Agenda Item
To: Honorable Mayor and Members of the City Council
From: John Broderick, Chief of Poli
Sam Gonzalez,Lieutenant
Via: Henry Garcia, City Administrator cii)
Date: May 19, 1997
Subject: Change Order#1-Removal of Underground Diesel Storage Tank at Police Facility
and Additional Services from Converse Consultants
Background
The original plans and specifications for the City of Azusa Police Facility Addition and Alteration
Project called for the City to be responsible for the removal of our 3,000 gallon underground diesel
fuel storage tank. This tank supports the department's emergency generator, both of which will be
replaced with new above ground systems. However, at the Police Department's direction, the
architect issued an addendum advising the bidding general contractors to remove the note from the
drawings holding the City responsible for the tank removal. The architect informed us that their were
two such notes and that one should remain.
Findings
The Logic behind leaving one of these notes on the plans, was that due to the very nature of the
uncertainty surrounding the possible contamination, shoring requirements and other uncertainties of
unearthed conditions,contractors would likely include a large lump sum in their base bid to cover the
tank removal. The estimated lump sum would have been in the $100,000 range and regardless of the
actual incurred costs,the City would have probably paid close to the entire lump sum fee. Therefore,
once a contractor was selected, a more prudent approach was to have the contractor provide a more
realistic price for the tank removal via a detailed change order.
Attached is a copy of the change order provided by the Hazama Corporation identifying the various
components necessary for the tank removal. Item #1 is a direct cost for the removal and 2-5 are
allowances and depend upon what is actually encountered in the field. Item#6 addresses plan checks
and permit fees,which will be directly reimbursed to the contractor with no overhead, as was the case
4146(//
&4J/7Z4
725 North Alameda Avenue, Azusa, California 91702-2504
s Zr
with the building permit. Additionally, item #6 addresses required soils testing, which should be
handled by the soils investigator of record, Converse Consultants West. A bid for the required testing
during the tank removal by Converse Consultants West was obtained for a total not-to-exceed fee
of$8,207.
Recommendations
Staff recommends that change order#1 be approved as attached in the amount of not to exceed
$70,400 and that Converse Consultants West be awarded the soils/geo-environmental services in
an amount not to exceed $8,207.
vp-afigy!rimk 0111111k
• Broderick
Chief of Police
•
.- CHANGE
ORDER# 01 D;stz timto:
OWNER FIELD
ARCHITECT OTHER
CONTRACTOR
PROJECT: Azusa Police Facility CHANGE ORDER NUMBER: 01
(name,address) 725 North Alameda Avenue
Azusa, California 91702 INITIATION DATE: 5/13/97
TO(caotrador): Hazama Corporation CONTRACTOR'S PROJECT NO: CA 199
1045 W.Redondo Beach Blvd.,Ste 400
Gardena,CA 90247 CONTRACT FOR: City of Azusa
CONTRACT DATE: 3/3/97
Yon are directed to make the following changes in this Centrad:
Excavate and Remove Existing Diesel Tank
1. Remove Existing Tank including scope of work below (Direct Cost) $11,000.00
Excavation (not including unexpected soil condition-larger than 1/2" rock, etc.), Remove and disposal of existing diesel
fuel, Cleaning and disposal of the tank and pipes. Import and Backfill includes allowance of 35 tons 1/2" rocks.
2. Additional excavation, Import and backfill (Allowance) Allowance $10,000.00
CAT 235 Excavator $750 mobilize. $150/hr. 14 hrs min.) Foreman $65 /hour
Loader $200 mobilize. $115/hr. (4 hrs min.) Laborer $50/hour
Dump Truck $90/hr. (4 hrs min.) Dump fees (construction rubble) $50/ton
Registered Geologist $99/hour Import and Backfill (1/2" rock) $21 /ton
Backhoe $60/hour
3. Remove and dispose contaminated materials (Allowance) Allowance $10,000.00
Remove and disposal of contaminated water& Remove and disposal of contaminated soil &
Transportation $0.65 per gal and $650 per 3,000 gal.min. Transportation $64.75 /ton and $600 per load min.
Removal and disposal of sludge $3.50/gallon Cleaning Labor $75 /hour
4. Design /build shoring system (Allowance) Allowance $13,000.00
Shoring $85.55 /s.f. Casing $18 /s.f.
Coring $550/hour
5. General Condition/Fees (General Condition Allowance of 30 days) Allowance $26,400.00
Delays- General Condition $880/day Bond 0.65%
Overhead /Profit 5% Insurance 0.42%
6. Exclusions
Plan check, Permit & Fees (will be reimbursed)
Soil testing, reports, engineering, utility relocation and removal of concrete footing for tank.
NOTE: All items above with unit price to be finaized in subsequent change order.
Total Amount This Change Order: Will be determined
Not valid u ti signed by both the Owner and Architect.
•
The Original Centrad Sum was $ 2,908,916.00
Net Change by previously authorized Change Orders $ 0.00
The Contract sum prior to this Change Order $ 2,908,916.00
The Contract Sum will be(inaeased) byIbis Change Order $ will be determined
The New Centrad Sum including this Change Order $ 2,908,916.00
The Centrad Time will be(increased)-deer.eeed)(embosged)by will be determined
The Date of Substantial Completion as of the date of this Change Orda therefore is. will be determined
Authorized:
WMM Associates The City of Azusa Hazama Corporation
3731 Wilshire Boulevard Suite 670 725 Nath Alameda Avenue 1045 W.Redondo Beach Blvd,Ste 400
Los Angeles,C)lifornia 90010 Azusa,California 91702 Gardena,California 90247
By: . By: j lora By: U
Date: ^" /.�� 7`�� By: Date: -& 115 ICA—7
LaSalle National Bank Date: ,$-/S-t3