TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD
FROM: MANNY ROBLEDO, DIRECTOR OF UTILITIES
DATE: JULY 20, 2020
SUBJECT: AWARD A PROFESSIONAL SERVICE AGREEMENT FOR INSPECTION
SERVICES TO MWH CONSTRUCTORS FOR WATER CAPITAL
IMPROVEMENT PROJECT W-277
BACKGROUND:
Azusa Light & Water (“ALW”) has recommended the award of a contract for construction of
Water Capital Improvement Project W-277 Cypress Transmission Water Main Replacement,
involving 6,500 linear feet of water main and appurtenances. If approved, given the size and
scope of this project, ALW will require the services of a dedicated construction inspector to
ensure that the project is constructed as specified. After a solicitation of qualified construction
inspectors, MWH Constructors is recommended as the lowest responsible bidder. The proposed
action would award a Professional Services Agreement (“Agreement”) to MWH Constructors for
full-time construction inspector services during the 180 calendar day project construction period.
RECOMMENDATION:
Staff recommends the Utility Board take the following action:
1) Approve the Professional Services Agreement for Construction Management and
Inspection Services to MWH Constructors for Water Project W-277;
2) Authorize the Mayor to execute the Agreement, in a form acceptable to the City
Attorney.
ANALYSIS:
The Water Division’s Capital Improvement Project W-277 Cypress Transmission Water Main
Replacement includes 6,500 linear feet of water main on Cypress Street, from Azusa Avenue to
APPROVED
UTILITY BOARD
7/20/2020
Award PSA for W-277 Cypress Inspection
July 20, 2020
Page 2
Vincent Avenue, and a portion of work on various parts of Azusa Avenue from Cypress to
Arrow Highway. To ensure proper construction of the project, including safety and installation
procedures, ALW requires the services of a fulltime, on-site, construction inspector.
The responsibilities of the inspector will include, responding to submittal reviews, requests for
information, providing on-site geotechnical work, overseeing quality assurance and quality
control in conformance with plans and specifications, and providing as-built drawings. The
inspector will be required to provide a 24-hour phone number and contact person for the public
to ask questions or report problems. The inspector will also be required to perform after-hour
inspection services, as needed.
Proposals from five (5) consultants were reviewed in the context of the anticipated 180 calendar
day project, and were evaluated based on personnel qualifications, experience inspecting similar
projects, and responsiveness to the requirements of the Request for Proposals (“RFP”).
The proposals and their respective bid pricing, as submitted, were as follows:
1 Stantec Consulting Services, Inc. Failed to submit
2 Stetson Engineering, Inc. Failed to submit
3 MWH Constructors $ 98,750.00
4 Civiltec Engineering Inc. $ 164,005.00
5 NV5 Inc. (formerly Civil Source Inc.) $ 234,597.00
MWH Constructors (“MWH”) was determined to be the lowest, responsible bidder. Based on the
package review and assessment, the lowest bidder met all of the requirements of the RFP.
Accordingly, staff recommends MWH be awarded the Agreement for Construction Management
and Inspection Services for Water Project W-277. It is noteworthy that MWH has provided
successful inspection services on previous capital improvement projects for ALW.
FISCAL IMPACT:
The fiscal impact of the Agreement is $98,750.00. Funding for this service is available, under
Capital Improvement Project W-277 Cypress Transmission Water Main replacement, in Account
No. 32-80-000-721-7145-72116B.
Prepared by: Reviewed and Approved:
Melissa Barbosa, P.E. Manny Robledo
Senior Water System Engineer Director of Utilities
Award PSA for W-277 Cypress Inspection
July 20, 2020
Page 3
Reviewed and Approved:
Jared Macias
Assistant Director of Utilities - Water Operations
Reviewed and Approved:
Sergio Gonzalez
City Manager
Attachment:
1) Professional Service Agreement – Cypress Inspection Services
2) MWH Constructors Proposal
Building a Better World
June 4, 2020
Melissa Barbosa, P.E.
