AGENDA ITEM
Transmittal of the City Manager's Recommendations for the
COMPREHENSIVE LONG-RANGE CAPITAL IMPROVEMENT PROGRAM
for Fiscal Year 2002-03
September 23, 2002
Honorable Mayor and Members of the City Council:
It is my pleasure to transmit to you recommendations for another important
forward step in our Comprehensive Long-Range Capital Improvement Program for the
City of Azusa.
As noted last year, like most local governments in California,Azusa fell behind
in maintaining, expanding and replacing our infrastructure and capital assets.
During the period 1986-98, there were a number of important projects built (including
the Senior Center, Slauson Pool,Azusa Light&. Water headquarters and expanded Police
Facility) along with a prudent program of reinvestment in facilities and equipment for
Azusa Light &Water. But routine maintenance and reinvestment for other functions
(parks, public buildings, sewers, streets, alleys, sidewalks, equipment,vehicles etc.) was
postponed.
In the fall of 1998, a new start was made not only on cataloguing and
prioritizing our community's capital needs, but also in beginning to systematically
address long-delayed needs. Each year since,we have made progress in both catching
up on deferred investment and planning ahead for preventative maintenance.
I am particularly proud of the record of the past year:
• The opening of the Canyon City Skatepark represents a $400,000 investment
in the changing recreation needs of youngsters and adolescents and is the
aa_ xiL 03/e 2-- X19
largest and best of its kind in the San Gabriel Valley.
• Plans for a new Library that would replace our obsolete and inadequate
existing facility with a 60,000 square foot landmark "lifelong family learning
center" have been submitted to the State for funds to match the bond
approved by Azusa voters by a margin of more than 3-1.
• The Azusa Auditorium, placed this year on the National Register of Historic
Places, finally saw a complete interior and exterior renovation for a facility that
occupies a central place in the civic life of our community.
• A new vision for Azusa's future contained in a new General Plan and
Development Code is being completed for adoption by the City Council next
spring. Involving hundreds of Azusa residents through the Citizens Congress,
this comprehensive effort is the most ambitious effort of its kind undertaken by
a city of our size in the entire state.
• Keying off this effort, a new Park Master Plan is also being completed to guide
an "Azusa Park Renaissance" involving improvements to existing parks,
addition of new park land and facilities and greater shared use of public
facilities throughout the community.
• A major street and alley repair and sidewalk construction and repair effort
was completed
• Just in time for the summer swim season, Slauson Pool received a complete
overhaul to address deferred maintenance on the 9 year-old facility that left it
as good as new.
• Construction began on a major southern Gateway monument initiated by the
residents of Neighborhood Improvement Zone I.
• A number of smaller neighborhood improvement projects were completed
including beautification of the Vernon off-ramp, newly landscaped island north
of 1St and San Gabriel, curb and parking improvements next to our historic train
station and parkway improvements on Donna Beth.
• A replacement or'upgrade of all the city's obsolete or inefficient heating,
ventilation, air conditioning and lighting units with energy saving devices
• Replacing almost all of the worn-out equipment and rolling stock for the new
Public Works Department, along with continued upgrading of our computer
hardware citywide.
020
During the operating budget approval,we brought forward a continued equipment
replacement program, along with carry-over of project not yet completed. Tonight, we
are presenting new projects and amendments for the current fiscal year 2002-03. The
major elements include:
Azusa Light & Water Capital Investment: We will continue our long-term
investment in ensuring reliable service to our customers. Azusa can be proud that the
investments of the last fifteen years have paid off in avoiding the electric reliability and
water quality crises facing many other public and private utilities. In the year ahead, we
have the resources to devote an additional $6 million toward continuing this legacy which
results in reliable and affordable resources for our homes and businesses.
Among the high profile projects in this year's program is the construction of the
much-needed second substation to ensure reliable service to our growing customer
needs. The land has been acquired and construction will commence in 2003. The
Planning Commission has also approved plans for construction of a new Electric Division
Yard at 10"' and Vernon. In addition to improved office and service facilities, the move
will allow the new Public Works Department to expand and improve their support
facilities at the City yard which is currently shared with Azusa Light &Water.
One of the highlights of the Water Division program is a conservation
demonstration project that will underwrite native landscaping in the highly visible gateway
to the San Gabriel Canyon. The project scope expands a project approved earlier with
MTA grant funds and local Gas Tax match to acquire and construct attractive medians in
San Gabriel Canyon Road north of Sierra Madre. The demonstration project will expand
the project to landscape the existing median south of Sierra Madre, the initial westbound
median on Sierra Madre, the unimproved area of Canyon Park, the revegetation of
damaged areas of Canyon Park along with appropriate amenities and signage.
