HomeMy WebLinkAboutE-5 Staff Report - West Wing Ceiling AbatementCONSENT ITEM E-5 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL VIA: SERGIO GONZALEZ, CITY MANAGER FROM: DANIEL BOBADILLA, P.E., DIRECTOR OF PUBLIC WORKS/CITY ENGINEER DATE: APRIL 2, 2018 SUBJECT: AUTHORIZATION TO SOLICIT BIDS FOR THE WEST WING CEILING ABATEMENT PROJECT SUMMARY: An air quality test and material survey were conducted in the City Hall West Wing building. Test results recommend thorough cleaning above the drop ceilings and replacement of insulation and ceiling tiles throughout the entire West Wing. The proposed action will authorize Staff to solicit bids from qualified contractors to rehabilitate the ceiling at City Hall West Wing. RECOMMENDATION: Staff recommends the City Council take the following actions: 1) Approve the project plans; and 2) Authorize Staff to solicit a Notice of Inviting Bids for the West Wing Ceiling Abatement Project DISCUSSION: On September 8, 2015, Aurora Industry Hygiene, Inc. performed an air quality test and visual inspection of the spaces above the drop ceiling system in the West Wing of City Hall. The test results recommended removal and replacement of the drop ceiling system and insulation. Prior to proceeding with these improvements, Staff obtained the services of Owen Group and Ninyo & Moore to conduct a thorough analysis of all the materials in the ceiling system. The material survey, conducted on August 24, 2017, affirms the removal and replacement of the existing drop ceiling system and fiberglass insulation and also recommends the abatement of various materials within the ceiling system. If approved by the City Council, Staff will solicit bids from qualified contractors. Staff will review submitted bids and request approval from the City Council to award a contract at a future meeting. APPROVED CITY COUNCIL 4/2/2018 West Wing Ceiling Abatement Project April 2, 2018 Page 2 FISCAL IMPACT: There is no fiscal impact associated with the recommended actions. Prepared by: Reviewed and Approved: Christina Curiel Louie F. Lacasella Engineering Assistant II Senior Management Analyst Reviewed and Approved: Daniel Bobadilla Acting City Manager Attachment: 1) Project Plans OFFICE 1 HUMAN RESOURCES 2CONFERENCE ROOM 3 WOMEN'S RESTROOM 4 MEN'S RESTROOM 5 OFFICE 10 OFFICE 9 OFFICE 12 OFFICE 13 OFFICE 14 STAFF LOUNGE 16 WOMEN'S RESTROOM 17 MEN RESTROOM 18 STAFF ROOM 22 OFFICE 21 OFFICE 20 CONTROL ROOM 24 STAFF ROOM 19 STORAGE / HALLWAY 23 BUILDING & SAFETY 8 STAFF ROOM 7 HALLWAY 6 HALLWAY 15 PATIO 11 OFFICE CLG. HT.= 8' -9" A.F.F. 1 HUMAN RESOURCES CLG. HT.= 8' -9" A.F.F. 2 CONFERENCE ROOM CLG. HT.= 8' -9" A.F.F. 3 OFFICE CLG. HT.= 8' -6" A.F.F. 9 STAFF ROOM CLG. HT.= 7' -10" A.F.F. 7 CONFERENCE ROOM CLG. HT.= 7' -9" A.F.F. 3 BUILDING & SAFETY CLG. HT.= 8' -8" A.F.F. 8 OFFICE CLG. HT.= 8' -8" A.F.F. 12 OFFICE CLG. HT.= 7' -10" A.F.F. 13 STAFF ROOM CLG. HT.= 7' -10" A.F.F. 19 HALLWAY CLG. HT.= 7' -10" A.F.F. 23 CONTROL ROOM CLG. HT.= 7' -10" A.F.F. 24 STORAGE / RESTROOMS 17 - 18 CLG. HT.= 7' -6" A.F.F. HALLWAY 15 CLG. HT.= 7' -10" A.F.F. STAFF LOUNGE CLG. HT.= 8' -4" A.F.F. 16 BUILDING & SAFETY CLG. HT.= 8' -8" A.F.F. 8 RESTROOMS CLG. HT.= 9' -5" A.F.F. 4 - 5 H.R. SOFFIT CLG. HT.