Water System Engineer
729 North Azusa Avenue
Azusa, CA 91702
301 N. Lake Avenue, Suite 115, Pasadena, CA
Subject: Cypress Inspection Services Proposal W-277
Dear Ms. Barbosa,
Azusa Light & Water (ALW) will be selecting a firm to provide Professional Construction Inspection
Services for the Cypress CIP Water Main Replacement Project W-277.
We are proposing Dennis Brown as the Construction Inspector, who has 26 years of experience with
a proven track record of delivering projects within schedule and budget. Dennis brings extensive
communication skills in working with the public, effected communities, and stakeholders to
proactively mitigate issues before they arise. David Dismang will be backing up Dennis, serving as
Quality Assurance and Quality Control.
MWH brings the following advantages to ALW:
Trusted Partner in the Community – We understand the need to develop strong public relations in
order to mitigate construction impacts to the community, adjacent schools and local
businesses. Serving as your Principal-in-Charge, I have worked for most of the major Water
Agencies and City Utilities in the surrounding community. We are committed to serving as your
trusted advisor.
Established Relationship – We have established relationships with several ALW staff from
working together on past CIP projects over the years. We are familiar with ALW’s processes,
procedures, stakeholders, and local issues.
Experienced Local Construction Inspection Experience – We have experienced knowledgeable
personnel with relevant Southern California experience working for numerous local agencies.
Our proposed Construction Inspector, Dennis Brown, brings more than 26 years of construction
experience in municipal water/wastewater facilities, and is committed to be a solutions-oriented
partner with Azusa Light & Water.
We appreciate this opportunity to continue working with ALW and look forward to your response. If
you have any questions or require further information, please contact me at (949) 439-0423 or
randy.lovan@ mwhconstructors.com.
Randy B. Lovan
Southern California Regional Manager
Construction Management Services
Attachment 1
A LW, Cypress CIP Water Main Replacement Project W-227
Azusa Light & Water (ALW) Executive Summary l 1
Executive Summary
MWH’s philosophy is to staff every project with highly experienced, multidisciplined personnel who are
career professionals. Our goal is to be responsive to Azusa Light & Water’s needs, work pro-actively
with the Contractor to keep moving forward, and ensure a quality project is delivered on-time and
within budget.
Wet Infrastructure Experts
MWH’s Construction Management Services Group has been
serving the California wet infrastructure industry by providing
professional CM services since 1970. MWH has managed the
construction, start-up and integration of every type of wet
infrastructure facility that is currently on the market.
1. Staffing Resources
We provide our proposed team organization, including
identification and responsibilities. We provided a brief resume
for our Construction Inspector, Dennis Brown, who has 26
years of experience with a proven track record of delivering
projects within schedule and budget.
2. Proposed Method to
Accomplish the Work
MWH will use proven management and inspection
techniques to identify overall project issues and apply
appropriate controls. We use a flexible approach that allows
us to adapt and modify our management strategy as the
project progresses. MWH’s project management and
inspection approach are based on the application of
consistent practices through the project lifecycle. The MWH
approach to project management provides governance that
results in consistency and efficiency while also allowing
innovative ideas to be tested and incorporated into the overall
delivery process.
3. Fee Proposal
We provide our time and materials, not-to-exceed fee proposal
for the Scope of Services based in the Cypress CIP Water Main
Replacement Project W-277 RFP. MWH’s terms and conditions
are available upon request.
4. Other Information
MWH offers state-wide recognized water and wastewater facility
experience. Our presence in CA since 1945 and extensive
project experience has helped us build a reputation for our
ability to deliver capital improvement projects on time and within
the allocated budget. We offer world-class pipeline and potable
water distribution and treatment system services. We have
been involved with the planning, design, and construction of
more than 300,000 miles of pipelines. Our conveyance services
are focused in the core areas of water and wastewater,
including intakes, pipelines, tunnels, pumping stations, canals,
and reservoirs. Recent similar projects include:
$11M Talavera Water Main Replacement, Phase 2 Project,
Coachella Valley Water District (CVWD), CA. MWH 9.7
miles of 8- inch to 18-inch diameter zinc-coated ductile iron
pipe.
