ORDINANCE NO. 2133
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY
OF AZUSA APPROVING THE TERMS AND CONDITIONS
OF A PROJECT DEVELOPMENT AGREEMENT BETWEEN
SOUTHERN CALIFORNIA PUBLIC POWER AUTHORITY
AND THE CITY OF AZUSA, AND AUTHORIZING THE
EXECUTION OF AND DELIVERY OF SAID AGREEMENT
BY OFFICERS OF THE CITY OF AZUSA.
WHEREAS , pursuant to the provisions of Chapter 5 , Division
7, Title 1 of the Government Code of the State of California, as amended
(the "Joint Powers Act" ) , the City of Azusa and certain other public
agencies created pursuant to the laws of the State of California
(collectively, the "Members" ) , have entered into a Joint Powers Agreement
(the "Agreement" ) creating the Southern California Public Power Authority
(the "Authority" ) , a public entity separate and apart from the Members ; and
WHEREAS , in accordance with the Agreement and the Joint
Powers Act , the Authority has undertaken or will undertake to , among
other things , incur preliminary costs , make (or cause to be made) studies
and acquire (or cause to be acquired) options and permits ( "Development
Work" ) in connection with a project for the transmission of electric
energy , which project (the "Project" ) is the Mead-Phoenix DC Intertie ,
a +/-500 KV DC transmission line with AC/DC converter stations at each
end and related facilities , - to be located in the States of Arizona and
Nevada; and
WHEREAS , the City of Azusa desires to , among other things,
participate in, and obtain the benefits of , such Development Work and
to obtain the right of first refusal to output from the Project , and,
as such, has determined that it is desirable and in the best interests
of the customers of the electric system of the City of Azusa to enter
into a Project Development Agreement (the "Project Development Agreement" )
in the form submitted to this City Council .
NOW, THEREFORE , the City Council of the City of Azusa
does ordain as follows :
1. The City Council of the City of Azusa hereby finds
and determines that the terms and conditions of the Project Development
Agreement be, and the same are hereby , approved; provided that upon
execution thereof the Project Development Agreement will provide the
City of Azusa with an option to acquire 2 megawatts to 6 megawatts
of transmission capacity .
2 . The Mayor and City Clerk of the City of Azusa are
authorized to execute and deliver the Project 'Development Agreement by
and on behalf of '-the City of Azusa in substantially the form subritted
to`.this meeting.
3. Pursuant to Section 54241 of the Government Code
of the State of California, this Ordinance is subject to the provisions
for referendum applicable to the City of Azusa.
4. The City Clerk of the City of Azusa shall certify
to the enactment of this Ordinance and shall cause this Ordinance to
be published in accordance with Section 54242 of the Government Code
of the State of California.
5 . Thirty ( 30) days from and after its enactment , this
Ordinance shall take effect and be in full force , in the manner provided
by law.
Nw
ADOPTED AND APPROVED this 1st day of March
1982 .
4i
MAYOR
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) SS .
CITY OF AZUSA )
I , ADOLPH A. SOLIS, City Clerk of the City of Azusa,
do hereby certify that the foregoing Ordinance No. 2133 was regularly
introduced and placed upon its first reading at a regular meeting of
the City Council on the 16th day of February , 1982 . That , thereafter,
said Ordinance was duly adopted and passed at a regular meeting of
the City Council on the 1st day of March , 1982 , by the following vote
to wit :
AYES : COUNCILMEN: Decker, Fry, Cruz, Moses, Solem
NOES : COUNCILMEN: None
ABSENT: COUNCILMEN: None
44.(//( 1#
441"
CITY CLERK
Publish Azusa Herald 3/10/82.