The Utility Board/City Council of the City of Azusa met in regular session, at the above date and time, in the Azusa Light
and Water (ALW) Conference Room, located at 729 North Azusa Avenue, Azusa, California. Please note this meeting
was done via Teleconference only.
Chairman Alvarez called the meeting to order at 6:31 P.M.
ROLL CALL: Roll call was taken by Secretary Cornejo.
PRESENT: BOARD MEMBERS: ALVAREZ, CARRILLO, ROCHA, GONZALES, MACIAS
ABSENT: BOARD MEMBERS: NONE
ALSO PRESENT
Elected Officials: Secretary Cornejo
City Attorney: Jeff Ferre
Staff Members: City Manager Gonzalez, Utilities Director Robledo, Assistant Director of Water Operations Macias,
Utilities Programs Specialist Reid, Senior Water System Engineer Barbosa, Administrative Services Director Johnson,
Assistant Director of Customer Care and Solutions, Senior Management Analyst Smith, and Chief Deputy City Clerk
Garcia
A.PUBLIC PARTICIPATION
City Attorney Ferre reported the public may participate in the meeting via telephone and email.
B.UTILITIES DIRECTOR COMMENTS
Utilities Director Robledo reported over the past few weeks staff has focused on responding to the COVID-19 pandemic.
There have been no shortages and no prolonged outages for either water or electricity. Supplies for both are stable.
Statewide, power usage has declined 10%. Staff has been practicing social distancing and disinfecting surfaces. Water,
electric, and customer service staff are working staggered schedules as a preventative measure. Email and website
messaging states tap water is safe to drink because chlorine disinfects it. During the crisis, disconnection of service for
nonpayment has been suspended. Payments may be made at the drive-through window and online. Staff is answering
telephone calls. Morale is high, and staff feels they are helping people and are part of the solution. Athens has ceased
recycling materials and is using the facility as a transfer station. Athens will attempt to increase the amount of refuse
being burned at the waste energy facility, but a lot of refuse will be sent to the landfill. If the pandemic affects Athens'
ability to staff services, street sweeping will be the first service to cease. The automated metering information (AMI)
CONSENT ITEM
UTILITY BOARD
I-1
APPROVED
UTILITY BOARD
5/18/2020
Special Meeting
PAGE 2 – 03/23/2020
project will focus on the installation of electric meters during the pandemic. Recycling events in April have been
postponed to hopefully June or July. Work on the line extension to Canyon Business Park will continue. Work at the
Orchard site is currently complete.
In reply to Chair Alvarez's question, Assistant Director for Customer Service Holmes indicated a few hundred customers
have requested payment arrangements. Utilities Director Robledo added that the City Attorney has advised staff not to
forgive payments. Staff will work with customers to arrange affordable payments.
C. UTILITY BOARD MEMBER COMMENTS
None
D. SCHEDULED ITEMS
1. Authorize Plan to Fund the CalPERS Unfunded Accrued Liability Obligation for the Water Fund.
Utilities Director Robledo advised that staff recommends a loan from the Electric Fund to the Water Fund. The Water
Fund will pay interest of approximately 2.4% to the Electric Fund rather than pay approximately 3% in bond fees.
Administrative Services Director Johnson reported the Water Fund, Electric Fund, and Sewer Fund have unfunded
accrued liability (UAL) balances of approximately $6.4 million, $5.4 million, and $1.8 million respectively. The Electric
and Sewer Funds have sufficient cash to decrease their portion of the UAL and maintain good credit ratings. Staff
proposes that the $6.4 million Water Fund UAL balance be paid in full by: i) the Water Fund forgiving the $2.9 million
loan owed by the General Fund; ii) the General Fund issuing $2.9 million in Pension Obligation Bonds in lieu of paying
off said loan; and iii) the Water Fund borrow $3.5 million from the Electric Fund.
In answer to Board Members' questions, Administrative Services Director Johnson indicated the term of the loan to the
Water Fund would be five years, and the interest rate would be approximately 2.4%. The transactions will not negatively
affect the City's credit rating. Cash on hand in the Water Fund would exceed Moody's criterium for a AA rating.