$93M Wastewater Reclamation Project, Phase I Collection
System, Hi-Desert Water District (HDWD), Yucca Valley,
CA. 75 miles of collection system pipeline within the public
right-of way.
$1.4M Azusa Avenue Water Main Replacement Project No.
W-289, Azusa Light & Water (ALW). 4,200 linear feet of 12-
inch ductile iron pipe water main, all associated
appurtenances, pavement replacement, concrete
replacement, street restoration and traffic control.
“The MWH team has been providing comprehensive third-party CM and inspection services... (they have) sound recommendations in dealing
with unforeseen issues and assisted in minimizing conflicts and providing constructive recommendations for resolution of various issues. The
MWH team has been readily available and accessible as circumstances required and an integral and important resource supporting our overall
project.” — Dennis Mejia, P.E., Utilities Engineering Director, Ontario Municipal Utilities Company
A LW, Cypress CIP Water Main Replacement Project W-227
Azusa Light & Water (ALW)
Staffing Resources l 2
Staffing Resources
The MWH Team has expertise in providing Professional Construction Inspection services for water and
wastewater facilities. We are committed to delivering quality Inspection services tailored to the specific
needs of Azusa Light & Water and its stakeholders.
Firm Staffing and Key Personnel
Our Inspection Team brings demonstrated knowledge in potable
water mainline installation Inspection services needed for this
contract and are experienced in resolving the types of construction
issues expected to be encountered on contracts of this complexity.
RE/Construction Inspector
Dennis Brown, RCI, CPII, ICC, Certified Soils
Tester
Dennis brings 26 years of experience that includes resident
engineering and construction inspection, soils compaction
testing, scheduling, contract development/implementation,
owner/client/community relations, project controls, value
engineering, safety, conducting meetings, record drawings,
interfacing with project engineers, labor compliance, contractor
payments, budget development/management, training, RFI/
COR/ PCO/ DCM/ CO development/review, system testing, start
-up and close-out.
$93M Wastewater Reclamation Project, Phase I Collection
System, Hi-Desert Water District, Yucca Valley, CA – Resident
Engineer, PR, Inspection/quality Control Lead. Responsible for
managing and conducting site inspections, management of field
inspection staff, daily inspection reports review for compliance
and posting on electronic document control system
ProjetWise/EADOC by Bentley), resolution of site problems,
preparation of close-out documentation. Installation of over 50
miles of collection system pipeline and private property
connections and replaced existing streets with new roads.
$11M Talavera Water Main Replacement, Coachella Valley Water
District, Indio, CA – Resident Engineer and Inspector. Managed
schedule, budget development, internal/external HOA and
resident communication, field inspection, inspection reporting,
coordination with Engineer of Record. Included review/processing
of all RFIs, CORs and COs. Prepared all payment applications
from the Contractor for review/approval. The project consists of
the replacement of approximately 20,000 linear feet of 8- in, 12-in
and 18-in diameter zinc-coated ductile iron pipe.
On-Call Inspection Services, Coachella Valley Water District
(CVWD) Palm Desert, CA, Senior Inspector, $2M, 2018 - 2019
Provided inspection services to the Coachella Valley Water District
for assigned projects which included gantry crane installations, AC
pavement improvement projects, water treatment plant upgrades
(WRP 10), potable water pipelines, chlorine replacement projects,
sewer pipe installations and video inspection monitoring, well site
drilling and brush and bailing projects, and reservoir rehabilitations.
