HomeMy WebLinkAboutE-6 Staff Report - Arrow Highway Improvements Project FundingCONSENT ITEM
E-6
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
VIA: SERGIO GONZALEZ, CITY MANAGER
FROM: ROBERT DELGADILLO, P.E., DIRECTOR OF PUBLIC WORKS/CITY
ENGINEER
DATE: MAY 15, 2023
SUBJECT: AUTHORIZE EXCHANGE OF LACTMA LOCAL-RETURN FUNDS AND
MEASURE M FUNDING BETWEEN PHASES I AND II OF THE ARROW
HIGHWAY IMPROVEMENT PROJECTS
BACKGROUND:
On January 17, 2023 the City Council of the City of Azusa (“City”) awarded a contract to Toro
Enterprises, Inc. for the Arrow Highway Street Resurfacing and Highway Safety Improvement
Project, Federal Project No. HSIPL-5112(019) – Phase I. On April 17, 2023 the City Council of
the City of Azusa (“City”) awarded a contract to KASA Construction for the Arrow Highway
Parkway and Median Landscape Improvements Project – Phase II.
RECOMMENDATIONS:
Staff recommends the City Council take the following action:
1) Authorize staff to utilize the $940,00 in LACMTA Local-Return Funds approved for Phase
II to Phase I in exchange for $940,000 in Measure M Funding from Phase I to Phase II.
ANALYSIS:
The Arrow Highway Street Resurfacing and Highway Safety Improvement Project, Federal
Project No. HSIPL-5112(019) – Phase I is funded by $422,700 with Federal HSIP Grant Fund,
$50,000 with Azusa L&W Grant Funds, $840,000 with Senate Bill 1 (SB1-Road Maintenance &
Rehabilitation Account) Funds, and $1,711,577 with Measure M.
Approved
City Council
May 15, 2023
AUTHORIZE EXCHANGE OF LACTMA LOCAL-RETURN AND MEASURE M FUNDING
MAY 15, 2023
Page 2
The Arrow Highway Parkway and Median Landscape Improvements Project – Phase II is funded
by $940,000 with LACMTA Local-Return Funds per Exchange Agreement (STPL Funds
Balance), and $1,005,183.73 with Measure M funds.
The LACMTA Exchange Agreement requires the City to expend the LACMTA Funds on the STP-
L and Highway Infrastructure Program (HIP) Project identified in Exhibit B of the agreement. The
eligible project is the federally-funded Arrow Highway Street Resurfacing and Highway Safety
Improvement Project No. HSIPL-5112(019) – Phase I which includes the installation of the raised
medians instead of the Arrow Highway Parkway and Median Landscape Improvements Project –
Phase II.
ENVIRONMENTAL CLEARANCE:
This action is categorically exempt from the requirements of the California Environmentally
Quality Act (CEQA) pursuant to Section 15301 Class 1 (c) – Rehabilitation of Existing Streets and
Highways. Staff has filed a Notice of Exemption with the Los Angeles County Clerk’s Office.
FISCAL IMPACT:
The recommended actions will have no fiscal impact since funding for both construction projects
were previously approved by Council. Upon council approval of this action, staff will prepare a
budget amendment and add the respective budgets to each construction project accordingly (Phase
I - increase $940,000 in STPL budget and decrease $940,000 in Measure M; and Phase II - decrease
$940,000 in STPL budget and increase $940,000 in Measure M budget under the Public Works
Department). $940,000 in measure M is already included in the FY2022-23 approved budget
under 04-80-000-662-7120/66218B-7120, and upon Council approval and execution of the STPL
grant agreement, staff will prepare a budget amendment and add $940,000 in STPL grant budget
in the public works department for Phase I.
Prepared by: Reviewed by:
Christina Curiel Robert Delgadillo, P.E.
Public Works Project Manager Director of Public Works/ City Engineer
Fiscal Review by: Reviewed and Approved by:
Talika M. Johnson Sergio Gonzalez
Director of Administrative Services City Manager
Attachments:
1) Approved Staff Report 1-17-2023
2) Approved Staff Report 4-17-2023
3) LACMTA Exchange Agreement
CONSENT ITEM
E-12
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
VIA: SERGIO GONZALEZ, CITY MANAGER
FROM: ROBERT DELGADILLO, P.E., DIRECTOR OF PUBLIC WORKS/CITY
ENGINEER
DATE: JANUARY 17, 2023
SUBJECT: AWARD A CONTRACT FOR THE ARROW HIGHWAY STREET
RESURFACING AND HIGHWAY SAFETY IMPROVEMENT PROJECT;
FEDERAL PROJECT NO. HSIPL-5112(019) – PHASE I
BACKGROUND:
On September 19, 2022 the City Council authorized staff to solicit a Notice of Inviting Bids for
the Arrow Highway Street Resurfacing and Highway Safety Improvement Project, Federal Project
No. HSIPL-5112(019) – Phase I. Sealed bids were received on December 21, 2022. The proposed
actions will award the contract to Toro Enterprises, Inc.
RECOMMENDATIONS:
Staff recommends the City Council take the following actions:
1)Award a contract in the amount of $3,024,277, which includes a 10% contingency for
potential change orders as needed, to Toro Enterprises, Inc; and
2)Authorize the City Manager to execute contracts, in a form acceptable to the City Attorney,
on behalf of the City.
ANALYSIS:
The City was awarded a $545,111 in grant funding for preliminary engineering, design,
construction management and construction from the California Department of Transportation
APPROVED
CITY COUNCIL
1/17/2023
Attachment 1
AWARD A CONTRACT FOR THE ARROW HIGHWAY STREET RESURFACING AND
HSIP FEDERAL PROJECT NO. HSIPL-5112(019) – PHASE I
JANUARY 17, 2023
Page 2
(Caltrans) as part of Highway Safety Improvement Program (HSIP). The proposed HSIP project
will incorporate raised median islands with raised median curbs, ADA compliant curb ramps,
minor asphalt concrete paving to address surface drainage, and signing & striping. The proposed
improvements for the Arrow Highway Street Resurfacing Project include pavement resurfacing,
concrete improvements, and signing & striping. The HSIP project improvement limits on Arrow
Highway extend from 500 feet west of Azusa Avenue to Citrus Avenue. In addition, other
pavement improvements (not a part of the federal project) within the City of Azusa and Los
Angeles County jurisdictions from Citrus Avenue to the easterly city boundary (855 feet east of
Citrus Avenue). On April 3, 2017, the City Council adopted Resolution No. 2017-C-22 to enter
into a master agreement, program supplement agreement, fund exchange agreement, and/or fund
transfer agreement with Caltrans for Federal Project No. HSIPL-5112(019).
Sealed bids were received publicly on December 21, 2022. The results are as follows:
No. Company Location Total Bid
1 Toro Enterprises, Inc. Oxnard, CA $2,749,342.70
2 Sully-Miller Contracting Company Brea, CA $3,150,592.00
3 Hardy & Harper Inc. Lake Forest, CA $3,394,695.00
4 All American Asphalt Corona, CA $3,614,428.00
The lowest, responsive bid was submitted by Toro Enterprises, Inc., who has been in business in
Southern California since 1994. Toro Enterprises, Inc. is a general engineering contractor.
