922.99
Tracer Study Credit -$25,000
Sound Survey Allowance Credit -$73,375.00
SSC COR Cost Reduction -$36,135.74
Final COR Amount Offered by SSC to Close Out Project $82,412.25
Please feel free to contact us should you have any questions or require additional information.
0
Very truly yours,
BLACK & VEATCH
I•- yG'
Ashu Shirolkar, P.E.
Project Manager
M-1
AZUSA LIGHT AND WATER
CHANGE ORDER
Order No. 15
Date September 16, 2009
Agreement Date January 17, 2007
Sheet I of 4
Owner: Azusa Light and Water
Project: Canyon Filtration Plant Uparade and Expansion
Contractor: SSC Construction Inc.
The following changes are hereby made to the Contract Documents:
ADD DEDUCT
I.
O&M Building Permit Contract Time Extension and Additional
$5,186.61
Architectural Costs
(Reference SSC Change Order Request 13)
2.
Special Inspection Charges
$77,116.80
(Reference SSC Change Order Request 27)
3.
Membrane Building Blower Air
$38,960.42
(Reference SSC Change Order Request 35)
4.
Revisions to the Membrane Building Compressed Air Lines
$45,658.78
Required by Siemens
(Reference SSC Change Order Request 36)
5.
O&M Building City Inspection Corrections
$11,394.37
(Reference SSC Change Order Request 37)
6.
Membrane Building Spandrel Beam
$9;294.22
(Reference SSC Change Order Request 38)
7.
Los Angeles County Fire Department Plan Review Corrections
$27,222.97
(Reference SSC Change Order Request 39)
8.
New Circuits for Sample Pumps
$2,088.82
(Reference SSC Change Order Request 40)
9.
Tracer Study (Credit)
425,000.00
(Reference SSC Change Order Request 41)
10.
Sound Survey (Credit)
-$73,375.00
(Reference SSC Change Order Request 42)
11.
SSC Change Order Request Cost Reduction
-$36,135.74
NET COR AMOUNT (ADD)
$82,412.25
029
Justification
1. (Reference SSC Change Order Request 13) Obtaining a building permit was required for the
j O&M Building. SSC could not proceed with the O&M Building constriction until a permit
was provided by the City of Azusa Building Plan Check Department and approval was
provided by the Los Angeles County Fire Department (LACFD) Building Plan Check Unit.
2. (Reference SSC Change Order Request 27) SSC has requested reimbursement for costs
incurred for Special Inspection services for rebar, masonry, and structural steel performed by
Converse Consulting during construction. Per Specification 00700, Paragraph 13.03, the
OWNER is responsible for costs associated with these inspection services.
_ 3. (Reference SSC Change Order Request 35) The blower air piping for the membrane system
f was installed as steel pipe per Specification 01630, pipe schedule. Per Siemens'
j recommendation, in order to prevent damage to the membranes, this pipe had to be changed
If to stainless steel piping. SSC is requesting reimbursement for the difference in material costs
between steel pipe and stainless steel pipe.
4. (Reference SSC Change Order Request 36) SSC installed carbon steel piping for the
compressed air lines in the Membrane Building as required per specifications. Upon
commencement of system checkout, Siemens required all compressed air piping for the
membrane system to be copper and required air filters in several locations.
5. (Reference SSC Change Order Request 37) The city building inspector identified items to be
corrected during the final inspection. These items included modifications to the restroom
toilets, converting maintenance garage receptacles to GFI outlets, adding ADA signage, and
adding covers for the maintenance shop lights.
6. (Reference SSC Change Order Request 38) The pre-engineered spandrel beams in the
Membrane Building were installed at an elevation such that they interfered with the openings
in the masonry walls for the HVAC ducts and louvers. Prior to installation, the duct work
was modified such that it split and wrapped around the spandrel beams. SSC is requesting
reimbursement for these modifications.
