Loading...
HomeMy WebLinkAboutE-15 Staff Report - NOC ARC Asphalt ProjectCONSENT ITEM E-15 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL VIA: SERGIO GONZALEZ, CITY MANAGER FROM: LUCY DEMIRJIAN, SENIOR PROJECT MANAGER DATE: MARCH 18, 2024 SUBJECT: ACCEPTANCE OF PROJECT COMPLETION AND AUTHORIZATION TO FILE A NOTICE OF COMPLETION FOR THE AZUSA RESOURCE CENTER ASPHALT PROJECT BACKGROUND: On February 20, 2024, the City Council authorized the City Manager to execute contracts and purchase orders on behalf of the City for the completion of the Azusa Resource Center project under the declaration of a local emergency. A request for quotes was circulated and the project was awarded to Haitbrink Asphalt Paving, Inc. for the Azusa Resource Center Asphalt Project. The project was completed on March 8, 2024. The proposed actions will accept the improvements and authorize Staff to file a Notice of Completion for the project. RECOMMENDATIONS: Staff recommends the City Council take the following actions: 1)Accept the project improvements; and 2) Authorize Staff to file a Notice of Completion for the Azusa Resource Center Asphalt Project. ANALYSIS: The completed project required expedited paving of a portion of City-owned property located at 975 W. Foothill Blvd., for the interim housing project known as the Azusa Resource Center. The scope of work included paving of approximately 10,000 sf area at the northern end of the property. Approved City Council March 18, 2024 NOC for ARC Asphalt Project March 18, 2024 Page 2 FISCAL IMPACT: A contract for this project was awarded in the amount of in the amount of $98,700, which included a contingency for potential change orders. The project was completed on time and within budget. The construction project was funded by the American Recovery Plan Act (ARPA) State and Local Fiscal Recovery Funds (account #54-00-000-000-6625/11024A-6625). Prepared by: Fiscal Review by: Lucy Demirjian Talika M. Johnson Senior Project Manager Director of Administrative Services Reviewed and Approved by: Sergio Gonzalez City Manager Attachment: 1) Notice of Completion RECORDING REQUESTED BY AND WHEN RECORDED MAIL TO: NAME CITY OF AZUSA STREET ADDRESS 213 E. FOOTHILL BLVD CITY, STATE ZIP AZUSA, CA 91702 SPACE ABOVE THIS LINE FOR RECORDER’S USE NOTICE OF COMPLETION Notice pursuant to Civil Code Section 9204, must be filed within 15 days after completion. Notice is hereby given that: 1.The undersigned is owner or corporate officer of the owner of the interest or estate stated below in the property hereinafter described: 2.The full name of the owner is The City of Azusa 3.The full address of the owner is 213 E. Foothill Boulevard, Azusa, CA 91702 4.The nature of the interest or estate of the owner is: In fee. City of Azusa (IF OTHER THAN FEE, STRIKE “IN FEE” AND INSERT, FOR EXAMPLE , “PURCHASER UNDER CONTRACT OF PURCHASE”, OR “LESSEE” 5.The full names and full addresses of all persons, if any, who hold title with the undersigned as joint tenants or as tenants in common, are: NAMES ADDRESSES NONE 6.The full names and full addresses of the predecessors in interest of the undersigned, if the property was transferred subsequent to the commencement of the work or improvements herein referred to: NAMES ADDRESSES NONE 7.A work of improvement on the property hereinafter described was completed on March 8, 2024 . The work done was: Azusa Resource Center Asphalt Project 8.The name of the contractor, if any, for such work of improvement was: Haitbrink Asphalt Paving, Inc., 1480 Magnolia Ave., Corona, CA 92879 February 21, 2024 (IF NO CONTRACTOR FOR WORK OF IMPROVEMENT AS A WHOLE, INSERT “NONE”) (DATE OF CONTRACT) 9.The property on which said work of improvement was completed is in the City of Azusa, County of Los Angeles, California and as described as follows: Project area bounded by Industrial St. on the north, Foothill Blvd on the south, Miller Ave. on the west; and within the area bounded by Georgia Ave. on the east 10.The street address of said property is 975 W. Foothill Boulevard, Azusa CA. 91702 (IF NO STREET ADDRESS HAS BEEN OFFICIALLY ASSIGNED, INSERT “NONE”) Dated: Robert Gonzales, Mayor (SIGNATURE OF OWNER OR CORPORATE OFFICER OF OWNER NAMED IN PARAGRAPH 2 OR HIS AGENT) I, the undersigned, say: I am the person who signed the foregoing notice of completion. I have read said notice of completion and know its contents, and the facts stated therein are true of my own knowledge. I declare under penalty of perjury that the foregoing is true and correct. Executed on at (DATE) (CITY, COUNTY, & STATE) (SIGNATURE) Attachment 1