TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
VIA: SERGIO GONZALEZ, CITY MANAGER
FROM: LEILA HASSEN, LIBRARY SERVICES MANAGER
DATE: JUNE 19, 2023
SUBJECT: APPROVAL OF FIRST AMENDMENT TO THE PROFESSIONAL SERVICES
AGREEMENT WITH KORN RANDOLPH, INC. FOR PROJECT
DEVELOPMENT AND MANAGEMENT SERVICES RELATED TO THE
LIBRARY OUTDOOR LEARNING SPACE PROJECT
BACKGROUND:
In March of 2022, the Azusa City Library was awarded a Targeted State Grant in the amount of
$500,000 from the California State Library toward the design and construction of an Outdoor
Learning Space. Grant funds were formally accepted by the Azusa City Council at their meeting of July
18, 2022. A Request for Qualifications for hardscape/landscape design services was then issued on July
19, 2022. Following conclusion of the bid process, interviews were conducted in September 2022 with
the bid awarded to Korn Randolph, Inc. considering the firm’s qualifications and scope of experience. On
November 3, 2022, the City entered into a Professional Services Agreement (PSA) with Korn Randolph,
Inc. for Background Review/Survey and Concept Design associated with the Library Outdoor Learning
Space Project for a fee of $38,030.
The City now desires to proceed with the second phase of project development by amending the scope of
the original agreement with Korn Randolph, Inc. to include the development of construction documents,
geotechnical testing, bid-process coordination, and construction management services through project
completion for a cost of $145,960.
RECOMMENDATIONS:
Staff recommends that the City Council take the following actions:
1) Approve a First Amendment to the Professional Services Agreement with Korn Randolph,
Inc. increasing total compensation in the amount of $145,960 and amending the scope to
include project development and construction management services; and
Approved
City Council
June 19, 2023
First Amendment to PSA with Korn Randolph, Inc.
June 19, 2023
Page 2
2) Authorize the City Manager to execute the Amendment, in substantial form, subject to
minor modifications acceptable to the City Attorney, on behalf of the City.
ANALYSIS:
The City has received a total of $500,000 in California State Library grant funding toward the
design and construction of this project, with the goal of supporting Library programs and services
for the Azusa community. The Project concept entails a flexible outdoor classroom space
measuring approximately 5,000 square feet that would be situated adjacent and connected to the
north-side of the Library. Highlights of the design include outdoor programmatic and event space,
a sustainable garden, reading nooks, an elevated deck for outdoor performances, and seating areas
with views of Veterans Freedom Park and the local mountains.
As this project is currently in the design phase, a comprehensive project budget estimate for
hard/soft costs is not yet available. Staff anticipate that additional funding beyond the initial grant
award will be necessary, with total project-related costs anticipated in the general range of
$950,000. The City will continue to pursue additional grant funding opportunities during this time,
and is in the process of identifying potential special fund dollars that may be applied toward this
project for specific elements such as energy-efficient lighting features, ADA enhancements, and
water-conservation features.
Once the consultant has concluded the project design development phase and preparation of
construction documents, Staff will return to Council with an estimated cost for construction prior
to initiating the bid process for construction services. A break-down of project next steps and
general timeline is provided below:
Anticipated Project Timeline:
• Design Development (6 Weeks)
• Construction Documents (16 Weeks) / Submit to Agency for review at 8 Weeks
• Plan Check / Permitting (TBD)
• Korn Randolph, Inc will provide Project Cost Estimate prior to the bid process
• Council Approval for Project Budget and Initiation of Bid Process
• Bid Process / Agency Review (8 Weeks)
• Council Award of Construction Contract
• Construction / Support (16 Weeks)
• Project Close-Out (14 Days)
• Post Construction Review (at 30, 60, 75, and 90 days)
FISCAL IMPACT:
There is no fiscal impact associated with the recommended action at this time. The subject action
increases compensation for this Professional Services Agreement by a total of $145,960 for the
amended scope of services. $500,000 in Targeted State Grant funding has been received by the
City, and consultant costs associated with this project shall be drawn down from this initial amount.
Staff anticipate additional funding will be necessary for construction costs/project completion, and
First Amendment to PSA with Korn Randolph, Inc.