7. (Reference SSC Change Order Request 39) The Los Angeles County Fire Department
reviewed the plans and required the plant access road to be widened from 20 feet to 26 feet in
several locations. In addition, they required relocation of two fire department connections
and associatdd piping.
8. (Reference SSC Change Order Request 40) During the sample pump submittal process, it
was determined that the pump supplier could not guarantee a weather proof motor casing for
the pumps specified. New sample pumps were recommended that had larger horsepower
' requirements than the original pumps. The additional horsepower required dedicated cable
and a breaker for each pump that previously shared power with the water quality stations.
9. (Tracer Study Credit) SSC has obtained a purchase order for a third party tracer study
company. During a project meeting on 09/10/09 it was determined that SSC would credit the
030
purchase order amount to ALW and ALW would procure the services of the third party in the
future.
10. (Reference SSC Change Order Request 42 - CREDIT) SSC contracted a third party
company to conduct a sound survey as required in.the contract documents. The results of the
sound survey indicated mitigation measures would not be required of SSC. A credit of was
provided to ALW from SSC based on the amount allowed for in the specifications less the
costs of the sound survey.
11. (SSC Change Order Cost Reduction) As part of the negotiation process, SSC has agreed to
deduct contractor markups and labor costs from their CORS under Item 1 above. After the
meeting on September 10 and follow-up conversations, SSC and ALW have both agreed to
forego pursuing costs associated with approved time extensions and delay to the construction
schedule. As a result the contractual final completion date agreed upon is September 28,
2009. With the acceptance of this offer by ALW, SSC will also sign a document waiving
any and all rights to making an extended overhead claim.
031
i
e j
3
SUMMARY
Change Orders
CHANGE TO CONTRACT PRICE
Original Contract Price
Current Contract Price Adjusted
By Previous Change Order(s)
Contract Price due to this
Change Order will be (increased)
New Contract Price, Including this Change Order
CHANGE TO CONTRACT TIME:
Contract Time Will Be Increased by
Date of Completion of All Work
APPROVED:
Owner: Azusa Light & Water
By:
Chet Anderson
Engineer: Black & Veatch
By; - - - ---
Ashu Shirolkar, Project Manager
$82,412.25 Add (Net)
$ 35,905,500.00
$ 36.515.702.15
$ 82.412.25
$ 36.598.114.40
(Calendar Days)
September 28; 2010
ri X -4
INFORMATION ITEM
TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD AND AZUSA CITY COUNCIL
FROM: GEORGE F. MORROW, DIRECTOR OF UTILITIE
DATE: SEPTEMBER 24, 2009
SUBJECT: ANNUAL UPDATE ON PROGRAM TO PROTECT CUSTOMER
IDENTIFICATION AND CREDIT INFORMATION IN COMPLIANCE WITH
THE FAIR CREDIT REPORTING ACT AND FAIR AND ACCURATE CREDIT
TRANSACTIONS ACT OF 2003
The Fair Credit and Reporting Act (FORA) required creditors to develop and implement an
Identity Theft Prevention Program by November 2008, with this date later extended to
November 1, 2009. All organizations that extend credit to consumers, including utility service
providers, must comply with this regulation which is intended to identify, mitigate, and prevent
identity theft. The Fair and Accurate Credit Transactions (FACT) Act required that creditors
conduct a risk assessment to determine whether customer accounts it maintains are subject to a
reasonably foreseeable risk of identity theft, whether that risk is to the customers or to the
creditor itself. In October 2008, the Utility Board approved Light & Water's Identity Theft
Prevention Program to protect customer identification and credit information.
The regulation focuses primarily on Red Flags. A Red Flag is defined as "a pattern, practice, or
specific activity that indicates the possible existence of identity theft." Employees with direct
access to customer information are to receive initial training and annual training updates.
Periodic reviews, conducted at least annually, are intended to assess the effectiveness of the
policies and procedures in light of any changes in identity risks to customers or to Azusa Light &
Water or to the City. The Director of Utilities provides oversight over the policies and
procedures, and Azusa Light & Water reports annually to the Utility Board on the program
effectiveness.