ENVIRONMENTAL CLEARANCE:
This action is categorically exempt from the requirements of the California Environmentally
Quality Act (CEQA) pursuant to Section 15301 Class 1 (c) – Rehabilitation of Existing Streets and
Highways. Staff has filed a Notice of Exemption with the Los Angeles County Clerk’s Office.
FISCAL IMPACT:
The recommended actions award a contract Toro Enterprises, Inc. in the amount of $2,749,343
and further authorizes staff to amend the contract up to 10% or $274,934 for a total not-to-exceed
contract amount of $3,024,277. This construction project will be funded by $422,700 with Federal
HSIP Grant Fund 28 (28-80-000-662-7120/66222A-7120), $50,000 with Azusa L&W Grant
Funds (28-80-001-662-7120), $840,000 with Senate Bill 1 (SB1-Road Maintenance &
Rehabilitation Account) Funds, and $1,711,577 with Measure M (Fund # 04). The County will
reimburse the City of Azusa for construction within their jurisdiction. The County’s actual shared
costs will be based upon a final accounting after completion of the project.
Upon council approval, staff will prepare a budget amendment and add the respective budgets
based on what were approved.
AWARD A CONTRACT FOR THE ARROW HIGHWAY STREET RESURFACING AND
HSIP FEDERAL PROJECT NO. HSIPL-5112(019) – PHASE I
JANUARY 17, 2023
Page 3
Prepared by: Reviewed by:
Christina Curiel Robert Delgadillo, P.E.
Public Works Project Manager Director of Public Works/ City Engineer
Fiscal Review by: Reviewed and Approved by:
Talika M. Johnson Sergio Gonzalez
Director of Administrative Services City Manager
Attachment:
1) Public Works Contract
CONTRACT
- 1 -
CITY OF AZUSA STANDARD CONTRACT
ARROW HIGHWAY STREET RESURFACING AND HIGHWAY SAFETY
IMPROVEMENT PROJECT; FEDERAL PROJECT NO. HSIPL-5112 (019) – PHASE I
THIS CONTRACT is made this day of January, 2023, in the County of Los
Angeles, State of California, by and between the City of Azusa, hereinafter called City, and Toro
Enterprises, Inc., hereinafter called Contractor. The City and the Contractor for the
considerations stated herein agree as follows:
ARTICLE 1. SCOPE OF WORK. The Contractor shall perform all Work within the time
stipulated in the Contract and shall provide all labor, materials, equipment, tools, utility services,
and transportation to complete all of the Work required in strict compliance with the Contract
Documents as specified in Article 5 below for the following Project:
ARROW HIGHWAY STREET RESURFACING AND HIGHWAY SAFETY
IMPROVEMENT PROJECT; FEDERAL PROJECT NO. HSIPL-5112 (019) – PHASE I
The Contractor and its surety shall be liable to the City for any damages arising as a result of the
Contractor’s failure to comply with this obligation.
ARTICLE 2. TIME FOR COMPLETION. The Work shall be commenced on the date stated
in the City’s Notice to Proceed. The Contractor shall complete all Work required by the Contract
Documents within 60 working days from the commencement date stated in the Notice to
Proceed. By its signature hereunder, Contractor agrees the time for completion set forth above is
adequate and reasonable to complete the Work.
ARTICLE 3. CONTRACT PRICE. The City shall pay to the Contractor as full compensation
for the performance of the Contract, subject to any additions or deductions as provided in the
Contract Documents, and including all applicable taxes and costs, the sum of Two Million Seven
Hundred Forty Nine Thousand Three Hundred Forty Three Dollars and Zero Cents
($2,749,343.00). Payment shall be made as set forth in the General Conditions.
ARTICLE 4. LIQUIDATED DAMAGES. In accordance with Government Code section
53069.85, it is agreed that the Contractor will pay the City the sum of $4,800 for each and every
calendar day of delay beyond the time prescribed in the Contract Documents for finishing the
Work, as Liquidated Damages and not as a penalty or forfeiture. In the event this is not paid, the
Contractor agrees the City may deduct that amount from any money due or that may become due
the Contractor under the Contract. This Article does not exclude recovery of other damages
specified in the Contract Documents.
ARTICLE 5. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents”
include the following:
Attachment 1
CONTRACT
- 2 -
Notice Inviting Bids
Instructions to Bidders
Bid Form
Contractor’s Certificate Regarding Workers’ Compensation
Bid Bond
Designation of Subcontractors
Information Required of Bidders
Non-Collusion Affidavit form
Contract
Performance Bond
Payment Bond
General Conditions
Special Conditions
Technical Specifications
Addenda
Plans and Drawings
Approved and fully executed change orders
FHWA-1273
Caltrans Exhibit 12-G
Federal Wage Decision
Any other documents contained in or incorporated into the Contract
The Contactor shall complete the Work in strict accordance with all of the Contract Documents.
All of the Contract Documents are intended to be complementary. Work required by one of the
Contract Documents and not by others shall be done as if required by all. This Contract shall
supersede any prior agreement of the parties.
ARTICLE 6. PROVISIONS REQUIRED BY LAW. Each and every provision of law
required to be included in these Contract Documents shall be deemed to be included in these
Contract Documents. The Contractor shall comply with all requirements of the California Labor
Code applicable to this Project.
ARTICLE 7. INDEMNIFICATION. Contractor shall provide indemnification as set forth in
the General Conditions.
ARTICLE 8. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate
of wages in accordance with the Labor Code which such rates shall be made available at Azusa
City Hall or may be obtained online at http//www.dir.ca.gov/dlsr and which must be posted at the
job site.
ARTICLE 9. DECLARATION OF POLITICAL CONTRIBUTIONS. Consultant shall,
throughout the term of this Agreement, submit to City an annual statement in writing declaring
any political contributions of money, in-kind services, or loan made to any member of the city
council within the previous twelve-month period by the Consultant and all of Consultant's
employees, including any employee(s) that Consultant intends to assign to perform the Services
described in this Agreement.
CONTRACT
- 3 -
ARTICLE 10. CONFLICT OF INTEREST. In the procurement of supplies, equipment,
construction, and services by sub-recipients, the conflict of interest provisions in (State LCA –
24 CFR 85.36 and Non-Profit Organizations – 24 CFR 84.4), OMB Circular A-110, and 24 CFR
570.611, respectively, shall apply. No employee, officer or agent of the sub-recipient shall
participate in selection, or in the award or administration of a contract supported by Federal
funds if a conflict of interest, real or apparent, would be involved.
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named
parties, on the day and year above written.
TORO ENTERPRISES, INC.
________________________________
Name and Title
________________________________
Signature of Contractor
License No. ______________________
CITY OF AZUSA
________________________________
Robert Gonzales
Mayor
________________________________
Sergio Gonzalez
City Manager
________________________________
Jeffrey Lawrence Cornejo Jr.