June 19, 2023
Page 3
will return to Council at a future date with a comprehensive project budget estimate(s) following
the design development phase and preparation of construction documents. Staff will explore
alternative special revenue funding opportunities that may be applied toward this project, and will
return to Council for further direction. Upon Council acceptance of the First Amendment of the PSA,
Finance staff will amend the FY 23-24 budget to reflect these changes consistent with the grant
award amount. Fees for professional services will be charged to grant account 28-80-500-000-
6599.
Prepared by: Reviewed and Approved:
Leila Hassen Nico De Anda-Scaia
Library Services Manager Deputy City Manager
Fiscal Review by: Reviewed and Approved:
Talika M. Johnson Sergio Gonzalez
Director of Administrative Services City Manager
Attachments:
1) Original Korn Randolph PSA – Phase I (Signed 11/03/2022)
2) Proposed First Contract Amendment – Phase II
3) Amendment ‘Exhibit A’ - Revised Korn Randolph PSA / Scope of Services
4) Project Conceptual Design
Attachment 1
45635.01000\31368292.1 -1 -
CITY OF AZUSA
FIRST AMENDMENT TO
AGREEMENT FOR PROFESSIONAL SERVICES
1.PARTIES AND DATE.
This First Amendment to the Agreement for Professional Services (“First Amendment”) is
entered into on the 19th day of June 2023, by and between the City of Azusa (hereinafter referred
to as the “City”) and Korn Randolph, Inc. (hereinafter referred to as the “Consultant”). City and
Consultant are sometimes collectively referred to herein as the “Parties.”
2.RECITALS.
2.1 Agreement. The Parties entered into that certain Agreement for Professional
Services dated 11/09/2022 (“Agreement”).
2.2 First Amendment. The Parties now desire to amend the Agreement in order to
increase the total compensation of the Agreement by $145,960 in order to complete the Outdoor
Learning Center.
3.TERMS.
3.1 Scope of Services. The Agreement is hereby amended to include the scope of
services set forth in Exhibit “A,” attached hereto and incorporated herein by reference.
3.2 Compensation. Consultant shall receive compensation, including authorized
reimbursements, for all Services rendered under this First Amendment up to a not to exceed
amount of $145,960 at the rates set forth in Exhibit “A” attached hereto and incorporated herein
by reference.
3.3 Remaining Provisions of Agreement. Except as otherwise specifically set forth in
this First Amendment, the remaining provisions of the Agreement shall remain in full force and
effect.
Attachment 2
45635.01000\31368292.1 - 2 -
IN WITNESS WHEREOF, the parties have executed this First Amendment to Agreement
on this 19th day of June, 2023.
CITY OF AZUSA KORN RANDOLPH, INC.
By:
Sergio Gonzalez City Manager
By:
Amy Korn of Korn Randolph, Inc President
ATTEST:
By:
Jeffrey Lawrence Cornejo, Jr. City Clerk
APPROVED AS TO FORM:
By:
Best Best & Krieger LLP City Attorney
45635.01000\31368292. 1 B-3
EXHIBIT “A”
TO FIRST AMENDMENT TO
AGREEMENT FOR PROFESSIONAL SERVICES
SCOPE OF SERVICES
Per proposal attached.
609 EAST GREEN STREET PASADENA CA 91101 Page 1 of 7
Landscape Architectural Services for
Construction Phases
The Azusa Public Library Outdoor Learning Space
Client: City of Azusa
213 East Foothill Blvd.
Azusa, CA 91702
Date of Proposal: May 30, 2023 | Revised June 7, 2023
SCOPE OF SERVICES
SITE PROGRAM
A.The following phases are based on the approved Concept Design for the Azusa Library Outdoor
Learning Space as submitted on April 30, 2023.
DESIGN DEVELOPMENT - 6 WEEKS
A.Set up Construction Package Layout:
1.Design Development Background for Coordination with Sub Consultants.
2.Drawing to be set up in auto cad format
3.Issue backgrounds and drawings to sub-consultants.
4.Meet subconsultant team on-site to review the project scope.
5.Coordinate Site Utility Diagram.
6.Note: this phase kicks off work for sub-consultants that were not a part of the
Concept Phase. (MEP Engineers & Structural Engineers and the Construction Phase
Civil Engineer).
7.Meet Geotechnical Consultants on-site for Soil Testing.
8.Review Geo Technical Testing results and coordinate with the engineering team.