Over this past year the following occurred and/or deficiencies were noted and corrected:
1. Customer Service employees with access to customer information received an initial two-hour
training session with workbook and tips. Annual update training was provided in August 2009.
033
2. Access to the Information Technology server room located on the first floor of the Light &
Water building was secured and a separate door built for entry by the general staff to the adjacent
training and mail room.
3. For information privacy, Information Technology put passwords on Customer Service
computers and set screens to go dark after 10 minutes of inactivity. Users must enter their
passwords to regain access.
4. Systems & Software created and deployed a new method of source code control on our
customer information system server. The goal was to ensure that no programmer could alter the
production source code directly on any customer's server. Any source code updates now need to
be deployed via an automated system to ensure not only code consistency, but to also ensure
there is an audit trail should issues arise at a later date.
5. Customer Service vendors with access to customer identity information were requested to
confirm that they have taken all reasonable and necessary steps to safeguard name and social
security number and/or name and date of birth. All confirmed they are in compliance.
6. Lobby doors opening to the back office were secured with key entrances.
7. Locks were installed on selected cabinets so all staff can lock away papers and notebooks
with customer information.
8. Cross -shredders were purchased so sensitive customer information can be shredded
immediately. All other unneeded paper is shredded weekly.
The FY 2009-10 budget includes amounts for shredder replacements. Estimated costs are not to
exceed $3,000.
Prepared by:
Karen Vanca, Assistant Director Customer Care & Solutions
034
AZUSA
INFORMATIONAL ITEM
TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD AND AZUSA CITY COUNCIL
FROM: GEORGE MORROW, DIRECTOR OF UTILITIES
DATE: SEPTEMBER 28, 2009 '
SUBJECT: QUARTERLY FUEL COST ADJUSTMENT FOR SAN JUAN RESOURCE
On July 26, 2004, the Utility Board approved a fuel cost adjustment mechanism for San Juan
power plant. This mechanism is intended to credit customers with cost savings that are realized
when our power plant operates reliably and replacement power costs are avoided, and
conversely, allow the Utility to increase revenues to recover a portion of our replacement power
costs when the San Juan resource experiences outages.
This report encompasses replacement power costs incurred for the San Juan resource during the
period of June 16, 2009 through September 13, 2009. For reasons stated below, staff
recommends that NO Fuel Cost Adjustment be assessed on customer electric billings for the
period of October 1, 2009 through December 31, 2009.
The availability of the San Juan unit #3 during the period of June 16, 2009 through September
13, 2009 was 96%, higher than the budgeted availability of 85%. The average cost of
replacement power was $31.41/MWh as compared to the budgeted cost of $40/MWh, resulting
in a net credit of $307,673 for Fuel Cost Adjustment for the quarter, and when combined with
the carry over from the previous quarter of $32,016 it resulted in a total FCA credit of $275,657.
Normally, when FCA credits exceed $150,000 the amount would be credited back to customers
on their electric bills in the immediately following quarter. However, given the anticipated San
Juan replacement power costs in the second quarter of 2010 due to a planned San Juan unit 3
maintenance outage staff recommends the FCA credits be carried over to offset the foreseeable
la-rge San Juan FCA charges next year.