City Clerk
Approved as to Form:
______________________________
Best Best & Krieger LLP
City Attorney
BONDS
- 4 -
PERFORMANCE BOND
FOR
ARROW HIGHWAY STREET RESURFACING AND HIGHWAY SAFETY
IMPROVEMENT PROJECT; FEDERAL PROJECT NO. HSIPL-5112 (019) – PHASE I
KNOW ALL PERSONS BY THESE PRESENTS:
THAT WHEREAS, City of Azusa (hereinafter referred to as “City”) has awarded to Toro
Enterprises, Inc., (hereinafter referred to as the “Contractor”) an agreement for ARROW
HIGHWAY STREET RESURFACING AND HIGHWAY SAFETY IMPROVEMENT
PROJECT; FEDERAL PROJECT NO. HSIPL-5112 (019) – PHASE I (hereinafter referred to as
the “Project”).
WHEREAS, the work to be performed by the Contractor is more particularly set forth in the
Contract Documents for the Project, (hereinafter referred to as “Contract Documents”), the terms
and conditions of which are expressly incorporated herein by reference; and
WHEREAS, the Contractor is required by said Contract Documents to perform the terms thereof
and to furnish a bond for the faithful performance of said Contract Documents.
NOW, THEREFORE, we, Toro Enterprises, Inc., the undersigned Contractor and
_____________________________________________ as Surety, a corporation organized and
duly authorized to transact business under the laws of the State of California, are held and firmly
bound unto the City in the sum of Two Million Seven Hundred Forty Nine Thousand Three
Hundred Forty Three Dollars and Zero Cents ($2,749,343.00), said sum being not less than one
hundred percent (100%) of the total amount of the Contract, for which amount well and truly to
be made, we bind ourselves, our heirs, executors and administrators, successors and assigns,
jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that, if the Contractor, his or its heirs,
executors, administrators, successors or assigns, shall in all things stand to and abide by, and
well and truly keep and perform the covenants, conditions and agreements in the Contract
Documents and any alteration thereof made as therein provided, on its part, to be kept and
performed at the time and in the manner therein specified, and in all respects according to their
intent and meaning; and shall faithfully fulfill all obligations including the one-year guarantee of
all materials and workmanship; and shall indemnify and save harmless the City, its officers and
agents, as stipulated in said Contract Documents, then this obligation shall become null and void;
otherwise it shall be and remain in full force and effect.
As a part of the obligation secured hereby and in addition to the face amount specified therefore,
there shall be included costs and reasonable expenses and fees including reasonable attorney’s
fees, incurred by City in enforcing such obligation.
As a condition precedent to the satisfactory completion of the Contract Documents, unless
otherwise provided for in the Contract Documents, the above obligation shall hold good for a
BONDS
- 5 -
period of one (1) year after the acceptance of the work by City, during which time if Contractor
shall fail to make full, complete, and satisfactory repair and replacements and totally protect the
City from loss or damage resulting from or caused by defective materials or faulty workmanship.
The obligations of Surety hereunder shall continue so long as any obligation of Contractor
remains. Nothing herein shall limit the City’s rights or the Contractor or Surety’s obligations
under the Contract, law or equity, including, but not limited to, California Code of Civil
Procedure section 337.15.
Whenever Contractor shall be, and is declared by the City to be, in default under the Contract
Documents, the Surety shall remedy the default pursuant to the Contract Documents, or shall
promptly, at the City’s option:
(1) Take over and complete the Project in accordance with all terms and conditions in
the Contract Documents; or
(2) Obtain a bid or bids for completing the Project in accordance with all terms and
conditions in the Contract Documents and upon determination by Surety of the
lowest responsive and responsible bidder, arrange for a Contract between such
bidder, the Surety and the City, and make available as work progresses sufficient
funds to pay the cost of completion of the Project, less the balance of the contract
price, including other costs and damages for which Surety may be liable. The
term “balance of the contract price” as used in this paragraph shall mean the total
amount payable to Contractor by the City under the Contract and any
modification thereto, less any amount previously paid by the City to the
Contractor and any other set offs pursuant to the Contract Documents.
(3) Permit the City to complete the Project in any manner consistent with California
law and make available as work progresses sufficient funds to pay the cost of
completion of the Project, less the balance of the contract price, including other
costs and damages for which Surety may be liable. The term “balance of the
contract price” as used in this paragraph shall mean the total amount payable to
Contractor by the City under the Contract and any modification thereto, less any
amount previously paid by the City to the Contractor and any other set offs
pursuant to the Contract Documents.
Surety expressly agrees that the City may reject any contractor or subcontractor which may be
proposed by Surety in fulfillment of its obligations in the event of default by the Contractor.
Surety shall not utilize Contractor in completing the Project nor shall Surety accept a bid from
Contractor for completion of the Project if the CITY, when declaring the Contractor in default,
notifies Surety of the City’s objection to Contractor’s further participation in the completion of
the Project.
The Surety, for value received, hereby stipulates and agrees that no change, extension of time,
alteration or addition to the terms of the Contract Documents or to the Project to be performed
thereunder shall in any way affect its obligations on this bond, and it does hereby waive notice of
BONDS
- 6 -
any such change, extension of time, alteration or addition to the terms of the Contract Documents
or to the Project.
IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of
______________________, 2023.
_________________________________________
CONTRACTOR/PRINCIPAL
_________________________________________
Name
By_______________________________________
SURETY:
By: ______________________________________
Attorney-In-Fact
The rate of premium on this bond is ____________ per thousand. The total amount of premium
charges, $_______________________________.
(The above must be filled in by corporate attorney.)
THIS IS A REQUIRED FORM
Any claims under this bond may be addressed to:
(Name and Address of Surety) ___________________________________________
___________________________________________
___________________________________________
(Name and Address of Agent or ___________________________________________
Representative for service of
process in California, if different ___________________________________________
from above)
___________________________________________
BONDS
- 7 -
(Telephone number of Surety and ___________________________________________
Agent or Representative for service
of process in California
BONDS
- 8 -
STATE OF CALIFORNIA
COUNTY OF
On before me, (here insert
name and title of the officer), personally appeared , who proved
to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to
the within instrument and acknowledged to me that he/she/they executed the same in
his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the
person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under penalty of perjury under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
Signature __________________________________
(Seal)
NOTE: A copy of the Power-of-Attorney to local representatives of the bonding company must
be attached hereto.
BONDS
- 9 -
PAYMENT BOND
FOR
ARROW HIGHWAY STREET RESURFACING AND HIGHWAY SAFETY
IMPROVEMENT PROJECT; FEDERAL PROJECT NO. HSIPL-5112 (019) –
PHASE I
KNOW ALL MEN BY THESE PRESENTS That
WHEREAS, the City of Azusa (hereinafter designated as the “City”) has awarded to Toro Enterprises, Inc., hereinafter designated as the “Principal,” a contract for the work described as follows: ARROW HIGHWAY STREET RESURFACING AND HIGHWAY SAFETY IMPROVEMENT PROJECT; FEDERAL PROJECT NO. HSIPL-5112 (019), – PHASE I (the “Project”); and
WHEREAS, said Principal is required to furnish a bond in connection with said contract; providing that if said Principal or any of its Subcontractors shall fail to pay for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, or for amounts due under the Unemployment Insurance Code or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of said Principal and its Subcontractors with respect to such work or labor the Surety on this bond will pay for the same to the extent hereinafter set forth.
