TO:
FROM:
DATE:
CONSENT CALENDAR
HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD
MANNY ROBLEDO, DIRECTOR OF UTILITIES Lf\C/L.
MAY 28, 2019
SUBJECT: AWARD OF CONTRACT FOR WATER PROJECT W-347 CITRUS AVENUE
AND FOOTHILL BOULEVARD 830 TIE-IN
BACKGROUND:
In March 2019, Azusa Light & Water (ALW) issued a notice inviting formal bids (NIB) for the
Water Division's Citrus Avenue and Foothill Boulevard 830 Tie-In Capital Improvement
Project. This project will replace a section of abandoned water pipe and provide a redundant
feed to the 830 pressure zone.
RECOMMENDATION:
Staff recommends the Utility Board take the following action:
1)Approve the Award of Contract to C.P. Construction Co., Inc. of Ontario, California
for Water Project W-347; and
2)Authorize the Mayor to execute the Contract, in a form acceptable to the City
Attorney.
ANALYSIS:
The water main that crosses Cilrus Avenue, connecting the water mains on the west and east
sides of the street, has been identified as a high priority replacement. Currently, the water main
is disconnected due to a severe leak. ALW has prepared the Water Plans and Specifications for
its replacement in-house. Replacing and reconnecting the water main will provide a secondary
feed to a critical portion of the 830 pressure zone. The pipeline replacement is located on Citrus
Avenue, just south of Foothill Boulevard, and will include the installation of 100 linear feet of
12-inch ductile iron class 350 water pipe.