Prepared by:
George Morrow, Director of Utilities
Attachment
i sm
53 FCA Q4_09.xts
i
035
San Juan Fuel Cost Adjustment Calculation for Q4 2009
Actual SJ Output
Actual SJ Replac Energy Cost
Maximum Output
Unavailable SJ Output
% Outage Rate
Base SJ Output @ 85%
Unavailable SJ Output
% Outage Rate
Base SJ Replac Energy Cost @$40/MWh
Actual - Base SJ Replac Energy Cost
San Juan Insurance Premium Recovery
San Juan Insurance Payout
Cumulative Quarterly Difference (CQD)
Q3 2009 Carry -Over
If I(CQD)I<$100,000, then adjustment=0
If I(CQD)I>$750,000, then adjustment=+ -$750,000
or else adjustment = CQD
Forecast Retail Sales (MWh)
SJ FCA for Q4 2009 (cents/KWh)
(*) Through September 13th, 2009
June 16 -July
August
September*
32,009
20,894
9,3.14
$34,205
$45,669
$1,253
33,120
22,320
9;360
1,111
1,426
46
3.35%
6.39%
0.49%
28,152
18,972
7,956
4,968
3,348
1,404
15.00%
15.00%
15.00%
$198,720
$133,920
$56,160
-$164;515
-$88,251
-$54,907
$0
$0
$0
$0
$0
$0
-$307,673
$32,016
-$275,657
October November December
22,383 19,978 20,211
-0_44
$31.41
3.99%
INFORMATION ITEM
TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD AND AZUSA CITY COUNCIL
FROM: GEORGE MORROW, DIRECTOR OF UTILITIES
DATE: SEPTEMBER 28, 2009
SUBJECT: LEGISLATIVE UPDATE
During the 2009 calendar year, the Utility Board adopted various positions on state legislation
and advocated these positions in letters to state representatives. The deadline for the State
Legislature to approve bills this year was September 11, 2009. Bills that were not approved
became 2 -year bills and may be taken up next calendar year. Bills approved by the Legislature
were "Enrolled" for the Governor's signature. The Governor has until October l la' to sign bills
or veto them. Following shows status of bills Azusa Light & Water took positions on this
calendar year:
Bill No.
Subject
Status/Committee
Position
AB 49
Water Conservation — 20010 per capita
2 Yr Bill/Senate
Support
reduction
Appropriations
AB 64
Renewable Energy Requirement — 2091b
Enrolled
Oppose
by 2013; 26% by 2016 and 33% by 2020
(Implements SB 14)
AB 87
Prohibit Distribution of Free Plastic
2 Yr Bill/Assembly
Support if
Grocery Bags/Impose Fee
Appropriations
Amended
AB 222
Defined Biorefineries as Renewable
2 Yr Bill/Senate
Support
Energy Facilities
Environmental Quality
AB 479
Increase Waste Diversion Requirement
2 yr Bill/Senate
Oppose
on Cities to 60010 by 2015 and 75% by
Appropriations
2020
AB 1404
Cap of Greenhouse Gas Emission Offsets
Enrolled
Oppose
and Authorization for ARB to adopt
Administrative Fees
SB 14
Renewable Energy Requirement — 20%
Enrolled
Oppose
by 2013; 26% by 2016 and 33% by 2020
SB 25
Increase Waste Diversion Requirement
2 Yr Bill/Assembly
Oppose
on Cities to 60% by 2015 and 75% by
Natural Resource
2020; Mandatory Commercial Recycling
and Imposition of additional Landfill Fees
SB 488
Mandatory Reporting for Utilities that
Enrolled
Oppose
have Comparative Energy Usage
Disclosure Programs
SB 805
Renewable Energy Requirement — 20%
2 Yr Bill/Senate
Support
by 2013 and 33% by 2020
Appropriations
037
SB 14 and AB 64. Of the four noted bills currently enrolled, two would increase the renewable
portfolio standard (RPS) to 33% by 2020. While Azusa adopted a support position to increase its
RPS to 33% by 2020, SB 14 and AB 64 would limit the amount of renewable energy that could
be delivered from out of state resources. This aspect of both bills raised concern amongst
municipal electric utilities throughout California and caused our affiliate associations, such as
California Municipal Utilities Association (CMUA) and Southern California Public Power.
Authority (SCPPA), to oppose these bills.
Historically, it has been difficult to construct power generation in the State of California and so
some power generation facilities were built out-of-state and transmission infrastructure was
developed to import the energy. The transmission infrastructure is considered a valuable asset
and can be used to deliver renewable energy to the California market place. It is believed that
having access to out-of-state renewable energy can help lower cost in two ways, by providing'
competition and by making use of existing transmission infrastructure. The Governor appears to
share this perspective and is expected to veto SB 14 and AB 64.
