INFORMATION ITEM
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: ROY BRUCKNER, DIRECTOR OF COMMUNITY DEVELOPMENT
VIA: RICK COLE, CITY MANAGER
DATE: MARCH 17, 2003
SUBJECT: REPORT ON THE MONITORING OF THE MOUNTAIN COVE DEVELOPMENT
The City Council requested a report from Staff concerning the implementation and monitoring of the Mountain
Cove project, and its current status.
BACKGROUND
Mountain Cove, a 327 unit single family residential neighborhood, was approved by the City Council on
1/18/2000, following preparation of a number of environmental and technical studies, an EIR, as well as a Fiscal
Impact Study. The project’s approval was subject to a long list of conditions of approval and mitigation
measures that came out of the EIR and hearing process. The timing of these conditions and mitigation
measures varies in accordance with the progress of construction, with some being required during the pre-
development stage, some during the grading stage, and others during the construction and occupancy stages.
Monitoring of these items are accomplished by the respective divisions and departments of the City during their
normal oversight and inspection process, and coordinated by the Planning Division. In order to obtain a handle
on the implementation and timing of the conditions and mitigation measures, a 3-ring note binder containing
the conditions and mitigation measures was prepared, and organized according to the timing of construction
and responsible party. The organizing headings are as follows:
1. General Conditions
2. Prior to Final Map recording
3. Conditions for Improvement Plans
4. Prior to Grading Permit
5. During Construction
6. Prior to Building Permit Issuance
7. Prior to Certificate of Occupancy
Each respective City Department and Division has its conditions of approval, which are reviewed and
administered during the development and construction phases. The Planning Division monitors the EIR
mitigation measures. As an example, during the grading stage, Engineering did the actual grading inspections,
and ensured compliance with NPDES, while Planning coordinated with the Engineering inspector to ensure that
an archaeologist and Native American expert were present to observe grading operations. Typically, before the
final Certificate of Occupancy is granted, all departments and divisions are given one last opportunity to review
2
the project to make sure all requirements have been met.
CURRENT STATUS
The project is still in its construction phase. To date, a total of 247 building permits have been issued. So far,
106 permits have been finaled and Certificates of Occupancy issued and 60 more are under construction. The
issuance of the permits for the remaining 80 units is anticipated to occur later this year. The first home closing
occurred on May 24, 2002.
UPCOMING MILESTONES
Fiscal Impact. An escrow fund has been established for Fiscal Impact monitoring ($60,000 required payable at
$15,000 per year over 4 years). The current balance of the escrow fund is $30,000. After the 2nd and 4th years
following the first occupancy, the fiscal impact study is to be reviewed, and the City reimbursed from the
escrow account, if the actual impact is determined to be negative during the build-out period. While the first
review would be scheduled on May 24, 2004, given the fact that full build-out will occur by the end of this
current year, with full occupancy shortly thereafter, Staff will require fiscal impact review within this timeframe.
PENDING OR UNRESOLVED ISSUES
Conveyance of Remaining Open Space to the Public. The Developer has not found an entity willing to take the
dedication of the open space. The San Gabriel Rivers and Mountains Conservancy is not interested in taking
ownership. The Developer is currently contacting the Trust for Public Lands to see if there is any interest.
Noise Study. A noise study is required to determine any “fair-share” noise impacts resulting from the project
along San Gabriel Canyon Rd. and along San Gabriel Ave. north of Sierra Madre Ave. This noise analysis has run
into a snag, in that the standards in the City’s noise ordinance are outdated and are geared to “single event”
noise sources. Thus ongoing noise levels cannot be measured using these standards. Staff has directed the
Developer to use common “industry-accepted” thresholds. The study will proceed on this basis.
Wildlife Response Training for Police Officers. The Developer is required to fund a training class for 3 police
officers for responding to wildlife calls. The Police Department advises that the Humane Society, under
contract, handles calls and complaints related to wildlife wandering into the neighborhood. In the
Department’s opinion, therefore, such training for its officers is unnecessary. The Developer, in order to comply
with this condition, will make payment to the City for such a class.
Consultation with Public Transit Agencies for Facilities and Service to the Site. Foothill Transit is not interested
in providing service, according to the Developer. Azusa Transit will be contacted to request that their routes be
modified to include transportation services to the site.
CONCLUSION
Staff will continue to work on the issues noted. The Developer is in compliance with all other conditions and
mitigation measures.