Also provided oversight of the water district’s third-party soil
compaction and materials testing technicians and scheduled them as
needed
Role and Responsibilities
The RE/Construction Inspector will be responsible for all
assigned activities: MWH’s safety and health plan; project
activities conducted in accordance with the contract, MWH, and
legal; weekly project status reports; coordination with the City;
interfacing with client, Contractors, and vendors; project resource
management; timely responses to Contractor submittals, RFIs,
and other documents; correspondence with Contractor; weekly
progress meetings with the Contractor, client, Design Engineer,
and subcontractor representatives; day-to-day administration of
the contract including review and final recommendation to ALW
on Contractor application of payment, change order requests,
work change directives, and construction schedule updates; final
inspection and issue certificate of substantial completion, and
certificate of final completion; assist with permitting, public
outreach; constructability reviews as requested by the client; pre-
construction conferences; claims submitted by the Contractor;
contract close out with Design Engineer, client, and Contractor;
change order management, scoping, and estimating efforts; and
stakeholder coordination.
Subcontractors/ Subconsultants
MWH will not be utilizing subcontractors to perform construction
management services if awarded this contract.
A LW, Cypress CIP Water Main Replacement Project W-227
Azusa Light & Water (ALW)
Scope & Approach Work l 3
Scope & Approach
Maintaining a consistent approach to delivery, coordination with all key stakeholders, and successful
integration with the Owner’s staff throughout the duration of any long-term project has been proven to be
critical for successful project delivery. Our approach is based on best practices developed, tested,
refined and proven from multiple large capital projects.
Approach
MWH has been providing construction management
services to Southern California clients consistently for the
past few decades. The team will be supported by Principal-
in-Charge, Mr. Randy Lovan. This section contains detailed
descriptions about how the above-specified work will be
executed. Frequent and thorough communication with ALW
staff will be a common element of every assigned task.
Objectives
MWH will maintain focus
on our primary objective,
to serve as facilitators on
behalf of ALW and to the
benefit of the Project. Our
inspection approach
directly supports this
objective by incorporating
the following principles
into our daily processes:
MWH will represent ALW’s best interest – MWH
will represent ALW’s best interest in all matters of the
project while developing a team/ partnering
environment.
MWH will provide leadership – MWH’s lead
personnel are selected and retained because of their
leadership abilities. MWH personnel will provide
leadership, while developing an inclusive team
environment.
MWH will enforce the Contract requirements – MWH
will enforce the Contract requirements of the Project to
ensure that, although ALW and MWH seeks to develop
a team environment with the Contractor, all provisions
of the Project are not compromised.
MWH will take ownership of the project – Each
member of the MWH Project Team will take a “pride of
ownership” approach to the construction of the project,
and will inspect the construction works as if they were
building the project for their own personal use.
MWH will deliver a high-quality project – The “pride of
ownership” and team-oriented approach ensure that
MWH will deliver a lasting, quality project that meets the
durability requirements of a public works facility that will
operate properly for its duration.
MWH’s Approach is designed to achieve these objectives, collaborate with ALW staff; and produce a quality and reliable delivered project within budget and on schedule.
MWHC will provide the following
services:
A. Coordinate the project start and attend all meetings
including preconstruction, field meetings, construction
progress meetings, project close out meetings, etc.
Prepare meeting agenda, and minutes for all meetings.
B. Provide full time inspection of construction work to
assure quality of construction and adherence to
specifications, drawings, and submittals. Inspection will
be provided as needed estimated to require 8 hours per
day each day the work is being executed. Document
daily work progress with written logs and photographs
and submit weekly to the ALW Project Manager. Include
pre-construction photographs, photographs of installation
during construction and post-construction photographs.
In the event that the contractor uses two crews, one
inspector will inspect the work for this project. Generally,
work will take place Monday through Friday. After hours
work or holiday work will occasionally be necessary and
will be paid for by the Construction Contractor.