B.Present Design Development Drawings to Owner prior to issuing to sub-consultants.
CONSTRUCTION DOCUMENTS - 16 WEEKS
A.Construction Documents shall be based upon client approved Design Development
backgrounds.
B.Manage Documents for all Consultants, Korn Randolph will be the project lead.
Attachment 3
Azusa Library Outdoor Learning Space Construction Phases | REV June 7, 2023 Page 2 of 7
C. DELIVERABLES:
HARDSCAPE PLAN, DETAILS & SHEET SPECIFICATIONS
1. Hardscape Plan showing proposed hardscape flat work improvements.
a. Legend and layout.
2. Path of Travel Diagram for ADA Ingress/Egress.
3. Tree Protection Diagram
4. Construction Details.
a. Ingress Egress Gates
b. Manual Rolling/Staking Gates
c. Site Fence and Low Retaining Wall Detail
d. Sloped Pathways
e. Decorative Concrete Flatwork
f. Decomposed Granite
g. Stone Walls
h. Seat Boulders
i. Platform Deck
j. Bench Reading Nook Seating
k. Fountain Detail with Drainage.
l. String/Festoon Lighting
m. Locations of additional power supply
n. Landscape up-lights and accent lighting
o. Outdoor speaker locations
p. Furnishing Selections
q. Library Cabinet with chalk or dry erase board
5. Construction Specifications Sheet Format.
PLANTING PLAN, DETAILS & SHEET SPECIFICATIONS
6. Planting Plan describing the existing and proposed plantings.
a. Species types and Images for Owner.
b. Quantities
c. Locations
d. Special notes on suppliers as needed.
7. Planting Details
a. General Details and Site Specific details per site conditions.
8. Planting Specifications.
a. Soil Amendments.
IRRIGATION PLAN, DETAILS & SHEET SPECIFICATIONS
9. Irrigation Plan showing proposed irrigation improvements.
a. Field Walk to access existing conditions (completed).
b. Recommend portions of existing system be retained where viable.
c. Irrigation Plan and layout with product legend and equipment.
d. Model Water Efficient Landscape Ordinance
10. Irrigation Specifications.
Azusa Library Outdoor Learning Space Construction Phases | REV June 7, 2023 Page 3 of 7
LOW VOLTAGE LIGHTING CONCEPT PLAN & SPECIFICATIONS
11. Plan Detailing Locations and product cutsheets of selected fixtures.
SUB-CONSULTANTS
1. CIVIL ENGINEERING - Final Demolition, Erosion Control, Grading and Drainage Plans LID
Plans and details.
2. MEP ENGINEERING - Site Electrical and Safety Path of Travel Photometrics Lighting
3. STRUCTURAL ENGINEERING – All Hardscape elements over 36”.
D. Two (2) Meetings to review Construction Documents.
E. Submit Construction Drawings for Agency Review at 8 weeks 75% Complete Construction
Documents.
OPINION OF PROBABLE COSTS
A. Estimate Construction Costs based on Design Development Drawing Set.
B. Meet with Sub-contractors to review scope elements.
C. Prepare a spreadsheet for review.
D. Meet with the Client Team to discuss the estimate.
AGENCY REVIEW | BID PHASE - 8 WEEKS
E. Respond to City of Azusa Submittal Review
F. Bid Instructions
G. Pre-Bid Meeting and Bid Walk.
H. Bid clarifications and addendum.
I. Respond to Requests for Clarifications
J. Bid review and comment
CONSTRUCTION SUPPORT - 4 MONTH HOURLY ESTIMATE (Jan 15, 2024 – May 15, 2024)
A. Coordination with Owner, Contractor and Sub-contractors as required.
B. Review Contractor Shop Drawings, respond to RFI’s.
C. Plant Procurement
Azusa Library Outdoor Learning Space Construction Phases | REV June 7, 2023 Page 4 of 7
D. Review Mock-ups and Layouts.
E. Review the work of the contractors, report on their progress and adherence to design intent and
requirements of the construction documents.