= 6' -11" A.F.F. 2 STAFF ROOM 22 CLG. HT.= 7' -10" A.F.F. OFFICE CLG. HT.= 8' -4" A.F.F. 10 OFFICE CLG. HT.= 7' -10" A.F.F. 13 OFFICE 14 CLG. HT.= 7' -10" A.F.F. C FALI O INRFEO TAT SA C-24750 NO.RHOD ORE C .GERO NAGAEXP.JAN.3 1 ,2019REGISTEREDPROFESSIONALARCHITECT RM RGCITY OF AZUSACEILING REHABILITATION213 E. Foothill Blvd.,Azusa, California 91702213 E. FOOTHILL BLVD., AZUSA, CA 91702 Description0816.2115.03 Checked by Drawn by Job. No.DateIT IS THE CLIENTS RESPONSIBILITY PRIOR TO OR DURING CONSTRUCTION TONOTIFY THE ARCHITECT IN WRITING OF ANY PERCEIVED ERRORS OROMISSIONSIN THE PLANS AND SPECIFICATIONS OF WHICH A CONTRACTOR THOROUGHLYKNOWLEDGEABLE WITH THE BUILDING CODES AND METHODS OFCONSTRUCTION SHOULD REASONABLY BE AWARE. WRITTEN INSTRUCTIONSADDRESSING SUCH PERCEIVED ERRORS OR OMISSIONS SHALL BE RECEIVEDFROM THE ARCHITECT PRIOR TO THE CLIENT OR CLIENTS SUBCONTRACTORSPROCEEDING WITH THE WORK. THE CLIENT WILL BE RESPONSIBLE FOR ANYDEFECTS IN CONSTRUCTION IF THESE PROCEDURES ARE NOT FOLLOWED.Project:APPROVAL: APPROVAL: APPROVAL: CITY OF AZUSA 811 WILSHIRE BLVD. , SUITE 1050 TEL: (213) 873−4700 FAX: (213) 873−4790 LOS ANGELES, CA 90017 www.owengroup.com RESUBMITTED WITH REVISEDHAZARDOUS MATERIAL SURVEY REPORT03/26/2018Scale:Ref: 1/8" = 1'-0" FLOOR PLAN (REFRENCE ONLY)1Scale:Ref: 1/8" = 1'-0" DEMOLITION & RECONSTRUCTION CEILING PLAN 2 OVERALL FLOOR PLAN & CEILING PLAN A-2.00 DEMOLITION KEYNOTES CEILING LEGENDS RECESSED LIGHT LIGHT HVAC REGISTERS CIRCULAR FAN SQUARE FAN SPEAKERS 2X2 T-BAR CEILING GRID FIRE ALARM APPLICABLE CODE ACTUALALLOWABLE BUILDING AREA (CBC TABLE 503) 8, 815 S.F.18, 000 S.F. RECONSTRUCTION KEYNOTES 01 50 EXISTING GYPSUM BOARD CEILING TO REMAIN. 02 08 REMOVE AND TEMPORARILY SECURE THE LIGHT FIXTURES DURING CONSTRUCTION FOR REUSE. EXISTING SOFFIT TO REMAIN. 09 REMOVE ALL EXISTING SUSPENDED CEILING GRID SYSTEM & CEILING TILES. REMOVE AND TEMPORARILY SECURE THE HVAC REGISTERS DURING CONSTRUCTION FOR REUSE. RE-INSTAL (E) LIGHT FIXTURES. 01 03 EXISTING LIGHT FIXTURES TO REMAIN. 55 INSTAL (N) SUSPENDED 2'X2' WHITE ARMSTRONG PRELUDE+XL CEILING GRID. 56 INSTAL (N) 2'x2'x5/8" WHITE ARMSTRONG SAHARA CEILING TILES. 04 51 RE-INSTAL (E) HVAC REGISTERS. 1 A-11.01 5 A-11.01 03 A-11.01 11 A-11.00 05 EXISTING FAN TO REMAIN. 01 03 TYP. 04 03 TYP.N.I.C. N.I.C. 10 REMOVE AND TEMPORARY SECURE THE SPEAKERS DURING CONSTRUCTION FOR REUSE. 11 REMOVE AND TEMPORARILY SECURE THE RECESSED LIGHT FIXTURES DURING CONSTRUCTION FOR REUSE. N.I.C. N.I.C. N.I.C.N.I.C. N.I.C. N.I.C. 04 03 TYP. 04 03 TYP. 05 06 EXISTING RECESSED LIGHT TO REMAIN. 07 50 TYP. 08 51 TYP. 52 RE-INSTAL (E) RECESSED LIGHT. 53 RE-INSTAL (E) SPEAKERS. 54 07 EXISTING FIRE ALARM TO PROTECT AND REMAIN IN PLACE. EXISTING FIRE ALARM TO PROTECT AND REMAIN IN PLACE. 06 54 TYP. 10 53 TYP. 09 52 TYP.02 TYP. TYP. 1155 TYP. 56 19 A-11.00 NOTE: •PROTECT THE EXISTING ITEMS IN PLACE TO REMAIN TO REUSE. •ACM WORK COORDINATE WITH THE CITY FOR ACM MITIGATION WORK, REFER TO HAZARDOUS BUILDING MATERIAL SURVEY REPORT BY NINYO AND MOORE, DATED AUGUST 24 2017. 57 BRACE ALL EXISTING WALLS TO COMPLY WITH CBC. 20 A-11.00 NOTE: •CONTRACTOR SHALL INSPECT AND VERIFY TO PROVIDE BLOCKING TO EXISTING WALLS WHERE REQUIRED TO COMPLY WITH CBC.20 A-11.00 N.I.C. ALL