NOW THEREFORE, we, the Principal and __________________________ as Surety, are held and firmly bound unto the City in the penal sum of Two Million Seven Hundred Forty Nine Thousand Three Hundred Forty Three Dollars and Zero Cents ($2,749,343.00) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Section 3181 of the Civil Code, fail to pay for any materials, provisions or other supplies, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or amounts due under the Unemployment Insurance Code with respect to work or labor performed under the contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Section 18663 of the Revenue and Taxation Code, with respect to such work and labor the Surety or Sureties will pay for the same, in an amount not exceeding the sum herein above specified, and also, in case suit is brought upon this bond, all litigation expenses incurred by the City in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses.
This bond shall inure to the benefit of any of the persons named in Section 3181 of the Civil Code so as to give a right of action to such persons or their assigns in any suit brought upon this bond.
BONDS
- 10 -
It is further stipulated and agreed that the Surety on this bond shall not be exonerated or released from the obligation of this bond by any change, extension of time for performance, addition, alteration or modification in, to, or of any contract, plans, specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described, or pertaining or relating to the furnishing of labor, materials, or equipment therefore, nor by any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or work of improvement herein above described, nor by any rescission or attempted rescission or attempted rescission of the contract, agreement or bond, nor by any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or under the bond, nor by any fraud practiced by any person other than the claimant seeking to recover on the bond and that this bond be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner or City and original contractor or on the part of any obligee named in such bond, but the sole conditions of recovery shall be that claimant is a person described in Section 3110 or 3112 of the Civil Code, and has not been paid the full amount of his claim and that Surety does hereby waive notice of any such change, extension of time, addition, alteration or modification herein mentioned.
IN WITNESS WHEREOF, two (2) identical counterparts of this instrument, each of which shall for all purposes be deemed unoriginal thereof, have been duly executed by the Principal and Surety above named, on the _____ day of ______________________ 2021 the name and corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative pursuant to authority of its governing body.
(Corporate Seal of Principal,
if corporation) Principal (Property Name of
Contractor)
By
(Signature of Contractor)
(Seal of Surety)
Surety
By
Attorney in Fact
(Attached Attorney-In-Fact
Certificate and Required
Acknowledgements)
*Note: Appropriate Notarial Acknowledgments of Execution by
Contractor and +surety and a power of Attorney MUST BE ATTACHED.
CONSENT ITEM
E-10
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
VIA: SERGIO GONZALEZ, CITY MANAGER
FROM: ROBERT DELGADILLO, P.E., DIRECTOR OF PUBLIC WORKS/CITY
ENGINEER
DATE: APRIL 17, 2023
SUBJECT: AWARD A CONTRACT FOR THE ARROW HIGHWAY PARKWAY &
MEDIAN LANDSCAPE IMPROVEMENTS PROJECT – PHASE II; AND
ENTER INTO A MEMORANDUM OF UNDERSTANDING WITH THE
CITY OF COVINA
BACKGROUND:
On September 19, 2022 the City Council authorized staff to solicit a Notice of Inviting Bids for
the Arrow Highway Street Resurfacing and Highway Safety Improvement Project – Phase I and
Phase II. The proposed improvements in Phase II include median landscaping, irrigation, and
parkway improvements within Azusa, Covina and Los Angeles County jurisdictions. Sealed bids
were received on March 22, 2023. The proposed actions will award a contract to KASA
Construction for the improvements included in the Base Bid and Alternate Bid Schedules, and will
authorize the City Manager to execute a Memorandum of Understanding with the City of Covina
for the construction of improvements within Covina’s jurisdiction.
RECOMMENDATIONS:
Staff recommends the City Council take the following actions:
1)Award a contract in the amount of $1,945,183.73, which includes a contingency in the
amount of $105,125.48 for potential change orders as needed, to KASA Construction; and
2) Authorize the City Manager to execute a Memorandum of Understanding with the City of
Covina for a not to exceed amount of $698,569.70 for the construction of the Arrow
Highway Parkway and Median Landscape Improvements within Covina’s jurisdiction; and
Approved
City Council
April 17, 2023
Attachment 2
AWARD A CONTRACT FOR THE ARROW HIGHWAY PARKWAY & MEDIAN
LANDSCAPE IMPROVEMENTS PROJECT – PHASE II
APRIL 17, 2023
Page 2
3)Authorize the City Manager to execute contracts, in a form acceptable to the City Attorney,
on behalf of the City.
ANALYSIS:
The City of Azusa is currently under contract with Toro Enterprises, Inc. for the construction of
the Arrow Highway improvements in Phase I which includes the installation of raised median
islands, street resurfacing, signage & striping, and traffic signal modifications. The proposed
improvements in Phase II for the Arrow Highway Parkway and Median Landscape Improvements
Project includes landscaping and irrigation in the raised median islands and parkway areas located
within the City of Azusa, City of Covina and Los Angeles County jurisdictions along Arrow
Highway from 500 feet west of Azusa Avenue to 855 feet east of Citrus Avenue.
As a part of the Phase II improvements, an alternate bid schedule was included in the contract bid
forms for proposed improvements throughout the project limits that fall within the City of Covina.
By entering into this memorandum of understanding, the City of Azusa is acting as the lead agency
for the project and the City of Covina will be providing payment for those improvements made
within their jurisdiction.
Sealed bids were received publicly on March 22, 2023. The results are as follows:
No. Company Location Total Base Bid
1 KASA Construction Chino, CA $1,051,254.75
2 Marina Landscape, Inc. Orange, CA $1,142,653.00
3 Southern California Landscape, Inc. Fontana, CA $1,214,217.05
4 Mariposa Landscape, Inc. Irwindale, CA $1,292,238.36
5 C.S. Legacy Construction, Inc.Walnut, CA $1,394,161.35
The lowest, responsive bid was submitted by KASA Construction who has been in business in
Southern California since 2008. KASA Construction is a general and landscape contractor which
holds additional contractor licenses including Class B and C-10.
ENVIRONMENTAL CLEARANCE:
This action is categorically exempt from the requirements of the California Environmentally
Quality Act (CEQA) pursuant to Section 15301 Class 1 (c) – Rehabilitation of Existing Streets and
Highways. Staff has filed a Notice of Exemption with the Los Angeles County Clerk’s Office.
AWARD A CONTRACT FOR THE ARROW HIGHWAY PARKWAY & MEDIAN
LANDSCAPE IMPROVEMENTS PROJECT – PHASE II
APRIL 17, 2023
Page 3
FISCAL IMPACT:
The recommended actions award a contract to KASA Construction in the amount of $1,840,058.25
(Base Bid $1,051,254.75 + Alternate Bid $788,803.50) and further authorizes staff to amend the
contract up to 10% of the Base Bid Price or $105,125.48 for a total not-to-exceed contract amount
of $1,945,183.73. This construction project will be funded by $940,000 with LACMTA Local-
Return Funds per Exchange Agreement (STPL Funds Balance), and $1,005,183.73 with available
Measure M funds. Upon Council approval, staff will prepare a budget amendment and increase
$940,000 in STPL budget and $1,005,183.73 in Measure M budget under the Public Works
Department.