F. Field Review Notes and Reports.
G. Post Construction Phase – Four Site Visits during the 90 Day Maintenance Period
1. Walk through at 30, 60 75 and 90 days.
H. Project Close-out.
1. Provide the City of Azusa with all necessary record files; AutoCad as well as PDF.
2. Record files will include all sub-consultants’ electronic files.
PROJECT FEES
FEES - KORN RANDOLPH
DESIGN DEVELOPMENT $ 16,500
CONSTRUCTION DOCUMENTS $ 54,310
OPINION OF PROBALE COSTS $ 6,500
AGENCY REVIEW | BID PHASE $ 3,500
CONSTRUCTION ADMINISTRATION *HOURLY $ 24,000
SUBTOTAL $104,810
FEES - BREEN ENGINEERING
DESIGN DEVELOPMENT $ 5,000
CONSTRUCTION DOCUMENTS $ 12,400
AGENCY REVIEW | PLAN CHECK $ 1,500
CONSTRUCTION ADMINISTRATION $ 2,500
STRUCTURAL ENGINEERING $ 8,500
ELECTRICAL ENGINEERING $ 4,000
SUBTOTAL $ 33,900
GEOTECHNICAL TESTING $ 6,000
**REIMBURSABLE EXPENSE ESTIMATE $ 1,250
GRAND TOTAL $145,960
Azusa Library Outdoor Learning Space Construction Phases | REV June 7, 2023 Page 5 of 7
BILLING
A. Fees will be invoiced monthly for completed work. Invoices are due within 60 days of
receipt.
B. *Korn Randolph will keep detailed records of time spent on tasks performed per this
scope of service, invoiced monthly per the Rate Schedule.
C. **Direct costs such as printing, travel over 50 miles, materials, sub-consultants and
on-wage expenses are considered reimbursable expenses and are billed at cost.
RATE SCHEDULE
A. Landscape Architect | Design Principal $ 215.00 | hr
B. Associate $ 175.00 | hr
C. Project Manager $ 130.00 | hr
D. Project Designer $ 95.00 | hr
E. Administration $ 55.00 | hr
TERMS & CONDITIONS
A. Korn Randolph, Inc. agrees to provide professional services in accordance with generally
accepted standards of the landscape architectural profession. Owner agrees to provide Korn
Randolph, Inc. with all information, surveys, locations of underground utilities, reports and
professional recommendations and any other related items requested by Korn Randolph, Inc. in
order to provide the professional services. Korn Randolph, Inc. shall be entitled to rely on the
accuracy of these plans, drawings and reports provided by the owner.
B. Korn Randolph, Inc. shall not be required to make exhaustive or continuous on-site inspections
to check the quality or quantity of the work being performed by contractors except for those
services expressly provided for in this agreement. Korn Randolph, Inc. shall neither have control
over or charge of, nor be responsible for, the construction means, methods, techniques,
sequences or procedures, or for safety precautions and programs in connection with the work.
C. Korn Randolph, Inc. shall not be responsible for the contractor’s failure to perform the work in
accordance with the requirements of the contract documents and shall not have control over or
charge of the contractor and shall not be responsible for acts or omissions of the Contractor,
subcontractors, or their agents or employees, or any other persons or entities performing
portions of the work.
Azusa Library Outdoor Learning Space Construction Phases | REV June 7, 2023 Page 6 of 7
D. Korn Randolph, Inc. has no control over the cost or availability of labor, equipment or materials,
or over market conditions or the contractor’s method of pricing. Korn Randolph, Inc.’s opinion
of probable construction costs are made on the basis of Korn Randolph, Inc.’s professional
judgment and experience. Korn Randolph, Inc. makes no warranty, express or implied, that the
bids or negotiated costs of the work will not vary from Korn Randolph, Inc.’s opinion of the
construction costs.
E. All drawings, specifications and other documents, including those in electronic form, prepared
by Korn Randolph, Inc. are instruments of service for use solely with respect to this project.
Korn Randolph, Inc. shall be deemed the authors and owners of the respective instruments of
service and shall retain all common law, statutory and other reserved rights, including
copyrights. Upon execution of this agreement, Korn Randolph, Inc. grants to owner a non-
exclusive license to reproduce Korn Randolph, Inc.’s instruments of service solely for the
purpose of constructing, using and maintaining the project, provided that the owner shall
comply with all obligations including prompt payment of all sums when due under this
agreement. Any termination of this agreement prior to the completion of the project shall
terminate this license.
F. Korn Randolph, Inc. and the owner hereby waive all consequential and incidental damages for
claims, disputes or other matters in question arising out of or relating to this agreement. This
mutual waiver is applicable without limitation to all consequential damages to either party’s
termination of this agreement.