The Neighborhood Improvement and Pavement Management Plan: In the first
Comprehensive Capital Improvement package,we funded a study of our street, alley and
sidewalk deficiencies. The price tag was a staggering$36 million. A careful staff review
of that program by our Director and Assistant Director of Public Works validates the
scope of that report, but proposes a more cost-effective intervention. Moving ahead
now will only cost one third as much, but will address 80% of the city's pavement
deficiencies over the next five years. The recommended plan comprehensively
coordinates sewer, water and repavement efforts to both shave and share costs. By
fixing the needs in an entire neighborhood (streets,gutters, sidewalks, alleys—along with
trimming street trees and other maintenance) we also minimize disruption and
duplication. While this project does save millions of dollars, it will require a funding
jumpstart. The plan includes options along with our recommendation for front-loading
the required investment.
The Azusa Park Renaissance Plan:Major work at Gladstone and Memorial Parks,
021
along with modest improvements at Northside, Veterans Freedom and Zacatecas Parks
have showcased the rebirth and expansion of Azusa's precious park resources. These
recommendations add another $4 million in projects funded or anticipated from grant,
endowment and community facility district sources. This unprecedented regreening of
Azusa will upgrade every single park in the city and significantly expand park acreage for
our residents.
Sewer Master Plan: As part of the Neighborhood Improvement and Pavement
Management Plan, we will implement a complete overhaul of the City's aging sewer
system. This upfront investment in our sewers over the next five years will, like pavement
management, save money in the long-run. We will be bringing detailed financing choices
to the Council fol. how to recover this investment.
Facilities Maintenance:An engineer's analysis of the Woman's Club has indicated
safety and structural integrity concerns that should be addressed. The historic facility
also deserves appropriate interior renovation and exterior repainting. The Public Works
Endowment is recommended as the funding source for $400,000 to move forward with
this project, subject to later adjustment as project specifications are finalized. A similar
amount ($375,000) is recommended for long-deferred punch list of interior and exterior
items at the Memorial Park Recreation Center, including air conditioning for the heavily-
used basketball gym. Finally, a modest budget of$25,000 is recommended as a Phase
IV for Auditorium renovation to address audio-visual equipment needs.
Capital project management: As we have embarked on our ambitious effort to
revitalize Azusa "one neighborhood" at a time, the scale and scope of our capital
program has strained our capacity to plan, budget, oversee and complete projects on
time and on budget. As a result, we have this year incorporated the overhead costs of
project management, both in-house and under contract. Our recent experience has
shown that a single manager for each project is essential, especially when multiple
departments are involved in projects along with private contractors. We expect to further
strengthen this function with a clearing house for all projects to ensure their satisfactory
management from at every step from planning to completion.
As an older city that continues to grow and revitalize, Azusa will continue to face
long-term challenges in funding both needed new capital investment as well as ongoing
replacement and maintenance. But with adoption and implementation of these
recommendations, we will have addressed our most glaring deficiencies. We will also
have left a legacy for future generations to continue the tradition of building for the long-
term prosperity and quality of life of Azusa residents.
Finally, I would like to express appreciation to those responsible for the progress
we have made and will be making. Our Finance Director Marcie Medina and Assistant
City Manager Robert Person have spearheaded this effort during the past year, including
the planning and preparation of these recommendations. Azusa Light &Water Director
022
Joe Hsu and his staff along with Public Works Director Bill Nakasone, Public Works Asst.
Director and City Engineer Nasser Abbaszadeh and Park Planning and Development
Director designate Randy Noriega have all been instrumental in project planning. But it is
not only City staff that have contributed, but the community as well. We are fortunate to
have a far-sighted and fiscally prudent City Council, able commissioners and interested
community activists and volunteers who can all take pride that their concerns are being
addressed. From volunteers planting new trees in a street parkway to Purchasing staff
processing vital paperwork, this effort to rebuild Azusa is truly a team effort and a team
achievement.
•
Sincerely,
Rick Cole
City Manager
023
City of Azusa
CIP 2003
New Funding Requests by Element
Description Element 2003 Funding Source
Additional funding Proj#72102G - Distribution Upgrades Water 1,000,000 Water Fund
Additional funding Proj#72102E- Pipeline Baseline Water 50,000 Water Fund
Additional funding Proj#72102H-Pipeline Lakeview Water 475,000 Water Fund
Additional funding Proj#72102B- Pipeline Dalton . Water 760,000 Water Fund
Additional funding Proj#72101P-Azusa Spreading Grounds Water 75,000 Water Fund
Purchase of property from city of Pasadena Water 55,000 Water Fund
Additional funding Proj#72101N - Upsize Discharges Wells Water 400,000 Water Fund
Fire Flow relief Gladstone/Bfarranca Water 200,000 Water Fund
Design and contruction of a Ranger station Water 700,000 Water Fund
Emergency backup power generator Water 100,000 Water Fund
Upgrade to the Canyon Filtration Plant Water 1,000,000 Water Fund
Northern Transmission Main Water 500,000 Water Fund
• 5,315,000
Additional Funding- New Library Library 275,000 General Fund Loan
Pavement Management Plan Public Works 1,289,000 To be determined
Pavement Management Plan Public Works 850,000 Gas tax
Remodeling of Light Building at the yard Public Works 180,000 Endowment Fund
210 Fwy soundwall Public Works 150,000 Endowment Fund
New sidewalks and concrete repair Public Works 200,000 Endowment Fund
2,669,000
Sewer Master Plan Construction Phase I Sewer 80,000 Sewer Fund
New Signs Sewer 100,000 Sewer Fund
180,000
C.)