In order to implement the 33% RPS requirement, the Governor signed Executive Order S-21-09
on September 15, 2009 (attached). The order directs the Air Resources Board (ARB) to develop
an RPS requirement of 33% by July 31, 2010, in cooperation with Public Utilities Commission.
and California Energy Commission. The last directive in the Executive Order reads: "The ARB
shall establish the highest priority for those resources that provide the greatest environmental
benefits with the least environmental costs and impacts on public health that can be developed
most quickly and that support reliable, efficient, cost-effective electricity system operations
including resources and facilities located throughout the Western Interconnection."
SB 488. After the City of Azusa sent its letter to Senator Pavley s office regarding SB 488,
Azusa was contacted by the Senator's office and certain objectionable language was removed'
from this bill. This effectively exempted Azusa from having to implement a program whereby
Azusa Light & Water would provide comparative electricity usage information to customers
through its utility bills. SB 488 was revised to now only require that utilities with comparative'
energy disclosure programs report the results of such programs to the State.
AB 1404. Existing law requires the ARB to adopt market based approaches to reduce;
greenhouse gas emissions. AB 1404 would impose a limit on the amount of emission reductions
that can be achieved using market based approaches to no more than 10% of greenhouse gas
emissions to be reduced during a reporting period. AB 1404 also authorizes ARB to adopt
administrative fees to pay for administration of this "offset" program. CMUA and SCPPA are.
requesting the Governor to veto AB 1404 to maximize the options available to achieve emission
reductions.
Prepared by:
Cary Kalscheuer, Assistant to the Director of Utilities
Office of the Govemor of the State of California
i
i
F�
Office of the Governor THE PEOPLE'S GOVERNOR
ARNOLD SCHWRRZENEGGER
%y
YYa:UIn
09/15/2009
WHEREAS the State of California is a world leader in efforts to reduce global warming and greenhouse gas emissions,
increase renewable energy production, promote energy efficiency and energy conservation, improve clean air and emissions
controls, expand the use of low carbon and alternative fuels and promote and commercialize new environmental technologies and
industries; and, -
WHEREAS producing electricity from renewable resources provides multiple and significant benefits to California's
environment and economy, including improving local air quality and public health, reducing global warming, diversifying our
energy supply, improving energy security, enhancing economic development and creating jobs; and
I WHEREAS California has and can access some of the best renewable energy resource areas in the world, providing
immense; potential for clean, valuable electricity generation, and the development of these resources must be accelerated and
maximized; and
I.
WHEREAS the Legislature enacted the California Global Warming Solutions Act of 2006 (Chapter 488, Statutes of 2006,
thereinafter "AB 32"), wherein the Legislature declared that global warming poses a serious threat to the environment of California
and created a comprehensive, multi-year program to reduce greenhouse gas emissions that cause global warming; and
WHEREAS AB 32 designated the Air Resources Board ("ARB") as the state agency charged with monitoring and regulating
sources of greenhouse gas emissions in California; and
WHEREAS among other requirements, AB 32 directs ARB to design emissions reduction measures, adopt regulations
requiring; the reporting and verification of greenhouse gas emissions, including accounting for greenhouse gas emissions from all
[electricity consumed in the state, and develop emissions reduction measures, including limits on emissions of greenhouse gases
applied to electricity and natural gas providers serving customers in California; and
WHEREAS substantially increased development of renewable energy, energy efficiency, and demand response are all
!heeded to meet the greenhouse reduction goal of 1990 levels by 2020 and 80 percent below 1990 levels by 2050, making the success
and expansion of renewable sources of energy a key priority for California's economic and environmental future; and
WHEREAS increased use of renewable electricity is one of the most promising means to reduce greenhouse gas emissions
in the transportation sector and meet California's 2050 greenhouse gas reduction goals; and
WHEREAS fostering greater and more timely renewable energy development requires a more cohesive and integrated
statewide strategy by California's energy and environmental agencies, including greater coordination and streamlining of the siting,