C. Conduct onsite interviews with contractor workers per the
Specifications & document findings. Verify with certified
payroll reports and report findings to the City.
D. Will meet and maintain the COVID 19 requirements and
the ALW Specifications.
E. Manage requests for change orders by the Contractor.
Provide requests for change orders with documentation
and recommendations to ALW for review and approval.
Implement changes as required and directed by ALW.
F. Maintain record drawings in the field indicating any
changes in the design, materials, dimensions, and
details. Provide red lined "as-built" drawings to ALW.
A LW, Cypress CIP Water Main Replacement Project W-227
Azusa Light & Water (ALW)
Fee Proposal l 4
G. Prepare a "punch list" of all items to be completed by
the Contractor to obtain final completion. Insure all
items are completed.
H. Arrange and conduct the final inspection and start-up
coordination work with the Azusa Light & Water crews
prior to the new facilities being placed into service. Final
inspection to be witnessed by ALW.
I. Will provide 24-hour number and Contact Person for
the Public to answer and field any questions.
J. The construction documents require the Contractor to
supply a soils technician for backfill, compaction,
compaction testing and reports by a licensed
geotechnical engineer MWH will provide a Certified
Compaction Testing Inspector to monitor the
contractor’s backfill, compaction testing, give
recommendations and ensure the contractor submits
Certified Reports for the trench to satisfy and meet City
of Covina Public Works Department & Los Angeles
County Public Works requirements.
K. Provide recommendations to ALW for each progress
payment based on bid item completions.
L. Provide clarification of contract documents; respond to
contractor requests for information and clarification;
review and provide comments and track contractor
submittals, mix designs; review and provide comments
regarding the BMP & SWPPP plan submitted by the
Contractor; review and provide comments regarding the
Solid Waste Management & Recycling plan submitted
by the Contractor; shop drawings, and material
certifications and certificates of compliance; labor
compliance/ equal employment opportunities; obtain
daily roll call submittals; conduct interviews onsite with
Contractor workers; ensure labor compliance.
M. Ensure that the contractor has an established safety
program and that regular safety meetings are
conducted. Ensure that the contractor meets all OSHA
safety requirements. Perform and conduct onsite
interviews with construction workers.
N. Prepare As-Builts including size, type, location of
existing and new utility lines, layout and schematic
drawings of connection details, verification of alignment,
cross sections, location of equipment. As-Builts
required to show all field changes made and
modifications to the construction drawings in detail.
Basis of cost:
The construction documents require the Contractor to supply a
soils technician for backfill, compaction, compaction testing and
reports by a licensed geotechnical engineer. MWH will provide a
Certified Compaction Testing Inspector to monitor the contractor’s
backfill, compaction testing, give recommendations and ensure the
contractor submits Certified Reports for the trench to satisfy and
meet City of Covina Public Works Department & Los Angeles
County Public Works requirements. Our Fee reflects oversight
soils inspection services.
Azusa Light & Water (ALW)
Resume l 5
Dennis Brown RCI, CPII, ICC, CWI, | Resident Engineer/Senior Inspector
Strong planner and problem solver who readily adapts to change,
works independently, and exceeds expectations with a strong focus on
detail and efficiency. Over 26 years of experience in the construction
inspection and materials testing industry. Excellent oral and written
communication skills. Trained in using Primavera P6 and proficient with
Office programs. Interested in career opportunities in Construction
Management with increasing growth and responsibilities.
Project Experience
Wastewater Reclamation Project, High Desert Water District (HDWD), Yucca
Valley, CA, Resident Engineer, $97M, 2019 - 2020
Provided Resident Engineer services in support of the Construction Manager during the
construction of approximately 50+ miles of sewer mainline and associated manholes
and laterals to residential and commercial properties, and three individual project lift
stations. Duties include conducting pre- construction and weekly progress meetings,
document control, reviewing schedules, approving pay estimates, reviewing extra work
invoices, and negotiating and writing change orders.