The City of Azusa has agreed to fund the landscaping improvements within the County’s
jurisdiction per the Cooperative Agreement approved by Council on April 5, 2022.
Per the Memorandum of Understanding (MOU), the City of Covina shall reimburse the City of
Azusa for construction administration services and improvements constructed within the City of
Covina’s right of way as a part of this project. The total estimated cost for Covina’s improvements
is $698,569.70. Any increases related to the construction of the project will be reflected in an
amendment to the proposed agreement. Covina’s actual shared costs will be based upon a final
accounting after completion of the project. After the City of Covina reimburses the City of Azusa
for the stated scope of work in the amount of $698,569.70, the net project costs will be
$1,246,614.03 ($1,945,183.73 - $698,569.70)
Prepared by: Reviewed by:
Christina Curiel Robert Delgadillo, P.E.
Public Works Project Manager Director of Public Works/ City Engineer
Fiscal Review by: Reviewed and Approved by:
Talika M. Johnson Sergio Gonzalez
Director of Administrative Services City Manager
Attachment:
1) Public Works Contract
2) KASA Construction Bid
3) MOU between the City of Azusa and the City of Covina
CONTRACT
- 1 -
CITY OF AZUSA STANDARD CONTRACT
ARROW HIGHWAY PARKWAY AND MEDIAN LANDSCAPE IMPROVEMENTS
PROJECT – PHASE II
THIS CONTRACT is made this __ day of April, 2023, in the County of Los Angeles,
State of California, by and between the City of Azusa, hereinafter called City, and KASA
Construction, Inc., hereinafter called Contractor. The City and the Contractor for the
considerations stated herein agree as follows:
ARTICLE 1. SCOPE OF WORK. The Contractor shall perform all Work within the time
stipulated in the Contract and shall provide all labor, materials, equipment, tools, utility services,
and transportation to complete all of the Work required in strict compliance with the Contract
Documents as specified in Article 5 below for the following Project:
ARROW HIGHWAY PARKWAY AND MEDIAN LANDSCAPE IMPROVEMENTS
PROJECT – PHASE II
The Contractor and its surety shall be liable to the City for any damages arising as a result of the
Contractor’s failure to comply with this obligation.
ARTICLE 2. TIME FOR COMPLETION. The Work shall be commenced on the date stated
in the City’s Notice to Proceed. The Contractor shall complete all Work required by the Contract
Documents within 60 working days from the commencement date stated in the Notice to
Proceed. By its signature hereunder, Contractor agrees the time for completion set forth above is
adequate and reasonable to complete the Work.
ARTICLE 3. CONTRACT PRICE. The City shall pay to the Contractor as full compensation
for the performance of the Contract, subject to any additions or deductions as provided in the
Contract Documents, and including all applicable taxes and costs, the sum of One Million Eight
Hundred Forty Thousand Fifty Eight Dollars and Twenty Five Cents ($1,840,058.25). Payment
shall be made as set forth in the General Conditions.
ARTICLE 4. LIQUIDATED DAMAGES. In accordance with Government Code section
53069.85, it is agreed that the Contractor will pay the City the sum of $500 for each and every
calendar day of delay beyond the time prescribed in the Contract Documents for finishing the
Work, as Liquidated Damages and not as a penalty or forfeiture. In the event this is not paid, the
Contractor agrees the City may deduct that amount from any money due or that may become due
the Contractor under the Contract. This Article does not exclude recovery of other damages
specified in the Contract Documents.
ARTICLE 5. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents”
include the following:
Attachment 1
CONTRACT
- 2 -
Notice Inviting Bids
Instructions to Bidders
Bid Form
Contractor’s Certificate Regarding Workers’ Compensation
Bid Bond
Designation of Subcontractors
Information Required of Bidders
Non-Collusion Affidavit form
Contract
Performance Bond
Payment Bond
General Conditions
Special Conditions
Technical Specifications
Addenda
Plans and Drawings
Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract
The Contactor shall complete the Work in strict accordance with all of the Contract Documents.
All of the Contract Documents are intended to be complementary. Work required by one of the
Contract Documents and not by others shall be done as if required by all. This Contract shall
supersede any prior agreement of the parties.
ARTICLE 6. PROVISIONS REQUIRED BY LAW. Each and every provision of law
required to be included in these Contract Documents shall be deemed to be included in these
Contract Documents. The Contractor shall comply with all requirements of the California Labor
Code applicable to this Project.
ARTICLE 7. INDEMNIFICATION. Contractor shall provide indemnification as set forth in
the General Conditions.
ARTICLE 8. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate
of wages in accordance with the Labor Code which such rates shall be made available at Azusa
City Hall or may be obtained online at http//www.dir.ca.gov/dlsr and which must be posted at the
job site.
ARTICLE 9. DECLARATION OF POLITICAL CONTRIBUTIONS. Consultant shall,
throughout the term of this Agreement, submit to City an annual statement in writing declaring
any political contributions of money, in-kind services, or loan made to any member of the city
council within the previous twelve-month period by the Consultant and all of Consultant's
employees, including any employee(s) that Consultant intends to assign to perform the Services
described in this Agreement.
ARTICLE 10. CONFLICT OF INTEREST. In the procurement of supplies, equipment,
construction, and services by sub-recipients, the conflict of interest provisions in (State LCA –
CONTRACT
- 3 -
24 CFR 85.36 and Non-Profit Organizations – 24 CFR 84.4), OMB Circular A-110, and 24 CFR
570.611, respectively, shall apply. No employee, officer or agent of the sub-recipient shall
participate in selection, or in the award or administration of a contract supported by Federal
funds if a conflict of interest, real or apparent, would be involved.
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named
parties, on the day and year above written.
KASA CONSTRUCTION, INC.
________________________________
Name and Title
________________________________
Signature of Contractor
License No. ______________________
CITY OF AZUSA
________________________________
Robert Gonzales
Mayor
________________________________
Sergio Gonzalez
City Manager
________________________________
Jeffrey Lawrence Cornejo Jr.
City Clerk
Approved as to Form:
______________________________
Best Best & Krieger LLP
City Attorney
BONDS
- 4 -
PERFORMANCE BOND
FOR
ARROW HIGHWAY PARKWAY AND MEDIAN LANDSCAPE IMPROVEMENTS
PROJECT – PHASE II
KNOW ALL PERSONS BY THESE PRESENTS:
THAT WHEREAS, City of Azusa (hereinafter referred to as “City”) has awarded to KASA
Construction, Inc., (hereinafter referred to as the “Contractor”) an agreement for ARROW
HIGHWAY PARKWAY AND MEDIAN LANDSCAPE IMPROVEMENTS PROJECT -
PHASE II (hereinafter referred to as the “Project”).