Moved by Board Member Rocha, seconded by Board Member Gonzales, to approve the staff recommendation by the
following vote of the Board:
AYES: BOARD MEMBERS: ALVAREZ, CARRILLO, ROCHA, GONZALES, MACIAS
NOES: BOARD MEMBERS: NONE
ABSENT: BOARD MEMBERS: NONE
ABSTAIN: BOARD MEMBERS: NONE
Resolution No. 2020-UB-01 authorizing the forgiveness of the loan balance of approximately $2.9 million owed by the
General Fund to the Water Fund established by Resolution No. 14-C81 upon completion of the General Fund issuing
Pension Obligation Bonds to pay the same $2.9 million towards the Water Fund's $6.4 million portion of the Unfunded
Accrued Liability for pensions to CalPERS was adopted; Resolution No. 2020-UB-01 approving an agreement for the
Electric Fund to loan $3.5 million to the Water Fund to pay the remaining portion of the Water Fund's 46.4 million
Unfunded Accrued Liability for pensions to CalPERS was adopted; and the City Manager was authorized to approve
lump-sum payments of the City's Unfunded Accrued Liability for pensions to CalPERS from the Water Utility (Fund 32)
in a not-to-exceed amount of $3.5 million,
E. CONSENT CALENDAR
Moved by Board Member Rocha, seconded by Board Member Gonzales, to approve the Consent Calendar by the
following vote of the Board with the exception of Item E-5 which was handled under the Special Call portion of the
agenda:
AYES: BOARD MEMBERS: ALVAREZ CARRILLO, ROCHA, GONZALES, MACIAS
NOES: BOARD MEMBERS: NONE
PAGE 3 – 03/23/2020
ABSENT: BOARD MEMBERS: NONE
ABSTAIN: BOARD MEMBERS: ALVAREZ (Item 1 only), MACIAS (Item 1 only)
1. The minutes of the February 24, 2020 regular meeting of the Utility Board were approved.
2. The competitive purchase requirements pursuant to Section 2-521(a), Article VII, Chapter 2 of the Azusa
Municipal Code (Cooperative and Piggyback Purchasing) were waived; the purchase of one (1) new 2020 Ford
Super Duty F-350 DRW (F3G) XL 2-WD Reg Cab and Royal 12' contractor body with equipment was approved;
and the issuance of a Purchase Order to National Auto Fleet Group in the amount not-to-exceed $53,049.41 was
authorized.
3. Bid document #LD2020-Switchrack Steel and bid document #LD2020-Equipment for the Circuit Breaker
Expansion Project at the Azusa Substation were approved; and the City Clerk's Office was authorized to advertise
and solicit for bids for these two items.
4. The competitive purchase requirements pursuant to Chapter 2, Article VII, Section 2-521(a) of the Azusa
Municipal Code (Cooperative and Piggyback Purchasing) were waived; and the issuance of a Purchase Order to
National Auto Fleet Group of Watsonville, California, in an amount not-to-exceed $55,294.93, including sales tax
and delivery charges, for a 2020 Ford Super Duty F-250 SRW pickup and custom body was approved.
6. Task Order 10 for Well No. 1 rehabilitation to General Pump Company under the existing Master Maintenance
Services Agreement for a not-to-exceed amount of $343,310 was awarded.
SPECIAL CALL
Authorization to Solicit Bids for Project W-277 Water Main Replacement on Cypress Street Between Vincent Ave. and
Azusa Ave.
In answer to Board Member Rocha's questions, Utilities Director Robledo advised that the water main was installed in
1913 and has reached the end of its useful life. This segment of the water main needs frequent repairs. Assistant Director
of Water Operations Macias indicated the anticipated life span of the new pipe is 75 years, but in some cases the lifespan
has reached 100 years.
Moved by Board Member Rocha, seconded by Chair Alvarez to approve project plans and specifications for Project W-
277 Water Main Replacement on Cypress Avenue between Vincent Ave and Azusa Ave; and advertise and solicit bids for
the project by the following vote of the Board:
AYES: BOARD MEMBERS: ALVAREZ, CARRILLO, ROCHA, GONZALES, MACIAS
NOES: BOARD MEMBERS: NONE
ABSENT: BOARD MEMBERS: NONE
F. STAFF REPORTS/COMMUNICATIONS
None
G. VERBAL COMMUNICATIONS
1. Power Supply Update
Utilities Director Robledo reported renewable energy comprises approximately 21.3% of the power portfolio. The Lodi
Energy Center is undergoing repairs and should be online by July. The bulk of the repair costs will be paid by insurance
proceeds. Power demand has decreased due to temporary business closures. Staff is negotiating to retain ALW's cap-and-
trade allowances and to purchase resource adequacy capacity for 2021. In addition, staff is working with the California
Independent System Operator (CAISO) to adjust the load forecast to match supply and demand.
PAGE 4 – 03/23/2020
2. Water Supply Update
Utilities Director Robledo related that rainfall totals approximately 16 inches to date. The water table was down
approximately 0.4 feet prior to 5 inches of rain in March but remained in the operating range. Reservoirs have plenty of
water. Raw water is processed through the filtration plant and then treated with a chlorine solution that kills viruses and
bacteria, including the coronavirus.
3. General Policy and Regulatory Updates
Utilities Director Robledo indicated most governmental actions concern the coronavirus; however, staff continues to
monitor legislative and executive actions.
H. CLOSED SESSION
None
I. ADJOURNMENT
The meeting was adjourned by consensus of the Utility Board.
TIME OF ADJOURNMENT: 7:03 P.M.