On-Call Inspection Services, Inland Empire Utilities Agency (IEUA), Inland
Empire, CA, Senior Inspector 2019
Provided inspection services for various projects, including the light pole replacement
and handicap access upgrades in the RP-1 Waste Water Treatment Plant, two manhole
rehabilitation projects in various locations throughout Ontario and Chino, and the
Baseline recycled water pipeline extension project in Fontana.
On-Call Inspection Services, Coachella Valley Water District (CVWD) Palm
Desert, CA, Senior Inspector, $2M, 2018 - 2019
Provided inspection services to the Coachella Valley Water District for assigned projects
which included gantry crane installations, AC pavement improvement projects, water
treatment plant upgrades (WRP 10), Water pipeline, chlorine replacement projects,
sewer pipe installations and video inspection monitoring, well site drilling and brush and
bailing projects, and reservoir rehabilitations. Also provided oversight of the water
district’s third-party soil compaction and materials testing technicians and scheduled
them as needed.
Treatment Plant Modifications and Upgrades – Capital Improvement Projects
• Water Reclamation Plant 10 T2 Tertiary Filter Modifications and Plant B upgrades to
aeration basins and associated piping and sludge pumps
• Water Reclamation Plant 10 Chlorination System Upgrade
Water Storage Reservoir Construction and Rehabilitation – Capital Improvement
Projects
• Water Storage Reservoir 3601-2 Construction
• Water Storage Reservoir 4606-1 Construction
• Water Storage Reservoirs 5643-1 and 5643-2 Rehabilitation
Well Construction and Rehabilitation – Capital Improvement Projects
• Well 4519 Repairs
• Well 4521 Brush, Bail and Replace
Industry Experience
Total MWHC 26 2
Education
John W. North, High School, 1989
Training / Certifications
American Construction Inspectors
Association (ACIA)- Registered
Construction Inspector (Public
Works)
American Public Works Association
(APWA)- Certified Public
Infrastructure Inspector (CPII)
ICC#1066095 Certified Inspector for:
Reinforced Concrete,
Structural Masonry,
Structural Steel and Bolting,
Prestressed Concrete,
Spray-Applied Fireproofing,
Soils, and
Commercial Building.
American Welding Society (AWS)
Certified Welding Inspector (CWI)
#13081941
County of Los Angeles: Concrete,
PT Concrete, Masonry, Structural
Steel Bolting & Welding Inspector
#01919
Concrete Field-Testing Technician,
Grade I: American Concrete Institute
(ACI)
Nuclear Gauge Operator Training
A LW, Cypress CIP Water Main Replacement Project W-227
Azusa Light & Water (ALW)
Fee Proposal l 6
Request for Proposal
Construction Inspection
Services
Cypress CIP Water Main Replacement Project W-
277
Azusa Light & Water (ALW) is requesting a not to exceed proposal to provide Construction
Inspection Services for Project W-277. The inspection services for this water main replacement
is on a high-profile street within multiple jurisdictions. Cost will be a major factor in the
selection of the inspector for this project. In order to allow for overtime and weekend work,
please base your proposed cost on 180 calendar days for the contract duration. Please include
a resume and the name(s) of personnel you intend to use for the project inspection. Please
submit a proposed project scope of work included, items excluded and the not to exceed price
of work for Cypress CIP Water Main Replacement Project W-277.
Construction Inspection Services for Project W-
277
Item Description Price per hour Total Price
1 Construction Inspection Services $ 125.00 $ 89,500.00
2 Certified Compaction Testing during backfill $ 125.00 $ 6,250.00
3 As-Builts $ 125.00 $ 3,000.00
Total Not-To-Exceed Price to Provide Construction
Inspection Services Complete for Project W-277
$ 98,750.00
Company Name: MWH Constructors
Name: Randy Lovan
Phone Number: (949) 439-0423
Authorized Signature:
Date: June 4, 2020