WHEREAS, the work to be performed by the Contractor is more particularly set forth in the
Contract Documents for the Project, (hereinafter referred to as “Contract Documents”), the terms
and conditions of which are expressly incorporated herein by reference; and
WHEREAS, the Contractor is required by said Contract Documents to perform the terms thereof
and to furnish a bond for the faithful performance of said Contract Documents.
NOW, THEREFORE, we, KASA Construction, Inc., the undersigned Contractor and
_____________________________________________ as Surety, a corporation organized and
duly authorized to transact business under the laws of the State of California, are held and firmly
bound unto the City in the sum of One Million Eight Hundred Forty Thousand Fifty Eight
Dollars and Twenty Five Cents ($1,840,058.25), said sum being not less than one hundred
percent (100%) of the total amount of the Contract, for which amount well and truly to be made,
we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and
severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that, if the Contractor, his or its heirs,
executors, administrators, successors or assigns, shall in all things stand to and abide by, and
well and truly keep and perform the covenants, conditions and agreements in the Contract
Documents and any alteration thereof made as therein provided, on its part, to be kept and
performed at the time and in the manner therein specified, and in all respects according to their
intent and meaning; and shall faithfully fulfill all obligations including the one-year guarantee of
all materials and workmanship; and shall indemnify and save harmless the City, its officers and
agents, as stipulated in said Contract Documents, then this obligation shall become null and void;
otherwise it shall be and remain in full force and effect.
As a part of the obligation secured hereby and in addition to the face amount specified therefore,
there shall be included costs and reasonable expenses and fees including reasonable attorney’s
fees, incurred by City in enforcing such obligation.
As a condition precedent to the satisfactory completion of the Contract Documents, unless
otherwise provided for in the Contract Documents, the above obligation shall hold good for a
period of one (1) year after the acceptance of the work by City, during which time if Contractor
shall fail to make full, complete, and satisfactory repair and replacements and totally protect the
City from loss or damage resulting from or caused by defective materials or faulty workmanship.
BONDS
- 5 -
The obligations of Surety hereunder shall continue so long as any obligation of Contractor
remains. Nothing herein shall limit the City’s rights or the Contractor or Surety’s obligations
under the Contract, law or equity, including, but not limited to, California Code of Civil
Procedure section 337.15.
Whenever Contractor shall be, and is declared by the City to be, in default under the Contract
Documents, the Surety shall remedy the default pursuant to the Contract Documents, or shall
promptly, at the City’s option:
(1) Take over and complete the Project in accordance with all terms and conditions in
the Contract Documents; or
(2) Obtain a bid or bids for completing the Project in accordance with all terms and
conditions in the Contract Documents and upon determination by Surety of the
lowest responsive and responsible bidder, arrange for a Contract between such
bidder, the Surety and the City, and make available as work progresses sufficient
funds to pay the cost of completion of the Project, less the balance of the contract
price, including other costs and damages for which Surety may be liable. The
term “balance of the contract price” as used in this paragraph shall mean the total
amount payable to Contractor by the City under the Contract and any
modification thereto, less any amount previously paid by the City to the
Contractor and any other set offs pursuant to the Contract Documents.
(3) Permit the City to complete the Project in any manner consistent with California
law and make available as work progresses sufficient funds to pay the cost of
completion of the Project, less the balance of the contract price, including other
costs and damages for which Surety may be liable. The term “balance of the
contract price” as used in this paragraph shall mean the total amount payable to
Contractor by the City under the Contract and any modification thereto, less any
amount previously paid by the City to the Contractor and any other set offs
pursuant to the Contract Documents.
Surety expressly agrees that the City may reject any contractor or subcontractor which may be
proposed by Surety in fulfillment of its obligations in the event of default by the Contractor.
Surety shall not utilize Contractor in completing the Project nor shall Surety accept a bid from
Contractor for completion of the Project if the CITY, when declaring the Contractor in default,
notifies Surety of the City’s objection to Contractor’s further participation in the completion of
the Project.
The Surety, for value received, hereby stipulates and agrees that no change, extension of time,
alteration or addition to the terms of the Contract Documents or to the Project to be performed
thereunder shall in any way affect its obligations on this bond, and it does hereby waive notice of
any such change, extension of time, alteration or addition to the terms of the Contract Documents
or to the Project.
BONDS
- 6 -
IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of
______________________, 2023.
_________________________________________
CONTRACTOR/PRINCIPAL
_________________________________________
Name
By_______________________________________
SURETY:
By: ______________________________________
Attorney-In-Fact
The rate of premium on this bond is ____________ per thousand. The total amount of premium
charges, $_______________________________.
(The above must be filled in by corporate attorney.)
THIS IS A REQUIRED FORM
Any claims under this bond may be addressed to:
(Name and Address of Surety) ___________________________________________
___________________________________________
___________________________________________
(Name and Address of Agent or ___________________________________________
Representative for service of
process in California, if different ___________________________________________
from above)
___________________________________________
(Telephone number of Surety and ___________________________________________
Agent or Representative for service
of process in California
BONDS
- 7 -
STATE OF CALIFORNIA
COUNTY OF
On before me, (here insert
name and title of the officer), personally appeared , who proved
to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to
the within instrument and acknowledged to me that he/she/they executed the same in
his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the
person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under penalty of perjury under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
Signature __________________________________
(Seal)
NOTE: A copy of the Power-of-Attorney to local representatives of the bonding company must
be attached hereto.
BONDS
- 8 -
PAYMENT BOND
FOR
ARROW HIGHWAY PARKWAY AND MEDIAN LANDSCAPE
IMPROVEMENTS PROJECT - PHASE II
KNOW ALL MEN BY THESE PRESENTS That
WHEREAS, the City of Azusa (hereinafter designated as the “City”) has awarded to KASA Construction, Inc., hereinafter designated as the “Principal,” a contract for the work described as follows: ARROW HIGHWAY PARKWAY AND MEDIAN LANDSCAPE IMPROVEMENTS PROJECT – PHASE II (the “Project”); and
WHEREAS, said Principal is required to furnish a bond in connection with said contract; providing that if said Principal or any of its Subcontractors shall fail to pay for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, or for amounts due under the Unemployment Insurance Code or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of said Principal and its Subcontractors with respect to such work or labor the Surety on this bond will pay for the same to the extent hereinafter set forth.
NOW THEREFORE, we, the Principal and __________________________ as Surety, are held and firmly bound unto the City in the penal sum of One Million Eight Hundred Forty Thousand Fifty Eight Dollars and Twenty Five Cents ($1,840,058.25) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Section 3181 of the Civil Code, fail to pay for any materials, provisions or other supplies, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or amounts due under the Unemployment Insurance Code with respect to work or labor performed under the contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Section 18663 of the Revenue and Taxation Code, with respect to such work and labor the Surety or Sureties will pay for the same, in an amount not exceeding the sum herein above specified, and also, in case suit is brought upon this bond, all litigation expenses incurred by the City in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses.
This bond shall inure to the benefit of any of the persons named in Section 3181 of the Civil Code so as to give a right of action to such persons or their assigns in any suit brought upon this bond.
