HomeMy WebLinkAboutVI- J Project Contract Award- Traffic Signal Improvements at Gladstone Pasadena CONSENT CALENDAR TO: HONORABLE MAYOR AND CITY COUNCIL MEMBERS FROM: NASSER ABBASZADEH, CITY ENGINEER VIA: RICK COLE, CITY MANAGER DATE: JANUARY 21, 2003 SUBJECT: PROJECT CONTRACT AWARD - TRAFFIC SIGNAL IMPROVEMENTS AT THE INTERSECTION OF GLADSTONE AND PASADENA RECOMMENDATION It is recommended that the City Council: 1. Award the contract for Traffic Signal Improvements at the Intersection of Gladstone and Pasadena to LA Signal, Inc., in the amount of $67,496.00. 2. Approve transfer of $39,736.76 from the project budget to the Traffic Signal Maintenance Account (10-55-651-000-6493, outside services). BACKGROUND On January 14, 2003, the City Clerk’s Office received the following nine bids for the subject project: 1. LA Signal, Inc. $67,496.00 2. Villegas Electric $68,821.00 3. Macadee Electrical $75,750.00 4. Steiny & Company, Inc. $73,269.00 5. Dynalectric $73,514.00 6. Pete & Sons $75,288.00 7. VT Electric, Inc. $75,750.00 8. CT&F Inc. $76,927.00 9. TDS Engineering $104,266.00 Staff has examined the bids and determined that LA Signal Inc. is the low, responsible bidder. Project Background Staff completed a traffic signal warrant study for the intersection of Gladstone and Pasadena previously and recommended the installation of the traffic signal. Funding was an issue for the new signal and on December 2, 2002, City Council approved the transfer of the savings realized in Street Improvements project. The traffic signal will include a two-phase system to allow for alternate movements on Gladstone and Pasadena as well as safe passage for pedestrians crossing Gladstone (the controller will be an eight- phase computer with capabilities for potential expansion, like left turn protective arrows for the east bound, if warranted in the future). FISCAL IMPACT On December 2, 2002, the City Council approved a CIP Amendment to transfer $107,232.76 to this project. Since this project will be completed with $67,496.00, staff is requesting the transfer of the balance of $39,736.76 to the Traffic Signal Maintenance Account (10-55-651-000-6493, outside services). We have recently experienced extra-ordinary maintenance needs at the following locations and the maintenance budget needs to be augmented: 1. The signal at San Gabriel/Fifth with the circa-1946 cabinet and controller collapsed on December 6, 2002. Our initial estimate for the replacement is $14,390. 2. The controller at Citrus/Alosta needed special attention for an estimated cost of $2,000. 3. The cabinet and controller at First/Vernon need to be replaced with a price tag of $28,000.