G. No deduction shall be made from Korn Randolph, Inc.’s compensation on account of penalty,
liquidated damages or other sums withheld from payments to contractor or on account of the
cost of changes to the work.
H. In the event of a termination, suspension or abandonment of the project, Korn Randolph, Inc.
will be equitably compensated for all services performed to date and those services currently in
progress. Failure of the owner to make payments to Korn Randolph, Inc. in accordance with
those agreements shall be considered substantial non-performance and sufficient cause for
Korn Randolph, Inc. to either suspend or terminate services. Either Korn Randolph, Inc. or the
owner may terminate this agreement after giving no less than seven days written notice if the
other party substantially fails to perform in accordance with the terms of this agreement.
I. Neither party shall assign its rights or delegate its duties under this agreement without prior
written consent of the other.
J. This contract is entered into solely for the benefit of the owner and the Korn Randolph, Inc.
Neither owner nor Korn Randolph, Inc. intends to confer any rights under this agreement to any
other persons or beneficiaries.
K. In any dispute relating to the interpretation or enforcement of this agreement, the prevailing
party shall be entitled to costs and attorney’s fees.
L. Owner shall be responsible and pay for all required permits for the construction of the work.
Owner shall be responsible for all taxes, assessments and charges required by public agencies.
Azusa Library Outdoor Learning Space Construction Phases | REV June 7, 2023 Page 7 of 7
M. Client shall advise Korn Randolph, Inc. of any known or suspected contaminants at the project
site and shall be solely responsible for any remediation or clean-up costs. Owner shall also be
solely responsible for all subsurface soil conditions.
N. Waterproofing and damp proofing detailing and specifications, mechanical, electrical, plumbing,
civil and structural engineering, as well as fountain hydraulic and gas mechanics features are not
part of the scope of services.
O. Any rework or changes to the design program requested by the owner after the work has been
undertaken constitutes a change in the work and is not included in the fee and will be billed at a
hourly rate per the schedule of fees.
P. When requested by owner, additional services or meetings will be billed based on the schedule
of fees provided or on a fixed fee established when the additional services are authorized by the
client.
Q. Owner shall, to the full extent permitted by law, indemnify, defend and hold harmless Korn
Randolph, Inc., its officers, agents, employees and sub-consultants against any damages,
liabilities, or costs including reasonable attorney’s fees and defense costs to the extent caused
by owner’s negligent acts in connection with the project and the acts of the contractor,
subcontractors or consultants or anyone to whom the owner is legally liable.
R. Landscape architects are licensed by the State of California; Matt Randolph RLA 4400 & Amy
Korn RLA 6609
ACCEPTANCE
Upon acceptance of this proposal, please sign and return one copy of this agreement.
Signature Date
Print Name (For Client)
Partner, Korn Randolph, Inc. Date
THANK YOU
GARDEN ACCESS GATES
LIBRARY INGRESS/EGRESS
PUBLIC PATHWAY
READING NOOK - WOOD
1
2
5
6
8
9
10
11
12
EXISTING FLOSS SILK TREES
ACTIVITY TABLE
LOUNGE
MOVABLE FURNISHINGS
15
18
19
20
21
WOOD DECK
7
STAKING GATES - 16' OPEN TO PARK3
EXISTING LAWN
4
ACCENT LIGHTING
16
LIBRARY CABINET
17
WOOD BENCH AT DECK EDGE
ACCENT PAVING
GARDEN PLANTINGS
13
DECOMPOSED GRANITE
14
STONE FOUNTAIN
STONE GARDEN EDGING
4'8'0 16'
OUTDOOR LEARNING SPACE - CONCEPT DESIGNAZUSA PUBLIC LIBRARY - City of Azusa
729 N Dalton Ave, Azusa CA 91702
April 30, 2023
LANDSCAPE PLAN
STONE GARDEN & SEAT WALLS
PERIMETER FENCE
EXISTING PARKING LOT
22
25
26
27 EXISTING MURAL TO REMAIN
23
24
SITE TREES TO REMAIN
ACCESSIBLE PATH
ACCENT PLANTERS
6
7
26 6
1
1
3
3
2
7
20
21
22
17
13
11
18
7
5 5
8
9
12
11
14
16
16
12
15
23
WOOD STEPS
4
10
27
25
24
17
23
7
19
N
D
A
L
T
O
N
A
V
E
N
U
E
L I B R A R Y B U I L D I N G
V E T E R A N S F R E E D O M P A R K
28 LIBRARY WINDOWS - PRESERVE VIEWS
28
OUTDOOR LEARNING SPACE - CONCEPT DESIGNAZUSA PUBLIC LIBRARY - City of Azusa
729 N Dalton Ave, Azusa CA 91702
April 30, 2023
LANDSCAPE IMAGERY
616.92 BW
616.91 TW
FLUSH w/
BW
4.9%
4.9%
616.49 FS
616.47 FS
616.30 FS
616.41 FS
616.37 FS
2.5%
614.18 FS
4.9%
614.18 FS
4.