It is further stipulated and agreed that the Surety on this bond shall not be exonerated or released from the obligation of this bond by any change, extension of time for
BONDS
- 9 -
performance, addition, alteration or modification in, to, or of any contract, plans, specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described, or pertaining or relating to the furnishing of labor, materials, or equipment therefore, nor by any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or work of improvement herein above described, nor by any rescission or attempted rescission or attempted rescission of the contract, agreement or bond, nor by any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or under the bond, nor by any fraud practiced by any person other than the claimant seeking to recover on the bond and that this bond be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner or City and original contractor or on the part of any obligee named in such bond, but the sole conditions of recovery shall be that claimant is a person described in Section 3110 or 3112 of the Civil Code, and has not been paid the full amount of his claim and that Surety does hereby waive notice of any such change, extension of time, addition, alteration or modification herein mentioned.
IN WITNESS WHEREOF, two (2) identical counterparts of this instrument, each of which shall for all purposes be deemed unoriginal thereof, have been duly executed by the Principal and Surety above named, on the _____ day of ______________________ 2021 the name and corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative pursuant to authority of its governing body.
(Corporate Seal of Principal,
if corporation) Principal (Property Name of
Contractor)
By
(Signature of Contractor)
(Seal of Surety)
Surety
By
Attorney in Fact
(Attached Attorney-In-Fact
Certificate and Required
Acknowledgements)
*Note: Appropriate Notarial Acknowledgments of Execution by
Contractor and +surety and a power of Attorney MUST BE ATTACHED.
Agreement Number 9200000000HIP2140
1
EXCHANGE AGREEMENT AND ASSIGNMENT OF FEDERAL SURFACE
TRANSPORTATION PROGRAM -LOCAL AND HIGHWAY INFRASTRUCT URE
PROGRAMS FUNDS
This Exchange Agreement and Assignment of Federal Surface Transportation Program-Local and
Highway Infrastructure Programs Funds ("AGREEMENT"), is made and entered into as of
July 1, 2022, by and between the City of Azusa ("CITY") and the Los Angeles County
Metropolitan Transportation Authority ("LACMTA").
RECITALS:
CITY is eligible for and has available Federal Surface Transportation Program-Local ("STP-L
Funds") and Highway Infrastructure Programs funds ("HIP Funds").
A.CITY desires to exchange $971,834 of CITY's STP-L Funds ("STP-L Funds Balance") and
its total allocation of $231,475 of CITY's HIP Funds ("HIP Funds Balance") that LACMTA
approved on April 22, 2021 for a like total amount of $1,203,309 of LACMTA Local
Transportation Funds ("LACMTA Funds").
B.LACMTA is willing to exchange $1,203,309 in LACMTA Funds for a like total amount of
CITY's STP-L Funds and CITY's HIP Funds subject to the terms and conditions contained
herein.
C.An exchange of CITY's STP-L Funds and CITY's HIP Funds with LACMTA Funds is
beneficial to and in the general interest of CITY and LACMTA.
NOW THEREFORE, in consideration of the mutual benefits to be derived by CITY and
LACMTA, and of the promises contained herein, it is hereby agreed as follows:
AGREEMENT:
1.CITY hereby assigns to LACMTA $971,834 of CITY's STP -L Funds and $231,475
of CITY's HIP Funds. LACMTA shall be authorized to deduct such amount s from CITY's
STP-L Funds Balance and CITY's HIP Funds Balance, respectively. This assignment shall be
automatically effective upon full execution of this AGREEMENT without the necessity of
the execution, delivery or recording of any further instrument whatsoever. Notwithstanding
the foregoing, at LACMTA's request, CITY shall execute and deliver such documents and
instruments as may be required to evidence such assignment of STP-L Funds and HIP Funds.
2.LACMTA hereby accepts CITY's assignment of CITY's STP-L Funds and CITY's HIP
Funds for use on federal-aid eligible project(s), to be determined by LACMTA in its sole and
absolute discretion.
Attachment 3
Agreement Number 9200000000HIP2140
2
3.Upon receipt of (i) a fully executed AGREEMENT, (ii) CITY's written certification of
the amount s of CITY's STP -L Funds Balance and CITY's HIP Fund s Balance, as defined
herein, whic h CITY's STP -L Funds Balance and CITY’s HIP Funds Balance show that
CITY has sufficient STP -L Funds and HIP Funds to meet its obligations hereunder, and (iii)
LACMTA's deduction of CITY's STP-L Funds and CITY's HIP Funds as provided in
paragraph 1 above, LACMTA shall pay CITY $1,179,242 of LACMTA Funds which
includes the deduction for the processing fee describ ed in paragraph 5 below. For purposes
of this AGREEMENT, CITY's "STP -L Funds Balance" and CITY's "HIP Funds Balance "
shall mean the amount s of funds contained in CITY's STP -L Funds and CITY's HIP Funds
accounts as of the date that this AGREEMENT is fully executed , which include CITY's
apportionment share of FY22 STP-L Fund s and share of HIP Funds from the federal
Coronavirus Response and Relief Supplemental Appropriations Act (CRRSAA) that was
enacted on December 27, 2020 . If the STP -L Funds Balance and HIP Funds Balance become
insufficient to satisfy CITY's exchange obligations hereunder, CITY hereby authorizes
LACMTA to deduct from CITY's future balance of STP-L funds until LACMTA has in the
aggregate received the amount of CITY's STP -L Funds and CITY's HIP Funds specified in
paragraph 1 above.
4.CITY must complete an d submit an Automated Clearing House (ACH) form (Exhibit
A) through LACMTA 's website to allow LACMTA to ma ke disbursements electronically.
Disbursements via ACH will be made at no cost to CITY. If electronic disbursements are
not the preferred method of disbursement, CITY may request an exception in writing.
5.CITY shall pay LACMTA a two -percent (2%) processing and administrative fee (the
"Processing Fee") in connection with the exchange contemplated by this AGREEMENT.
The Processing Fee shall be assessed against the total amount of LACMTA Funds payable
to CITY. CITY hereby authorizes LACMTA to d educt the Processing Fee from the amount
LACMTA is to pay CITY hereunder.
6.CITY shall expend the LACMTA Funds on an STP -L and HIP Eligible Project and by
the Lapsing Date , consistent with the Statement of Work , Schedule and Budget provided in
Exhibit B . For the purposes of this AGREEMENT, the "Lapsing Date" shall mean the date
that is three (3) years from the date that this AGREEMENT is fully executed. Any
LACMTA Funds not expended by the Lapsing Date shall lapse and be returned to LACMTA
within thirty (30) days of the Lapsing Date for further programming to third parties as
LACMTA determines in its sole discretion.
A.For the purposes of this AGREEMENT, the term "Eligible Project " shall mean
the transportation activities described in Exhibit B that: i) would normally qualify
under S ection 133(b) of Title 23, U.S.C : or ii) are for costs related to preventive
maintenance, routine maintenance, debt service payments, availability payments,
operations, personnel (including salaries of employees and those employees who
have been placed on administrative leave , or contractors), and coverage for other
revenue losses due to the coronavirus pandemic . Any other applicable federal
regulations and standards related to procur ement and project delivery issues may
be substituted with applicable state and local regulations, standards, and policies.
