TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
VIA: SERGIO GONZALEZ, CITY MANAGER
FROM: DANIEL BOBADILLA, P.E., DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
DATE: JULY 15, 2019
SUBJECT: AUTHORIZATION TO ISSUE SERVICE REQUEST WITH LOS ANGELES
COUNTY PUBLIC WORKS FOR THE NEWBURGH STREET, ET AL. PAVEMENT
PRESERVATION PROJECT
BACKGROUND:
Los Angeles County Public Works (LACPW) is proposing a pavement preservation project that falls
primarily within the unincorporated region bounded by West Gladstone Street to the north, East Arrow
Highway to the south, South Azusa Avenue to the east, and North Vincent Avenue to the west. Several
of the streets proposed for pavement preservation fall within both City and County jurisdiction. In order
to maintain uniformity, LACPW has recommended that the City of Azusa utilize the County’s
contractor on the segments of streets within the City’s jurisdiction.
RECOMMENDATION:
Staff recommends that the City Council take the following actions:
1)Authorize the Director of Public Works to issue a service request with Los Angeles County
Public Works for the Newburgh Street, et al. Pavement Preservation Project for an amount not to
exceed $45,000.
ANALYSIS:
Los Angeles County Public Works (LACPW) is proposing a pavement preservation project that falls
within the unincorporated region bounded by West Gladstone Street to the north, East Arrow Highway
to the south, South Azusa Avenue to the east, and North Vincent Avenue to the west (Attachment 1).
Several of the streets proposed for pavement preservation fall within both City and County jurisdiction.
LACPW is proposing a micro-mill and cape seal pavement preservation method which will prolong the
service life of the proposed streets. All affected pavement markings and striping will be included within
the project limits.
APPROVED
CITY COUNCIL
7/15/2019
Azusa Library ADA Compliant Restroom Retrofit Improvement Project
July 1 5, 2019
Page 2
The proposed streets, limits, and jurisdictions are provided in the table below:
Street Limits Jurisdiction
Laxford Road Vincent Avenue to County Boundary Line 100% City of Azusa
Newburgh Street Vincent Avenue to County Boundary Line 100% City of Azusa
Orkney Street 260 feet east of Leaf Avenue to 210 feet west
of Rimsdale Avenue
100% City of Azusa
Orkney Street 210 feet west of Rimsdale Ave to Azusa
Avenue
30% City of Azusa
FISCAL IMPACT:
This project will be funded by Measure M Local Return funds for a total construction cost of $45,000.
Prepared by: Fiscal Impact Reviewed By:
Robert Delgadillo Talika M. Johnson
Assistant Director of Public Works Director of Finance
Reviewed By: Reviewed and Approved:
Daniel Bobadilla, P.E Sergio Gonzalez
Director of Public Works/City Engineer City Manager
Attachment:
1) Los Angeles County Public Works Project Estimate
Project Design Concept Attachment V – City of Azusa Segments
Newburgh Street, et al. Pages 1 of 4
City of Azusa Segments (highlighted in blue on project map)
Street Limits Jurisdiction
LAXFORD RD VINCENT AV TO COUNTY BOUNDARY LINE 100%
NEWBURGH ST VINCENT AV TO COUNTY BOUNDARY LINE 100%
ORKNEY ST
260 FEET EAST OF LEAF AVENUE TO 210 FEET
WEST OF RIMSDALE AV 100%
ORKNEY ST
210 FEET WEST OF RIMSDALE AV TO AZUSA
AV 30%
Newburgh Street, et al.
Pavement Preservation
LOS ANGELES COUNTY PUBLIC WORKS
CITY OF AZUSA
T.G. 598 G2 – J2
DATE:
06/06/2019
PREPARED BY:
CS
NORTH
Project Design Concept Attachment V – City of Azusa Segments
Newburgh Street, et al. Pages 2 of 4
Newburgh Street, et al.
Pavement Preservation
LOS ANGELES COUNTY PUBLIC WORKS
CITY OF AZUSA
T.G. 598 G2 – J2
DATE:
06/06/2019
PREPARED BY:
CS
Project Design Concept Attachment V – City of Azusa Segments
Newburgh Street, et al. Pages 3 of 4
Prerequisite (To be performed by City of Azusa):
• Upgrade all affected curb ramps to Americans with Disabilities Act (ADA) standards prior
to pavement preservation treatments.
• Repair damaged sidewalks, driveways, and curbs and gutters.
• Perform pavement dig-outs associated with severe pavement distresses.
Roadway Scope:
Micro-mill and Cape Seal:
• Micro-mill the existing pavement full width.
• Apply a scrub seal using 5/16-inch Reclaimed Asphalt Pavement screenings over the
micro-milled surface. The scrub seal shall be applied 6 inches away from the edge of
gutter on both sides.
• Apply a Polymer Modified Emulsion-Reclaimed Asphalt Pavement Slurry Seal over the
scrub seal.
Traffic Scope:
• Restripe all affected pavement markings and striping within the project limits.
Newburgh Street, et al.
Pavement Preservation
LOS ANGELES COUNTY
PUBLIC WORKS
CITY OF AZUSA
T.G. 598 G2 – J2
DATE:
06/06/2019
PREPARED
BY: CS
Project Design Concept Attachment V – City of Azusa Segments
Newburgh Street, et al. Pages 4 of 4
Preliminary Estimate:
City of Azusa
Projected Preliminary Engineering $1,000
Construction Cost:
Pavement Treatment including striping $35,000
Construction Contingency (10%) $3,500
Construction Engineering (15%) $5,200
Subtotal $44,700
Contract City Liability Trust Fund
(CCLTF) 4.5% $300
Total $45,000