permitting and procurement processes for renewable energy generation, improving the manner in which California develops its
transmission infrastructure, and encouraging technically and economically feasible distributed renewable energy technologies; and
WHEREAS in 2002, Senate Bill 1078 added to Chapter 2.3 of Part I of Division 1 of the Public Utilities Code, a new
Article 16 (commencing with Section 399.11) establishing the California Renewable Portfolio Standard (RPS) Program, which
requires the State Energy Resources Conservation and Development Commission ("CEC") and the Public Utilities Commission
("PUC") to work collaboratively to implement the RPS Program; and
WHEREAS Senate Bill 1078 established a renewable energy standard and required electrical corporations to increase their
total procurement of eligible renewable energy resources by at least 1 percent per year so that 20 percent of their retail sales are
procured from eligible renewable energy resources by 2017; and
I
hnp://gov.ca.gov/index.php?/print-version/executive-order/13269/(I of3)92120095:25:21 PM 039
Office of the Govemor of the State of Cal ifornia
WHEREAS in 2003 Governor Schwarzenegger called for an acceleration of the RPS, urging that 20 percent of California's
electricity come from renewable sources by 2010 rather than 2017, seven years earlier than previously required, and this accelerated
standard became law in September 2006 when Governor Schwarzenegger signed Senate Bill 107; and
WHEREAS in 2003, the PUC and the CEC adopted the 2003 Energy Action Plan I, which accelerated the RPS 20 percent
renewable energy goal to 2010; and
WHEREAS in 2006 Senate Bill 107 and.Senate Bill 1036 further defined the roles and responsibilities of the CEC and PUC
and accelerated the implementation of the RPS; and
WHEREAS as stated in Executive Order S-14-08, an increase in renewable energy production has multiple and significant
benefits to California's environment and economy, including improving local air quality and reducing greenhouse gas pollution
among other benefits; and
WHEREAS as stated in Executive Order S-14-08, increased development of renewable electricity sources, energy efficiency
and demand response are needed to meet the greenhouse gas reduction goal of 1990 levels and 80 percent of the 1990 levels by
2050, making the success and expansion of renewable energy sources a key priority for California's economic and environmental
future; and
WHEREAS the goals and purposes of the RPS Program and the goals and purposes of AB 32 are mutual and compatible
because an increase in the use of renewable electricity will reduce greenhouse gas emissions; and
WHEREAS the joint and coordinated efforts of the energy and environmental agencies are intended to assure that the goals
and purposes of these various programs will be implemented by investor-owned and publically-owned utilities to the maximum
extent operationally and economically feasible and thereby will achieve the greatest results; and
WHEREAS the expansion of the RPS Program and the implementation of a complementary regulation under AB 32
designed to further reduce greenhouse gas emissions through the expansion of electricity production from renewable energy sources
will advance the goals and purposes of both programs; and
WHEREAS the AB 32 Scoping Plan adopted by the ARB in December 2008 recommends achieving a statewide renewable
energy mix of 33 percent as a key element for reducing greenhouse gas emissions to 1990 levels by 2020; and
WHEREAS such a complementary regulation under AB 32 will encourage the development and use of renewable energy
beyond those required by the RPS Program; and
WHEREAS Executive Order S-14-08 established a target that all retail sellers of electricity shall serve 33 percent of [heir
load with renewable energy by 2020; and
WHEREAS publically-owned utilities provide a significant amount of electricity in California and must be included in
statewide efforts to reduce greenhouse gases from their systems in a manner that recognizes their individual circumstances.
NOW, THEREFORE, 1, ARNOLD SCHWARZENEGGER, Governor of the State of California, by virtue of the power
vested in me by the Constitution and statutes of the State of California, do hereby order effective immediately as follows:
I. That the ARB, under its AB 32 authority, shall adopt a regulation consistent with the 33 percent renewable
energy target established in Executive Order S-14-08 by July 31, 2010. In developing the regulation, the ARB may
consider different approaches that would achieve the objectives of the Executive Order and may increase the target and
accelerate and expand the time frame based on a thorough assessment of such factors as technical feasibility, system
reliability, cost, greenhouse gas emissions, environmental protection or other relevant factors.