2
%
613.50 FS
615.50 FS
615.00 FS
614.50 FS
614.00 FS
613.50 FS
9.4%
2
.
0
%
614.18 FS 614.18 FS
614.18 FS
614.18 FS
613.50 FS
613.50 FS
612.57 BW
1.8%
PA
PA
PA
PA
PA
EL 613.50 FS
EL 615.00 FS
EL 615.50 FS
616.0
617.0
615.5
614.5
615.5
614.0
614.0
615.0
615.00 FS
61
4
61
5
61
6
EL 615.70 FS
615.0 WL
61
6
61
6
6
1
6
614
614
61
3
613.50 GB
EL 613.50 FS
613.1 TG
PA
PA
PA
PA
PA
PA
615.00 FS
617.5 617.0 617.0 616.0
616.5 TW
616.5 TW
616.41 FS
616.50 TW
PA
LAWN
LAWN
LAWN
LAWN
LAWN
LAWN
PA
4'8'0 16'
OUTDOOR LEARNING SPACE - CONCEPT DESIGNAZUSA PUBLIC LIBRARY - City of Azusa
729 N Dalton Ave, Azusa CA 91702
April 30, 2023
CONCEPT GRADING PLAN
N
D
A
L
T
O
N
A
V
E
N
U
E
L I B R A R Y B U I L D I N G
V E T E R A N S F R E E D O M P A R K
ABBREVIATIONS
CL CENTER LINE
EL ELEVATION PA PLANTER AREA
TW TOP OF WALL
TG TOP OF GRATE
BW BACK OF WALK FL FLOW LINE
WL WATERLINE
FS FINISHED SURFACE
EC EDGE OF CONCRETE GB GRADE BREAK
1
1 LOW IMPACT DEVELOPMENT INTERVENTION -
INFILTRATION TRENCH
LEGEND
3
2
2 AREA DRAIN
3 FOUNTAIN COPING
4 STONE GARDEN WALL
4
5
5 RAISED DECK
6 DECORATIVE PAVING
6
7 DECOMPOSED GRANITE SURFACE
7
7
6
OUTDOOR LEARNING SPACE - CONCEPT DESIGNAZUSA PUBLIC LIBRARY - City of Azusa
729 N Dalton Ave, Azusa CA 91702
April 30, 2023
PLANT PALETTE
MUHLENBERGIA RIGENS - DEER GRASS L
G
CEANOTHUS 'RAY HARTMAN HEDGEE
J LOMANDRA LONGIFOLIA - LIME TUFF N SALVIA LEUCANTHA 'SANTA BARBARA'
LONICERA JAPONICA - JAPANESE HONEYSUCKLE
F
K
ANIGOZANTHOS 'BUSH PEARL' - PINK KANGAROO PAWB
D CHILOPSIS LINEARIS - BURGUNDY DESERT WILLOW
O TECOMA X SMITHII - ORANGE BELLSCISTUS X PULVERULENTUS 'SUNSET' - MAGENTA ROCKROSE
ARBUTUS MARINA - DWARF STRAWBERRY TREE
C
A
LEONOTIS LEONURUS - LION'S TAILH
I PENSTEMON HETEROPHYLLUS - 'MARGARITA BOP'MLEUCADENDRON 'SAFARI SUNSET' - SAFARI CONEBUSH
A B C D
E F G H I
J K L M N O
GREVILLEA - 'MASON'S HYBRID GREVILLEA
ELYMUS CONDENSATUS - CANYON PRINCE WILD RYE