TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD
FROM: MANNY ROBLEDO, DIRECTOR OF UTILITIES
DATE: MAY 18, 2020
SUBJECT: APPROVE A PURCHASE ORDER WITH RS CONSTRUCTION AND
DEVELOPMENT FOR FLOORING, PAINTING, AND LAMINATING OF
THE FIRST FLOOR CUSTOMER SERVICE LOBBY, CONFERENCE ROOM,
HALLWAYS, OFFICES, AND DESKS IN THE AMOUNT OF $65,220.00.
BACKGROUND:
The Azusa Light & Water (ALW) building was built in 1995, and the Customer Service Lobby
Remodel Project was established to provide safety glass to protect employees and ADA upgrades
for customer accessibility. The recommended action would approve a purchase order for paint
and laminate flooring for ALW first floor customer service office, conference room, and lobby
areas as well as the lamination of work surfaces that now require replacement.
RECOMMENDATION:
Staff recommends the Utility Board take the following action:
1)Approve a Purchase Order to RS Construction and Development in an amount not-to-
exceed $65,220.00.
ANALYSIS:
The customer service first floor hallways, offices, and large conference room flooring, paint, and
lamination of customer and employee desks were completed and have been in use since 1995.
The flooring, desks, and counters are used daily by customers, employees, committees, and other
Azusa public groups and is worn out, unsafe, and well beyond its useful life. The flooring has
tiles and carpet that are not fixable, unsafe, and unmatchable due to age and availability. The
paint of the first floor walls has faded and is unable to be cleaned. The replacement of the
flooring, paint, and desk lamination will increase public and employee safety as well as
APPROVED
UTILITY BOARD
5/18/2020
Special Meeting
Approve PO for RS Construction
May 18, 2020
Page 2
accommodate the current Americans with Disabilities Act (ADA) guidelines. The Utilities
Customer Service Department staff has obtained estimates listed below to procure and replace
the L&W building first floor areas of flooring, paint, and lamination with RS Construction being
the lowest for each estimate at a total of $65,220.00.
Customer Service First Floor Painting
1 RS Construction & Development $22,720.00
2 AMS Construction $23,580.00
3 TMB Construction No Bid
Customer Service First Floor Flooring
1 RS Construction & Development $24,950.00
2 AMS Construction $32,250.00
3 Smith Floors and Installations $31,110.00
Desk and Counter Laminate and Shaping
1 RS Construction & Development $17,550.00
2 AMS Construction $19,350.00
3 Serna Cabinets $22,949.00
Staff recommends approving a Purchase Order for RS Construction and Development in the
amount of $65,220.00.
FISCAL IMPACT:
Funds for this project are available in the Consumer Services Division’s Capital Improvement
Program budget Account No. 31-80-711-903-7120/71115A-7120.
Prepared by: Reviewed and Approved:
Danny Smith Manny Robledo
Utilities Admin & Finance Manager Director of Utilities
Reviewed and Approved:
Sergio Gonzalez
City Manager
Approve PO for RS Construction
May 18, 2020
Page 2
Attachment:
1) Painting Cost Estimates
2) Flooring Cost Estimates
3) Laminate and Shaping Estimates
Attachment 1
Attachment 2
Attachment 3