2. That the ARB shall work with the PUC and the CEC to ensure that a regulation adopted under authority. of AB
32 to encourage the creation and use of renewable energy sources shall build upon the RPS Program and shall regulate
all California load serving entities, including investor-owned utilities, publically-owned utilities, direct access providers
and community choice aggregators.
3. That the PUC and the CEC are requested to provide advice and assistance to, and cooperate with, the ARB in
its consideration and implementation of a regulation to reduce greenhouse gas emissions through the creation and use of
renewable energy sources. The ARB may delegate to the PUC and the CEC any policy development or program
implementation responsibilities that would reduce duplication and improve consistency with other energy programs
such as demand response, energy efficiency and energy storage.
http://gov.ca.govfndex.php?/print-vmionlexmutive-order/13269/ (2 of 3)9121(20095:25:21 PM 040
i
Office of the Govemor of the Slate of California
I
4. That the ARB shall consult with the Independent System Operator and other load balancing authorities on,
among other aspects, impacts on reliability, renewable integration requirements and interactions with wholesale power
markets in carrying out the provisions of this Executive Order.
5. The ARB shall establish the highest priority for those resources that provide the greatest environmental
benefits with the least environmental costs and impacts on public health that can be developed most quickly and that
support reliable, efficient, cost-effective electricity system operations including resources and facilities located
throughout the Western Interconnection.
I This Order is not intended to, and does not, create any rights or benefits, substantive or procedural, enforceable at law or in
equity, against the Stateof California, its agencies, departments, entities, officers, employees, or any other person.
I FURTHER DIRECT that as soon as hereafter possible, this Order be filed in the Office of the Secretary of State and that
widespread publicity and notice be given to this Order.
IN WITNESS WHEREOF I have hereunto set my hand and caused the Great Seal of the State of
California to be affixed this 15th day of September 2009.
ARNOLD SCHWARZENEGGER
Governor of California
ATTEST:
DEBRA BOWEN
Secretary of State
041
http://gov.m.gov(ndex.php?/print-venionlexemtive-order/] 32691 (3 of 319212009 5:25:21 PM
INFORMATIONAL ITEM
TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD AND AZUSA CITY COUNCIL
FROM: GEORGE F. MORROW, DIRECTOR OF UTILITIES,
DATE: SEPTEMBER 28, 2009
SUBJECT: UPDATE ON SOLID WASTE AND RECYCLING PROGRAMS
Annual statistics for various solid waste and recycling programs are attached for your reference.
The reporting period covers Fiscal Year 2008-09.
In August 2009, the City filed its annual report with the State on Azusa's compliance effort with
the State's recycling mandate, AB 939, for calendar year 2008. Compliance is measured in
terms of lbs per person per day disposed at landfills. Azusa's limit is set at 6.3 lbs per person per
day, which is equivalent to 50% waste diversion. The City of Azusa reported disposing of 5.6
lbs per person per day, well under our limit.
Processing mixed waste through Athens' material recovery facility (MRF) continues to be the
central program relied on by the City to achieve the AB 939 waste reduction requirements and
the program continues to keep the City in compliance. As shown in the attached report, about
40% of the waste diverted through the MRF is yard waste. During last fiscal year, this amounted
to about 5,000 tons, more tonnage than was collected from single family residential customers,
which totaled about 3,000 tons during the same period. Unfortunately, when Puente Hills
landfill closes in October 2013, we will no longer be able to transport yard waste to that facility
and get recycling credit for it being used as alternative daily cover (ADC). This has prompted
some cities to begin the process of exploring recycling options for yard waste. Athens Services
also has indicated that they have purchased a compost facility and will have an option available
for the City.