"QPage 1 of 2
City of Azusa
CIP 2003
New Funding Requests by Element
Description Element 2003 Funding Source
Veterans Freedom Park Imp. Recreation 50,000 MCCFD
Memorial Park Improvements Recreation 212,000 Proposition 12
Memorial Park Improvements Recreation 46,500 MCCFD
Northside Park ImprovementsRecreation 223,000 MCCFD
Pioneer Park Improvements Recreation 246,000 MCCFD
Slauson Park Improvements Recreation 4,500 MCCFD
Zacatecas Park Improvements Recreation 350,000 Murray-Hayden
Wilderness Park Acquisition` Recreation 500,000 Proposition 13
Parks Master Plan Recreation 10,000 MCCFD
SG River Bike Path Recreation 100,000 MCCFD
SG River Bike Path Recreation 350,000 LA County Proposition A
US Forest Service Station Recreation 700,000 Water Fund
Rubberized Handicap Resurf. Recreation 19,000 MCCFD
Interpretive Gardens Recreation 350,000 LA County Proposition A
Angeleno Park Recreation 50,000 Quimby
Zacatecas Park Matching Funds Recreation 150,000 Quimby
Consultant for Des/Arch Recreation 51,000 MCCFD
3,412,000
Women's Club Improvements Public Works 400,000 Endowment Fund
Memorial Park Rec Center Public Works 375,000 Endowment Fund
Auditorium A/V Upgrades Public Works 25,000 Endowment Fund
1 800,000
Total 112,651,000
C:)
C.11 Page 2 of 2
City of Azusa
CIP 2003
New Funding Requests by Funding Source
Description Element 2003 Funding Source
Remodeling of Light Building at the yard Public Works 180,000 Endowment Fund
210 Fwy soundwall Public Works 150,000 Endowment Fund
New sidewalks and concrete repair Public Works 200,000 Endowment Fund
Women's Club ImprovementsPublic Works 400,000 Endowment Fund
Memorial Park Rec Center Public Works 375,000 Endowment Fund
Auditorium NV Upgrades Public Works 25,000 Endowment Fund
1,330,000
Pavement Management Plan Public Works 850,000 Gas tax
Pavement Management Plan Public Works 1,289,000 To be determined
Additional Funding- New Library Library 275,000 General Fund Loan
275,000
SG River Bike PathRecreation 350,000 LA County Proposition A
Interpretive Gardens Recreation 350,000 LA County Proposition A
700,000
Veterans Freedom Park Imp. Recreation 50,000 MCCFD
Memorial Park Improvements Recreation 46,500 MCCFD
Northside Park Improvements Recreation 223,000 MCCFD
Pioneer Park Improvements Recreation 246,000 MCCFD
Slauson Park Improvements Recreation 4,500 MCCFD
Parks Master Plan Recreation 10,000 MCCFD
SG River Bike Path Recreation 100,000 MCCFD
Rubberized Handicap Resurf. Recreation 19,000 MCCFD
Consultant for Des/Arch Recreation 51,000 MCCFD
750,000
C)
i
Zacatecas Park Improvements Recreation 350,000 Murray-Hayden
Memorial Park Improvements Recreation 212,000 Proposition 12
Wilderness Park Acquisition Recreation 500,000 Proposition 13
Angeleno Park Recreation 50,000 Quimby
Zacatecas Park Matching Funds Recreation 150,000 Quimby
200,000
Sewer Master Plan Construction Phase I Sewer 80,000 Sewer Fund
New Signs Sewer 100,000 Sewer Fund
180,000
Additional funding Proj#72102G - Distribution Upgrades Water 1,000,000 Water Fund
Additional funding Proj#72102E- Pipeline Baseline Water 50,000 Water Fund
Additional funding Proj#72102H - Pipeline Lakeview Water 475,000 Water Fund
Additional funding Proj#72102B- Pipeline Dalton Water 760,000 Water Fund
Additional funding Proj#72101P -Azusa Spreading Grounds Water 75,000 Water Fund
Purchase of property from city of Pasadena Water 55,000 Water Fund
Additional funding Proj#72101 N - Upsize Discharges Wells Water 400,000 Water Fund
Fire Flow relief Gladstone/Barranca Water 200,000 Water Fund
Design and contruction of a Ranger station Water 700,000 Water Fund
Emergency backup power generator Water 100,000 Water Fund
Upgrade to the Canyon Filtration Plant Water 1,000,000 Water Fund
Northern Transmission Main Water 500,000 Water Fund
US Forest Service Station Recreation 700,000 Water Fund
6,015,000
Total 12,651,000