and limited corrosion. With the approval of this Task Order, Staff will coordinate with General
Pump to start repair work immediately so the well can be operational during high demand
summer months.
FISCAL IMPACT:
Funding for Task Order 10 is available in the Water Fund 32, Capital Improvement Project –
Well Rehabilitation Program No. 72120A, account number 32-80-000-721-7130/72120A. The
total project cost is $343,310, which includes a 10% contingency.
Prepared by: Reviewed and Approved:
Melissa Barbosa, P.E. Manny Robledo
Senior Water System Engineer Director of Utilities
Reviewed and Approved:
Jared Macias
Assistant Director of Utilities - Water Operations
Reviewed and Approved:
Sergio Gonzalez
City Manager
Attachment:
1) Task Order 10
UB-782