Agreement Number 9200000000HIP2140
3
B. The term "expend" as used in Section 6 shall mean "encumbered by an awarded
contract or paid for an eligible transportation activity ".
C. If the LACMTA Funds have lapsed and CITY has not returned all or a portion of
the lapsed LACMTA Funds to LACMTA, then CITY shall be considered to be in
default and agrees that such outstanding payments shall be paid from CITY fun ds
in the following priority: first, from any of CITY 's unobligated HIP Funds
Balance, then from CITY 's STP-L Funds Balance , then from CITY's Proposition
A local return funds, then from CITY 's Propo sition C local return funds, then
from CITY 's Measure R local return funds , and then from CITY 's Measure M
local return funds . If CITY is in default hereunder, in addition to all rights and
remedies available to LACMTA at law or in equity and without further notice or
ability to cure by CITY, CITY her eby authorizes LACMTA to withhold the
applicable HIP, STP -L or local return funds in the amount needed to satisfy the
outstanding amount of lapsed LACMTA Funds due and owing to LACMTA prior
to LACMTA transferring the balance of such funds to the CITY in accordance
with the applicable state laws or ordinances.
7. CITY must use the LACMTA Funds in the most cost -effective manner. If CITY
intends to use a consultant or contractor to imp lement all or part of the STP -L and HIP
Eligible Project, LACMTA requires that such activities be procured in accordance with
CITY's contracting procedures and be consistent with State law as appropriate. CITY will
also use the LACMTA Funds in the most cost -effective manner when the LACMTA Funds
are used to pay "in -hous e" staff time. CITY staff or consultants with project oversight roles
may not award work to companies in which they have a financial or personal interest. This
effective use of funds provision will be verified by LACMTA through on -going project
monitoring and through any LACMTA interim and final audits.
8. LACMTA, and/or its designee, shall have the right to conduct audits of CITY's use of
the LACMTA Funds, as deemed appropriate, such as financial and compliance audits;
interim audits; pre -award audits, perfo rmance audits, and final audits. CITY agrees to
establish and maintain proper accounting procedures and cash management records and
documents in accordance with Generally Accepted Accounting Principles (GAAP). CITY's
records shall include, without limitati on, any supporting evidence deemed necessary by
LACMTA to substantiate CITY's use of LACMTA Funds. These records must be retained
by CITY for five years following CITY's last use of the LACMTA Funds. CITY shall
reimburse LACMTA for any expenditure not in c ompliance with the Scope of Work and/or
not in compliance with other terms and conditions of this AGREEMENT. The eligibility of
costs for CITY's own expenditures submitted to LACMT A for the Eligible Project shall be
in compliance with Office of Management and Budget (OMB) Circular A -87 (relocated to
Title 2 in the Code of Federal Regulations , Subtitle A, Chapter II, part 225 ). The eligibility
of costs for CITY's contractors, consultants, and suppliers expenditures submitted to
LACMTA through CITY's Monthly Progress Reports and Quarterly Expenditures shall be in
compliance with OMB Circular A -87 (as relocated) or Federal Acquisition Regulation
(FAR) Subpart 31 (whichever is applicable). Findings of the LACMTA audit are final.
When LACMTA audit findings requir e CITY to return monies to LACMTA, CITY agrees to
Agreement Number 9200000000HIP2140
4
return the monies within thirty (30) days after the final audit is sent to CITY.
9. The terms of this AGREEMENT shall commence on the date that this AGREEMENT
is fully executed and shall terminate once CITY ha s expended all the LACMTA Funds and
all LACMTA audit and reporting requirements have been satisfied.
10. CITY shall fully indemnify, defend and hold LACMTA and its officers, agents, and
employees harmless from and against any liability and expenses, including, without
limitation, defend costs, any costs or liability on account of bodily injury, death or personal
injury of any person, or for damages of any nature whatsoever arising out of (i) a breach of
CITY's obligations under this AGREEMENT; or (ii) any act or omission of CITY or its
officers, agents, employees, contractors, or subcontractors in the use of the LACMTA
Funds.
11. LACMTA shall fully indemnify, defend and hold CITY and its officers, agents, and
employees harmless from and against any liability and expenses, including, without limitation,
defend costs, any costs or liability on account of bodily injury, death or personal injury of
any person, or for damages to or loss of risk of property, any environmental obligations, any
legal fees and any claims for damages of any nature whatsoever arising out of (i) a breach of
LACMTA's obligations under this AGREEMENT; or (ii) any act or omission of LACMTA
or its officers, agents, employees, contractors, or subcontractors in the use of CITY's STP-L
Funds and CITY's HIP Funds.
12. This AGREEMENT may be amended or modified only by mutual written consent of
LACMTA and CITY.
13. Any correspondence, communication, or contact concerning this AGREEMENT shall be
directed to the following:
CITY OF AZUSA
Robert Delgadillo, Director of Public Works/City Engineer
City of Azusa
213 E. Foothill Blvd.
Azusa, CA 91702
rdelgadillo@azusaca.gov
LACMTA
Michael Richmai
Senior Manager, Countywide Planning and Development
One Gateway Plaza (Mail Stop: 99-23-3)
Los Angeles, California 90012-2952
RichmaiM@metro.net
14. This AGREEMENT shall be interpreted and governed by the laws of the State of California.
15. This AGREEMENT constitutes the entire understanding between the parties with respect to
the subject matter herein.
Agreement Number 9200000000HIP2140
Exhibit A
AUTOMATED CLEARING HOUSE (ACH) PAYMENT AUTHORIZATION
Agreement Number 9200000000HIP2140
Exhibit A
AUTOMATED CLEARING HOUSE (ACH) PAYMENT AUTHORIZATION
Agreement Number 9200000000HIP2140
Exhibit A
AUTOMATED CLEARING HOUSE (ACH) PAYMENT AUTHORIZATION
Agreement Number 9200000000HIP2140
Exhibit B
STATEMENT OF WORK
Project Title: Street Improvements in the City of Azusa.
Arrow Highway Raised Median: The project will incorporate raised median islands with
doweled median curb, ADA compliant curb ramps, minor asphalt concrete paving to
address drainage, pavement resurfacing, landscape improvements, and signing & striping.
The improvements on Arrow Highway are from 500 feet west of Azusa Avenue to Citrus
Avenue.
Foothill Boulevard Pavement Rehabilitation: The project includes concrete
improvement, irrigation, landscape improvements, and signing & striping on Foothill
Boulevard from Orange Avenue to Alosta Avenue. Additional concrete improvements
on Alosta Avenue from Foothill Boulevard to Citrus Avenue are also part of this project.
Project Schedule
Arrow Highway Foothill Boulevard
Advertise November 2022 January 2023
Award Contract January 2023 March 2023
Start Construction February 2023 April 2023
Complete Construction June 2023 August 2023
Project Funding
Arrow Highway Foothill Boulevard TOTAL
LACMTA Funds* $940,000 $239,242 $1,179,242
Total Funding $940,000 $239,242 $1,179,242