HomeMy WebLinkAboutE-2.1. Approval of the Notice of Completion for the Construction of the Circuit Breaker ExpansionCONSENT CALENDAR
TO: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY
BOARD
FROM: MANNY ROBLEDO, DIRECTOR OF UTILITIES
DATE: MARCH 22, 2021
SUBJECT: APPROVAL OF THE NOTICE OF COMPLETION FOR THE CONSTRUCTION OF
THE CIRCUIT BREAKER EXPANSION AT THE AZUSA SUBSTATION BY
MIRON ELECTRIC CONSTRUCTION INC.
BACKGROUND
During its regular meeting on July 20, 2020, the Azusa Utility Board approved a contract with
Miron Electric Construction (MEC) Incorporated for the construction of the Azusa Substation
Circuit Breaker Expansion Project (Consent item I-15). Staff has inspected the construction of
this project, and determined that it has been completed within the specified timeframe and within
budgeted cost. Staff seeks the Utility Board’s acceptance of Notice of Completion for Project
LD2020-CB-Construction, and the recording thereof in the Office of the County Recorder of Los
Angeles County.
RECOMMENDATION:
Staff recommends the Utility Board take the following action:
1)Find that Miron Electric Construction Inc. has completed the Azusa Substation Circuit
Breaker Expansion in accordance with plans and specifications for Project LD2020-CB-
Construction; and
2)Approve the Notice of Completion; and authorize the Mayor to execute the Notice of
Completion on behalf of the City; and
3)Authorize the City Clerk to submit the Notice of Completion for recordation to the Office of
the County Recorder of Los Angeles County, within ten days of the Utility Board approval,
as required by Section 3093 of the California Civil Code.
E-2Approved
Utility Board
3/22/21
Approve Notice of Completion
March 22, 2021
Page 2
ANALYSIS:
On July 20, 2020 the Utility Board awarded the construction contract to Miron Electric in the amount of
$282,700. Consequently, the Purchase Order #034056 was issued. On August 24, 2020 Staff issued a
Notice to Proceed to Miron Electric. Due to the delay of delivery of material and equipment, Miron
Electric did not start the construction until October 5, 2020. This project was completed on February 24,
2021. Testing and inspections have been performed by Staff to determine that work has been completed
in accordance with plan and specifications for project LD2020-CB-Construction, within specified time
frame and budgeted cost amount.
Due to unknown field conditions at the job site and material changes, Staff has approved and authorized
several change orders for this project. The total amount for the change orders is $16,883.00, which is
6.6% of project base cost of $257,000. The 10% contingency fund budgeted for this project was
sufficient to pay for the change orders.
FISCAL IMPACT:
This project was completed within reasonable schedule, and budget cost of $273,883. Including the cost
of change orders, there is an available balance of $8,817 on PO #034056. Funding for this project is
budgeted for under the Utility’s Capital Improvement Budget Acct #33-80-000-730-7120.
Prepared by: Reviewed and Approved:
Hien K. Vuong Manny Robledo
Assistant Director of Utilities Director of Utilities
Electric Operations
Reviewed and Approved:
Sergio Gonzalez
City Manager