Staff will continue to administer other recycling programs referenced in attached. We are in the
process of having maintenance performed on the compartmentalized recycling bins used mostly
by schools to recycle beverage containers, newspaper and mixed paper. We also are continuing
to support the Sharps Mail Back Container program which seems to be fairly popular at the
Senior Center. Staff is in the process of purchasing additional Reusable Grocery Bags, in part,
with the help of a $1,000 donation from Athens Services. We will be supporting Los Angeles
County's public education campaign, November 15 through December 17, to promote greater
use of "reusable" grocery bags.
Prepared by: Cary Kalscheuer, Assistant to the Director of Utilities
042
SOLID WASTE PROGRAM UPDATE
FY 2008-2009
A. Used Oil Recycling:
Collection Centers: 5
Gallons Collected: 6,627
Filters Collected: 754
Drain Pans Distributed: 500
Program Expense (Consultant fee, containers, City staff time, advertisement, promo items)
$13,663.98
B. Sharps Collection Program:
Pick -Up Locations/Containers Distributed:
1) Azusa Medical Pharmacy/ 17 (20.73%)
2) Foothill Drug Pharmacy/ 16 (19.51%)
3) Azusa Senior Center/49 (59.75%)
Containers Purchased: 192
Total Mail -back Containers Distributed: 82
Program Expense (Containers & bus shelter ad): $4,774.67
C. Household Hazardous Event Result:
Household Served: 1225 (1,000
Vehicles)
Summary: Motor Oil
735 gallons
Anti -Freeze
130 gallons
Paint
6540 gallons
Dry Cell Battery
790 pounds
Oil Filters
250 pounds
Miscellaneous
3275 gallons
Car Batteries
185 units
CRT's
344 units
Misc. E -Waste
20475 pounds
Program Expense: N/A sponsored
by Los Angeles County Sanitation Districts
D. Beverage Container Recycling Program:
Participants: 15 schools and non-profit organizations
Total Tons Recycled: 215 tons (430,000 pounds)
Combined Fund Earned: $11,016.92
Program Expense: $7,400 contribution to California Resource Connections for
River Clean -Up Event on April 18, 2009
E. Reusable Bag Program:
Bags Purchased: 2500
Bags Distributed: 2344
Program Expense (Bags & Bus shelter ad) $7,023.55
1
043'
F. Materials Reclaimed/Recycled from Target Demolition Permit:
Lumber:
106.47 Tons
Concrete:
3,703 Tons
Ferrous and Non -Ferrous Metal:
276.55 Tons
Asphalt:
1,058 Tons
Brick:
500 Tons
G. Athens Services Contract: (FY 08-09)
Yard Waste:
Direct Haul ADC:
Tons:
Cost:
Cost/Ton:
MRF Recovery:
List All Materials Here:
Office/Computer Paper
Newspaper
Glass
Cardboard
Ferrous (Iron/Steel)
Aluminum
Plastics
Yard Waste
3,002.2
$ 112,400
$37.44
73.94
416.11
201.61
1,692.31
881.08
73.61
569.14
5,031.27
H. AB 939 Report:
Azusa Disposal Limit:
2008 Actual Disposal (at landfills)
Variance:
6.3 lbs/person/day
5.6 lbs/person/day
-11.11%
(40% of materials diverted)
AM
! Other Materials (Mixed Paper Waste) 2,712.51
Concrete 532.94
C
f C&D Recovery 270.13
f . Total Tonnage Recycled: 12,454.65
Incineration Tonnage: 971.50
Total Diversion: 13,426.15
Tons In MRF: 41,485.41
l Pct Diverted by MRF: 30%
Pct Diverted by MRF/Incineration: 32%
**MRF Program Cost: $ 1,416,181.00
Cost/Ton: $105.47
j **MRF Cost above Landfill
H. AB 939 Report:
Azusa Disposal Limit:
2008 Actual Disposal (at landfills)
Variance:
6.3 lbs/person/day
5.6 lbs/person/day
-11.11%
(40% of materials diverted)
AM